DRAINAGE IMPROVEMENT WORKS ON KAMWOKYA PHASE 1 (577M) IN CENTRAL DIVISION UNDER THE FRAMEWORK CONTRACT FOR ROUTINE ROAD

ELEMENT REPAIRS IN KAMPALA CAPITAL CITY


ID Task Task Name Duration Start Finish Predecessors
Jan 30, '22 Feb 6, '22 Feb 13, '22 Feb 20, '22 Feb 27, '22 Mar 6, '22 Mar 13, '22 Mar 20, '22 Mar 27, '22 Apr 3, '22 Apr 10, '22 Apr 17, '22 Apr 24, '22 May 1, '22 May 8, '22 May 15, '22 May 22, '22 May 29, '22 Jun 5, '22 Jun 12, '22 Jun 19, '22 Jun 26, '22 Jul 3, '22 Jul 10, '22 Jul 17, '22 Jul 24, '22 Jul 31, '22 Aug 7, '22 Aug 14, '22 Aug 21, '22 Aug 28, '22 Sep 4, '22 Sep 11, '22 Sep 18, '22 Sep 25, '22 Oct 2, '22
Mode SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S
1 DRAINAGE IMPROVEMENT WORKS ON 222 days Tue 2/1/22 Sat 9/10/22
KAMWOKYA PHASE 1 (577M) IN CENTRAL
DIVISION UNDER THE FRAMEWORK
CONTRACT FOR THE ROUTINE ROAD
ELEMENT REPAIRS USING PORTLAND
CEMENT BASED PRODUCTS AND
METHODS BETWEEN KAMPALA CAPITAL
CITY AUTHORITY AND M/S LINA
2 CONSTRCUTION
Preliminaries L 8 days Tue 2/1/22 Tue 2/8/22

3 Mobilization and establishment of site 7 days Tue 2/1/22 Mon 2/7/22 Foreman 1,Foreman 2,Site Engineer
camp

4 setting out 1 day Tue 2/8/22 Tue 2/8/22 3 surveyor

5 900mm culvert section (0+940 - 0+895) 25 days Wed 2/9/22Sat 3/5/22

6 Demolition of existing stone pitching 2 days Wed Thu 2/10/22 4 Foreman 1


2/9/22

7 Demolition of access slabs 3 days Wed 2/9/22 Fri 2/11/22 4 Foreman 1

8 Excavation 5 days Sat 2/12/22 Wed 2/16/22 7 Foreman 1,Site Engineer,surveyor

9 Installation of 900mm culverts on 7 days Thu Wed 8 Foreman 1,Site Engineer


class B bedding 2/17/22 2/23/22

10 Construction of manholes 10 days Thu 2/24/22Sat 3/5/22 9 Concrete Mixer,Foreman 1,Poker,Site Engineer

11 Backfilling 3 days Thu 2/24/22Sat 2/26/22 9 Foreman 1,Jumping compactor,Pedestrian roller

12 Open channel section (0+845 - 0+900) 49 days Thu 2/24/22Wed 4/13/22

13 Demolition of existing stone pitching 5 days Thu 2/24/22Mon 2/28/22 9 Foreman 1

14 Excavation 7 days Tue 3/1/22 Mon 3/7/22 13 Foreman 1

15 Rockfilling using hardcore 7 days Tue 3/8/22 Mon 3/14/22 14 Foreman 1,Site Engineer,surveyor

16 Casting channel base with BRC 7 days Tue 3/15/22Mon 3/21/22 15 Concrete Mixer,Foreman 1,Poker,Site Engineer

17 Construction of grouted stone pitching 20 days Tue 3/22/22Sun 4/10/22 16 Foreman 2

18 Backfilling 3 days Mon 4/11/22Wed 4/13/22 17 Foreman 1,Jumping compactor,Pedestrian roller

19 1200mm culvert section (0+780 - 0+845) 44 days Tue 3/22/22Wed 5/4/22

20 Demolition os existing stone pitching 10 days Tue 3/22/22Thu 3/31/22 16 Foreman 1

21 Demolition of access slabs 3 days Tue 3/22/22Thu 3/24/22 16 Foreman 1

22 Excavation 12 days Fri 4/1/22 Tue 4/12/22 20 Foreman 1,Site Engineer,surveyor

23 Installation of 900mm culverts on 7 days Wed Tue 4/19/22 22 Foreman 1,Site Engineer
class B bedding and casting access 4/13/22
culvert encasing

24 Construction of manholes 15 days Wed 4/20/22Wed 5/4/22 23 Concrete Mixer,Foreman 1,Poker,Site Engineer

25 Backfilling 4 days Wed 4/20/22Sat 4/23/22 23 Foreman 1,Jumping compactor,Pedestrian roller

26 Open channel section (0+520 - 0+670) 87 days Thu 5/5/22 Sat 7/30/22

27 Demolition of existing stone pitching 4 days Thu 5/5/22 Sun 5/8/22 24 Foreman 1

28 Excavation 4 days Mon 5/9/22 Thu 5/12/22 27 Foreman 1,Site Engineer,surveyor

29 Rockfilling using hardcore 4 days Fri 5/13/22 Mon 5/16/22 28 Dump trucks,Foreman 1,Site Engineer

30 Casting channel base with BRC 14 days Tue 5/17/22Mon 5/30/22 29 Concrete Mixer,Dump trucks,Poker,Site Engineer

31 Construction of grouted stone pitching 62 days Mon 5/23/22Tue 7/26/22 30 Foreman 2

32 Backfilling 4 days Wed 7/27/22Sat 7/30/22 31 Foreman 1,Jumping compactor,Pedestrian roller

33 Casting reinforced concrete lining open 61 days Wed Sun 7/31/22


section btn ch(0+670 -0+650) 6/1/22

34 Demolition of existing slab and stone 1 day Wed Wed 6/1/22 30 Foreman 1
pitching 6/1/22

35 Excavation 4 days Wed 6/1/22 Sat 6/4/22 30 Dump trucks,Foreman 1,Site Engineer,surveyor

36 Casting concrete blinding 1 day Sun 6/5/22 Sun 6/5/22 35 Concrete Mixer,Dump trucks,Foreman 1,Poker,Site Engineer

37 Steel fabrication 5 days Mon 6/6/22 Fri 6/10/22 36 Foreman 1,Site Engineer

38 Shuttering works 28 days Fri 6/10/22 Thu 7/7/22 37 Foreman 1

39 Casting R.C concrete 29 days Fri 6/10/22 Sat 7/9/22 38SS Concrete Mixer,Foreman 1,Poker,Site Engineer

40 Backfilling 1 day Sun 7/31/22Sun 7/31/22 32 Foreman 1,Jumping compactor,Pedestrian roller

41 open channel section (0+650 - 0+520) 51 days Mon Tue 7/26/22


6/6/22

42 Demolition of existing stone pitching 22 days Mon Tue 6/28/22 37 Foreman 1


6/6/22

43 Excavation 23 days Mon 6/6/22 Tue 6/28/22 42SS Dump trucks,Foreman 1

44 Rockfilling using hardcore 5 days Tue 6/7/22 Wed 6/29/22 43SS Dump trucks,Foreman 1,Site Engineer

45 Casting channel base with BRC 24 days Tue 6/7/22 Thu 6/30/22 44SS Concrete Mixer,Dump trucks,Foreman 1,Poker,Site Engineer

46 Construction of grouted stone pitching 27 days Wed Mon 44 Foreman 2,Site Engineer
6/29/22 7/25/22

47 Backfilling 1 day Tue 7/26/22Tue 7/26/22 46 Foreman 1,Jumping compactor,Pedestrian roller

Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Projec
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 1
DRAINAGE IMPROVEMENT WORKS ON KAMWOKYA PHASE 1 (577M) IN CENTRAL DIVISION UNDER THE FRAMEWORK CONTRACT FOR ROUTINE ROAD ELEMENT REPAIRS IN KAMPALA CAPITAL CITY
ID Task Task Name Duration Start Finish Predecessors
Jan 30, '22Feb 6, '22 Feb 13, '22 Feb 20, '22 Feb 27, '22 Mar 6, '22 Mar 13, '22 Mar 20, '22 Mar 27, '22 Apr 3, '22 Apr 10, '22 Apr 17, '22 Apr 24, '22 May 1, '22 May 8, '22 May 15, '22 May 22, '22 May 29, '22 Jun 5, '22 Jun 12, '22 Jun 19, '22 Jun 26, '22 Jul 3, '22 Jul 10, '22 Jul 17, '22 Jul 24, '22 Jul 31, '22 Aug 7, '22 Aug 14, '22 Aug 21, '22 Aug 28, '22 Sep 4, '22 Sep 11, '22 Sep 18, '22 Sep 25, '22 Oct 2, '22
Mode SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S
48 Box culvert (0+520) 19 days Sun 7/10/22Thu 7/28/22

49 Excavation and demolition of existing 3 days Sun Tue 7/12/22 39 Foreman 1


concrete 7/10/22

50 Rockfilling & casting concrete blinding 1 day Tue 7/12/22Tue 7/12/22 49 Dump trucks,Foreman 1,Site Engineer,surveyor

51 Bending and fixing steel reinforcements2 days Wed 7/13/22Thu 7/14/22 50 Dump trucks,Foreman 1,Site Engineer

52 Casting Box culvert Base 1 day Fri 7/15/22 Fri 7/15/22 51 Concrete Mixer,Foreman 1,Poker,Site Engineer

53 Shuttering & Casting Box culvert walls 4 days Sat 7/16/22 Tue 7/19/22 52 Foreman 1,Site Engineer

54 Shuttering work and casting Deck 2 days Wed 7/20/22Thu 7/21/22 53 Foreman 1,Site Engineer

55 Casting R.C concrete for Wing walls 5 days Fri 7/22/22 Tue 7/26/22 54 Concrete Mixer,Foreman 1,Poker,Site Engineer
and Headwall

56 Backfilling 2 days Wed 7/27/22Thu 7/28/22 55 Dump trucks,Foreman 1,Jumping compactor,Pedestrian roller

57 Open channel section (0+370 - 0+520) 29 days Wed 7/27/22


Wed 8/24/22

58 Demolition of existing stone pitching 4 days Wed 7/27/22Sat 7/30/22 55 Foreman 1

59 Excavation 5 days Sun 7/31/22Thu 8/4/22 58 Dump trucks,Foreman 1,Site Engineer,surveyor

60 Rockfilling using hardcore 5 days Fri 8/5/22 Tue 8/9/22 59 Dump trucks,Foreman 1,Site Engineer

61 Casting channel base with BRC 7 days Wed 8/10/22Tue 8/16/22 60 Concrete Mixer,Dump trucks,Foreman 1,Poker,Site Engineer

62 Construction of grouted stone pitching 6 days Wed 8/17/22Mon 8/22/22 61 Foreman 2,Site Engineer

63 Backfilling 2 days Tue 8/23/22Wed 8/24/22 62 Foreman 1,Jumping compactor,Pedestrian roller,Site Engineer

64 Tributary and Acces slab works 19 days Wed 8/17/22


Sun 9/4/22

65 Excavation 4 days Wed 8/17/22Sat 8/20/22 61 Foreman 1,Site Engineer,surveyor

66 Rockfilling using hardcore 2 days Fri 8/19/22 Sat 8/20/2265SS+2 days Dump trucks,Foreman 1,Site Engineer

67 Casting Channel base with BRC 3 days Sun 8/21/22Tue 8/23/22 66 Concrete Mixer,Dump trucks,Foreman 1,Site Engineer,Poker

68 Constructing grouted stone pitching 5 days Wed 8/24/22Sun 8/28/22 67 Foreman 2,Site Engineer

69 Shuttering and fixing steel for access 8 days Wed Wed 66FS+1 Foreman 1,Site Engineer
slabs 8/24/22 8/31/22 day

70 Casting R.C.concrete for access slabs 9 days Fri 8/26/22 Sat 9/3/22 67SS+2 days Concrete Mixer,Dump trucks,Foreman 1,Poker,Site Engineer

71 Casting concrete coping for stone 7 days Mon Sun 9/4/22 68 Concrete Mixer,Foreman 1
pitching 8/29/22

72 Site clearing and handover 6 days Mon 9/5/22Sat 9/10/22

73 Site clearing 5 days Mon 9/5/22 Fri 9/9/22 71 Dump trucks,Foreman 1,Foreman 2,Site Engineer

74 Site handover 1 day Sat 9/10/22 Sat 9/10/22 73 Site Engineer

Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Projec
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 2

You might also like