Professional Documents
Culture Documents
Work Program Kamwokya
Work Program Kamwokya
Work Program Kamwokya
3 Mobilization and establishment of site 7 days Tue 2/1/22 Mon 2/7/22 Foreman 1,Foreman 2,Site Engineer
camp
10 Construction of manholes 10 days Thu 2/24/22Sat 3/5/22 9 Concrete Mixer,Foreman 1,Poker,Site Engineer
15 Rockfilling using hardcore 7 days Tue 3/8/22 Mon 3/14/22 14 Foreman 1,Site Engineer,surveyor
16 Casting channel base with BRC 7 days Tue 3/15/22Mon 3/21/22 15 Concrete Mixer,Foreman 1,Poker,Site Engineer
23 Installation of 900mm culverts on 7 days Wed Tue 4/19/22 22 Foreman 1,Site Engineer
class B bedding and casting access 4/13/22
culvert encasing
24 Construction of manholes 15 days Wed 4/20/22Wed 5/4/22 23 Concrete Mixer,Foreman 1,Poker,Site Engineer
26 Open channel section (0+520 - 0+670) 87 days Thu 5/5/22 Sat 7/30/22
27 Demolition of existing stone pitching 4 days Thu 5/5/22 Sun 5/8/22 24 Foreman 1
29 Rockfilling using hardcore 4 days Fri 5/13/22 Mon 5/16/22 28 Dump trucks,Foreman 1,Site Engineer
30 Casting channel base with BRC 14 days Tue 5/17/22Mon 5/30/22 29 Concrete Mixer,Dump trucks,Poker,Site Engineer
34 Demolition of existing slab and stone 1 day Wed Wed 6/1/22 30 Foreman 1
pitching 6/1/22
35 Excavation 4 days Wed 6/1/22 Sat 6/4/22 30 Dump trucks,Foreman 1,Site Engineer,surveyor
36 Casting concrete blinding 1 day Sun 6/5/22 Sun 6/5/22 35 Concrete Mixer,Dump trucks,Foreman 1,Poker,Site Engineer
37 Steel fabrication 5 days Mon 6/6/22 Fri 6/10/22 36 Foreman 1,Site Engineer
39 Casting R.C concrete 29 days Fri 6/10/22 Sat 7/9/22 38SS Concrete Mixer,Foreman 1,Poker,Site Engineer
44 Rockfilling using hardcore 5 days Tue 6/7/22 Wed 6/29/22 43SS Dump trucks,Foreman 1,Site Engineer
45 Casting channel base with BRC 24 days Tue 6/7/22 Thu 6/30/22 44SS Concrete Mixer,Dump trucks,Foreman 1,Poker,Site Engineer
46 Construction of grouted stone pitching 27 days Wed Mon 44 Foreman 2,Site Engineer
6/29/22 7/25/22
Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Projec
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
DRAINAGE IMPROVEMENT WORKS ON KAMWOKYA PHASE 1 (577M) IN CENTRAL DIVISION UNDER THE FRAMEWORK CONTRACT FOR ROUTINE ROAD ELEMENT REPAIRS IN KAMPALA CAPITAL CITY
ID Task Task Name Duration Start Finish Predecessors
Jan 30, '22Feb 6, '22 Feb 13, '22 Feb 20, '22 Feb 27, '22 Mar 6, '22 Mar 13, '22 Mar 20, '22 Mar 27, '22 Apr 3, '22 Apr 10, '22 Apr 17, '22 Apr 24, '22 May 1, '22 May 8, '22 May 15, '22 May 22, '22 May 29, '22 Jun 5, '22 Jun 12, '22 Jun 19, '22 Jun 26, '22 Jul 3, '22 Jul 10, '22 Jul 17, '22 Jul 24, '22 Jul 31, '22 Aug 7, '22 Aug 14, '22 Aug 21, '22 Aug 28, '22 Sep 4, '22 Sep 11, '22 Sep 18, '22 Sep 25, '22 Oct 2, '22
Mode SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S
48 Box culvert (0+520) 19 days Sun 7/10/22Thu 7/28/22
50 Rockfilling & casting concrete blinding 1 day Tue 7/12/22Tue 7/12/22 49 Dump trucks,Foreman 1,Site Engineer,surveyor
51 Bending and fixing steel reinforcements2 days Wed 7/13/22Thu 7/14/22 50 Dump trucks,Foreman 1,Site Engineer
52 Casting Box culvert Base 1 day Fri 7/15/22 Fri 7/15/22 51 Concrete Mixer,Foreman 1,Poker,Site Engineer
53 Shuttering & Casting Box culvert walls 4 days Sat 7/16/22 Tue 7/19/22 52 Foreman 1,Site Engineer
54 Shuttering work and casting Deck 2 days Wed 7/20/22Thu 7/21/22 53 Foreman 1,Site Engineer
55 Casting R.C concrete for Wing walls 5 days Fri 7/22/22 Tue 7/26/22 54 Concrete Mixer,Foreman 1,Poker,Site Engineer
and Headwall
56 Backfilling 2 days Wed 7/27/22Thu 7/28/22 55 Dump trucks,Foreman 1,Jumping compactor,Pedestrian roller
60 Rockfilling using hardcore 5 days Fri 8/5/22 Tue 8/9/22 59 Dump trucks,Foreman 1,Site Engineer
61 Casting channel base with BRC 7 days Wed 8/10/22Tue 8/16/22 60 Concrete Mixer,Dump trucks,Foreman 1,Poker,Site Engineer
62 Construction of grouted stone pitching 6 days Wed 8/17/22Mon 8/22/22 61 Foreman 2,Site Engineer
63 Backfilling 2 days Tue 8/23/22Wed 8/24/22 62 Foreman 1,Jumping compactor,Pedestrian roller,Site Engineer
66 Rockfilling using hardcore 2 days Fri 8/19/22 Sat 8/20/2265SS+2 days Dump trucks,Foreman 1,Site Engineer
67 Casting Channel base with BRC 3 days Sun 8/21/22Tue 8/23/22 66 Concrete Mixer,Dump trucks,Foreman 1,Site Engineer,Poker
68 Constructing grouted stone pitching 5 days Wed 8/24/22Sun 8/28/22 67 Foreman 2,Site Engineer
69 Shuttering and fixing steel for access 8 days Wed Wed 66FS+1 Foreman 1,Site Engineer
slabs 8/24/22 8/31/22 day
70 Casting R.C.concrete for access slabs 9 days Fri 8/26/22 Sat 9/3/22 67SS+2 days Concrete Mixer,Dump trucks,Foreman 1,Poker,Site Engineer
71 Casting concrete coping for stone 7 days Mon Sun 9/4/22 68 Concrete Mixer,Foreman 1
pitching 8/29/22
73 Site clearing 5 days Mon 9/5/22 Fri 9/9/22 71 Dump trucks,Foreman 1,Foreman 2,Site Engineer
Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Projec
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2