MEP Project Execution Methodology: Material & Drawing Submission & Approval
MEP Project Execution Methodology: Material & Drawing Submission & Approval
Ductwork Installation:
Ductwork will be delivered from the fabrication area when required in a coordinated manner as follow:
Mark out support locations at duct work based on working drawings.
Drill holes in concrete element. Fix anchors arid drop rods.
Connect duct pieces in appropriate lengths arid widths between support rods.
Lift and raise ducts from floor to support level manually for small sections or mechanically for larger sections.
Fix angle supports and nuts to support dust at correct level.
Correct more pieces in appropriate lengths and install at desired level
Connect adjacent duct sections by slip joints or angle flanges as specified with sealant or gasket as appropriate.
Fix necessary accessories such as VCD’S. FDS. VAV’S access doors, veins and fans
Carry out pressure test to check for leakage monitor with suitable instrument,
After approval of coordinated reflected full ceiling drawings commence installation of flexible ducts and air terminal devices.
DUCTWORK INSULATION
After ducts have been satisfactorily tested for leakage, insulation work will be carried out.
Clean the external surface of the duct to remove grease, moisture or deleterious material.
Apply specified adhesive in surface of ducts at the manufacturers recommended application rate.
Fix self-adhesive stickpins on spot welded pins at the specified intervals
Cut and prepare insulation board pieces in required sizes according to manufacturer’s recommendations to prevent
compression of insulation to less than 75% of its nominal thickness. Fix the same on the duct surface with the help of stickpins
and previously applied adhesive, ensuring that the edges are straight and closely butted
Seal the joints and seams with vapor barrier mastic whore required as per the specifications
Apply the first coat of vapor barrier wrap with canvass/glass cloth and then apply second coat of vapor barrier.
Apply Insulation continuously through walls and partitions except fire rated walls and partitions
For fire rated wall and partition penetrations, terminate insulation at fire damper sleeves.
1
PLUMBING
Adequate traps will be provided with water seal. Standard method of construction as specified in contract documents will be
followed, Special care will be taken for safely aspect during execution.
During installation and handing pipe and things will be closed by arid caps to avoid the ingress of dust and dirt.
Plastic pipes will be stored in a covered area to avoid deterioration due to exposure to UV sunlight.
Installation levels will be taken as those defined in the drawings and specifications of the construction contract.
A check will be made with the authority for their relevant level system arid benchmark to ensure coordination with the
discharge drainage.
Buried pipe work will be carried in coordination with the external civil works.
A review of all the contract drawings will be made to ensure proper slopes are specified.
External installation connections to municipal drainage department will be offered tor inspection by the relevant authority.
Adequate clean out and traps will be provided unless specified elsewhere in the contract.
Prior to delivery and installation of sanitary ware a trial mock up installation will be prepared and offered for review and
approval by the consultant.
2
ELECTRICAL
Electrical Activities
Lay underground ducts or sleeves.
Surface conduit.
Install MDB’s
Testing
The installation of electrical equipment can be briefly summarized as under to be followed by electrical engineering team:
Underground sleeves for electrical services will be commenced during the earthwork and ground preparations.
Concealed conduits, sleeves/ducts etc. in the slabs and walls will be installed during the slab concreting and wall construction
i.e. block work.
Cable support systems which includes the cable trays, trunking etc. installation will commence after the slabs are ready and in
coordination with the other services i.e. mechanical, Plumbing and Fire Fighting.
DB’s SMDBs and MDBs installation will commence after the designated walls and electrical rooms are complete in almost air
respect of dell activities.
Circuit wiring and cabling work is carried out after the completion of structural and block work including the plastering.
Installation of lighting fixtures will be after completion of the painting activity.
External works including earthing lightning protection and external lightning will commence with the preparation of land fertile
landscaping and roadwork.
3
All the above works are to be inspected by the concerned authorities immediately after completion of each activity to ensure
that all the specifications are compiled during the installation and the installation is carried out as per the manufacturers’
guidelines.
Testing will be carried out progressively after each activity. Final testing will be carried out prior to handover.
Incoming power supply by the local power authority (the service connection) will be given when the latter completes the
associated works.