SARVEANTHARAN A/L NAGARAJAN (RC21316)

Question 1

a)

ESD=D17 LSD=D19
ESD=D14 LSD=D14
EFD= D20 LFD=D22
EFD= D16 LFD=D16
SLACK TIME = 2 ESD=D21 LSD=D26
SLACK TIME = 0
EFD= D22 LFD=D27
ESD=D2 LSD=D4 ESD=D9 LSD=D9
SLACK TIME = 5
EFD= D4 LFD=D4 EFD= D13 LFD=D13

SLACK TIME = 0 SLACK TIME = 0

ESD=D28 LSD=D28

EFD= D33 LFD=D33

SLACK TIME = 0

ESD=D0 LSD=D0 ESD=D5 LSD=D5 ESD=D23 LSD=D23


EFD= D1 LFD=D1 EFD= D8 LFD=D8 EFD= D27 LFD=D27
ESD=D17 LSD=D17
SLACK TIME = 0 SLACK TIME = 0 SLACK TIME = 0
ESD=D9 LSD=D10
EFD= D22 LFD=D22
EFD= D12 LFD=D13
SLACK TIME = 0
SLACK TIME = 1
b)
The MyNasi ordering system now has a completion time of 47 days. This is since the
previous length time for unit test, integration test, and system test was two days. Because
the new duration time is 5 days, the existing completion time of 44 days must be increased
by 3 days. The revised completion date will be in 47 days.

c)
SDE Task From Table 1 Proposed Tool Purpose Of Tool
Requirement Requirements Ninja Mock Used to generate digital
Elicitation sketches of your idea or
concept for an
application or website.
Planning Software Project Gantt Project Used to create schedule,
Planning project plans, manage
resources and keep track
of time.
Design Design The Microsoft Visio Can easily drag and drop
Requirements by any shape and search for
Functional Process suitable shapes.
Testing Unit Test, Integration Tricentis Neoload Designed for testing web
test & System Test application, it has
expanded to include
other test related
functions.
Coding Implements the system IntelliJ Idea It contains completion
design using PHP, tool, compilers and other
bootstrap. Coding on features to facilitate the
Sublime text. software development
process