http:\\www.vsl-intl.com I S S U E O N E 2 0 0 0

Australia / South East North East Central East Western Europe,


Pacific territories Asia Asia Europe and Africa and
Middle East Latin America
REGIONAL OFFICE REGIONAL OFFICE REGIONAL OFFICE
VSL Prestressing (Aust.) Pty. Ltd. VSL Singapore Pte. Ltd. VSL North East Asia
6 Pioneer Avenue 75 Bukit Timah Road 3/F Stelux House REGIONAL OFFICE REGIONAL OFFICE
THORNLEIGH, NSW 2120 04-08 Boon Siew Building 698 Prince Edward Road East VSL (Switzerland) Ltd L’Odyssée - Bât. A
AUSTRALIA Singapore 229833 San Po Kong / Kowloon Bernstrasse 9 2-12 Chemin des Femmes
Phone: +61 - 2 - 9484 59 44 SINGAPORE HONG KONG Lyssach - CH 3421 91886 MASSY Cedex
Fax: +61 - 2 - 9875 38 94 Phone: +65 336 29 23 Phone: +852 - 2590 22 22 SWITZERLAND FRANCE
Fax: +65 337 64 61 Fax: +852 - 2590 95 93 Phone: +41 - 34- 447 99 11 Phone: +33 - 1 - 69 19 43 00
AUSTRALIA - Queensland Fax: +41 - 34- 447 99 65 Fax: +33 - 1 - 69 19 43 01
VSL Prestressing (Aust.) Pty. Ltd. BRUNEI HONG KONG
GEEBUNG VSL Systems (B) Sdn. Bhd. VSL Hong Kong Ltd. AUSTRIA ARGENTINA
Phone: +61 - 7 - 3265 64 00 BRUNEI DARUSSALAM San Po Kong / Kowloon Universale GSB VSL Sistemas Especiales de
Fax: +61 - 7 - 3265 75 34 Phone: +673 - 2 - 380 153 Phone: +852 - 2590 22 88 VIENNA Construcción Argentina SA
- 381 827 Fax: +852 - 2590 02 90 Phone: +43 - 1 - 878 170 BUENOS AIRES
AUSTRALIA - New South Fax: +673 - 2 - 381 954 Fax: +43 - 1 - 878 17 782 Phone: +54 - 11 - 4326 - 06 09
Wales JAPAN Fax: +54 - 11 - 4326 - 26 50
VSL Prestressing (Aust.) Pty. Ltd. INDIA VSL Japan Corporation CZECH REPUBLIC
THORNLEIGH VSL India Private Ltd. TOKYO VSL Systemy (CZ) s. r. o. BELGIUM
Phone: +61 - 2 - 9484 59 44 CHENNAI Phone: +81 - 3 - 3346 - 8913 PRAGUE NV Procedes VSL SA
Fax: +61 - 2 - 9875 38 94 Phone: +91-44 859 2538 / 39 Fax: +81 - 3 - 3345 - 9153 Phone: +420 - 2 - 67 07 24 20 BERCHEM
Fax: +91-44 859 2537 Fax: +420 - 2 - 67 07 24 06 Phone: +32 3 230 36 34
AUSTRALIA - Southern KOREA Fax: +32 3 230 89 65
Division INDONESIA VSL Korea Co. Ltd. GERMANY
VSL Prestressing (Aust.) Pty. Ltd. PT VSL Indonesia SEOUL VSL Systems GmbH CHILE
NOBLE PARK JAKARTA Phone: +82 - 2 - 553 8200 BERLIN VSL Sistemas Especiales de
Phone: +61 - 3 - 9795 03 66 Phone: +62 - 21 - 570 07 86 Fax: +82 - 2 - 553 8255 Phone: +49 30 53 006-0 Construcción SA
Fax: +61 - 3 - 9795 05 47 Fax: +62 - 21 - 573 12 17 Fax: +49 30 53 006-37 SANTIAGO
MAINLAND CHINA Phone: +56 - 2 - 233 10 81
GUAM MALAYSIA VSL Engineering Corp., PRC POLAND Fax: +56 - 2 - 233 67 39
Structural Technologies Inc. VSL Engineers (M) Sdn. Bhd. Anhui Province, HEIFEI VSL Polska Sp. z o.o.
TUMON KUALA LUMPUR Phone: +86 - 551 - 557 6008 WARSAW GREAT BRITAIN
Phone: +1 - 671- 646 8010 Phone: +603 - 242 47 42 Fax: +86 - 551 - 557 6018 Phone: +48-22 817 84 22 VSL Systems (UK) Ltd
Fax: +1 - 671- 646 8060 Fax: +603 - 242 93 97 Fax: +48-22 817 83 59 CAMBRIDGESHIRE
PHILIPPINES Phone: +44 - 1 - 480 860 990
SINGAPORE VSL Philippines Inc. SWITZERLAND Fax: +44 - 1 - 480 861 092
VSL Singapore Pte. Ltd. MANDALUYONG CITY VSL (Switzerland) Ltd.
SINGAPORE Phone: +632 638 76 90 LYSSACH GREECE
Phone: +65 - 336 29 23 Fax: +632 638 76 91 Phone: +41 - 34 - 447 99 11 VSL Systems A/E
North America Fax: +65 - 337 64 61 Fax: +41 - 34 - 445 43 22 ATHENS
TAIWAN Phone: +30 - 1 - 363 84 53
THAILAND VSL Taiwan Ltd VSL (Suisse) SA. Fax: +30 - 1 - 360 95 43
VStructural Llc. PENTHAZ
Regional Office VSL (Thailand) Co. Ltd. TAIPEI
BANGKOK Phone: +886 - 2 - 2759 6819 Phone: +41 - 21 - 862 80 00 MEXICO
BALTIMORE, MD Fax: +41 - 21 - 862 80 02 VSL Corporation Mexico S.A
Phone: +1 - 410 - 247 - 1016 Phone: +66 - 2 - 237 32 88/89/90 Fax: +886 - 2 - 2759 6821
Fax: +66 - 2 - 238 24 48 de C.V
Fax: +1 - 410 - 247 - 1136 UNITED ARAB EMIRATES MEXICO
VIETNAM
VSL Representative Office VSL Middle East Office Phone: +52 - 5 - 396 86 21
DALLAS, TX DUBAI Fax: +52 - 5 - 396 84 88
VStructural Llc. HANOI
Phone: +84 - 4 - 8245 488 Phone: +971 - 4 - 282 08 03
Phone: +1 - 972 - 647 - 0200 Fax: +971 - 4 - 282 94 41 NETHERLANDS
Fax: +1 - 972 - 641 - 1192 Fax: +84 - 4 - 8245 717
VSL Benelux B.V
AT LEIDEN

Photos: M. Grabowski, D. Mc Allan, Photo Basilic AG, Skycam, L. Zylberman, G. Leitao, J. Jung, X.
DENVER, CO Phone: +31 - 71 - 576 89 00
VStructural Llc. Fax: +31 - 71 - 572 08 86
Phone: +1 - 303 - 456 - 9887
Fax: +1 - 303 - 456 - 9796 NORWAY
VSL Norge A/S
WASHINGTON, DC STAVANGER
VStructural Llc. Phone: +46 - 87 - 53 02 50
Phone: +1 - 703 - 451 - 4300 Fax: +46 - 87 - 53 49 73
Fax: +1 - 703 - 451 - 0862
PORTUGAL
VSL Sistemas Portugal SA
S. DOMINGO DE RANA
Phone: +351 - 21 - 445 83 10
France Fax: +351 - 21 - 444 63 77

SOUTH AFRICA
VSL France S.A. VSL Systems (South Africa) Pty Ltd.
EGLY Kya Sand, RANDBURG
Phone: +33 - 1 - 69 26 14 00 Phone: +27 - 11 - 708 21 00
Fax: +33 - 1 - 60 83 89 95 Fax: +27 - 11 - 708 21 20

SPAIN
CTT Stronghold
BARCELONA
Phone: +34 - 93 - 200 87 11
Fax: +34 - 93 - 209 85 90

SWEDEN
Internordisk Spännarmering AB
STOCKHOLM
Phone: +46 - 8 - 753 02 50
Fax: +46 - 8 - 753 49 73

Pakse Bridge - Laos


EDITORIAL HIGHLIGHTS BUILDINGS

An example to follow!
5 - H O N G KO N G -
C O M P L E T I O N O F T H E O LY M P I C S T A T I O N
The present issue of VSL News contains
Segment erection Olympic Station Development Due to the large number of angled
an article concerning the Pakse Bridge on
for the Nanjing Yangtze River Site C is the third phase of a new secondary beams and reductions
the Mekong River in Laos. This project
2nd Crossing residential and commercial in core wall and column thicknesses,
represents a good example of our strategy programme located on the Kowloon table formwork could not be used
based on providing customers with enlarged Peninsula overlooking Hong Kong or would have resulted in excessive

8-11
work packages that incorporate many of harbour. The programme comprised table-form modifications.
ten residential towers as well as a The typical core area formed per floor
VSL’s specialised techniques.
retail and transport centre, both was 940 m2 using VSL Climbform and
Our responsibilities on the Pakse Project already completed. For its last phase - 2,400 m2 with Mivan formwork.
construction of the 32-storey MTRC
included all superstructure works: VSL’s package and Hong Kong Bank office building- After only a 3-floor learning curve,
• design, construction and dismantling of for the Pakse Bridge the developer, Sino Land, required the building progressed regularly
Superstructure a faster construction schedule on a 4-day per floor cycle including
the precast segment casting yard;
than originally planned to catch up some modification works on certain
• production and erection of precast with the overall programme. floor levels. The structural frame was
Initially tendered for construction successfully completed just after the
segments, including the design, supply and
using traditional formwork methods, Chinese Lunar New Year. ■
commissioning of the erection gantry; VSL proposed speeding up
construction by using a combination of S t u a r t Pe a r s o n
• construction of the cast in-situ upper part
VSL Climbform system for the large VS L H o n g Ko n g
of the piers and pier-heads as well as the central core and Mivan system
two central span pylons; formwork for the beams and slabs VSL Climbform and Mivan Formwork
as well as for the columns and lift were used to speed up construction of this
• installation of post-tensioning and lobby / staircase areas. 32-storey office Building.
stay cables.

By providing our customers with a package


integrating all interfaces between the
different technical activities, we are able to
13-17 - CHILE -
save them both time and money. PT in Special Structures PT SLABS FOR THE B O U L E VA R D K E N N E DY C O M P L E X
We are proud to announce that the bridge Owned by Inmobiliaria Calle, the
complex comprises a 42-storey main

18-19
was completed 4 month ahead of schedule
tower incorporating the Marriott Hotel,
and to the full satisfaction of our client. two 18-storey twin office towers and a
We can do the same for you - anytime, four-level underground carpark.
anywhere. The main contractor, Constructora ACS,
Your local awarded VSL the design, supply and
installation of the post-tensioning
Alain le Pivert construction
slabs for the twin towers and the
CEO and Chairman of the Board partner underground levels, representing a
in Portugal 58,000-m2 area.
While the main tower was designed
using traditional reinforced concrete,
post-tensioning was the only solution
P U B L I S H E D B Y
for the construction of the twin towers
VSL International Ltd. Regional Editors: P. Bron - Western Europe, Africa
Bernstrasse 9, 3421 Lyssach and Latin America
given the need to provide for a 4.5-m
G. Pash - Australia and Pacific
Switzerland Tel: +61 2 9484 59 44 Tel: +33 1 69 19 43 00 cantilever and increased distances
and Co-ordination:
VSL Management J-P. Trin - South East Asia
between columns. PT was also the
S. Alezrah
41, avenue du Centre Tel: +33 1 30 12 09 42 Tel: +33 1 30 12 09 41 best solution for the underground
78067 St-Quentin-en-Yvelines
France A. Payne - North East Asia Design: levels, as it allowed excavation works
Red Line
Editor: A. Le Pivert Tel: +852 2590 22 22
Tel: +33 1 41 14 01 80 to be considerably reduced. ■
Tel: +33 1 30 12 09 30
H. Wlodkowski - Central East Linguistic Consultant: Located in Santiago next to a shopping concept in Chile by grouping together a
Technical Editor: H. R. Ganz Europe and Middle East N. Hargreaves
Tel: +33 1 30 12 09 30 Tel: +41 34 447 99 11 Tel: +33 1 43 66 88 05 centre, the Boulevard Kennedy Project hotel, office areas, conference rooms A n d re s A ve n d a ñ o
will introduce a new business services and other services in a single complex. VS L C h i l e

2 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 3
EDITORIAL HIGHLIGHTS BUILDINGS

An example to follow!
5 - H O N G KO N G -
C O M P L E T I O N O F T H E O LY M P I C S T A T I O N
The present issue of VSL News contains
Segment erection Olympic Station Development Due to the large number of angled
an article concerning the Pakse Bridge on
for the Nanjing Yangtze River Site C is the third phase of a new secondary beams and reductions
the Mekong River in Laos. This project
2nd Crossing residential and commercial in core wall and column thicknesses,
represents a good example of our strategy programme located on the Kowloon table formwork could not be used
based on providing customers with enlarged Peninsula overlooking Hong Kong or would have resulted in excessive

8-11
work packages that incorporate many of harbour. The programme comprised table-form modifications.
ten residential towers as well as a The typical core area formed per floor
VSL’s specialised techniques.
retail and transport centre, both was 940 m2 using VSL Climbform and
Our responsibilities on the Pakse Project already completed. For its last phase - 2,400 m2 with Mivan formwork.
construction of the 32-storey MTRC
included all superstructure works: VSL’s package and Hong Kong Bank office building- After only a 3-floor learning curve,
• design, construction and dismantling of for the Pakse Bridge the developer, Sino Land, required the building progressed regularly
Superstructure a faster construction schedule on a 4-day per floor cycle including
the precast segment casting yard;
than originally planned to catch up some modification works on certain
• production and erection of precast with the overall programme. floor levels. The structural frame was
Initially tendered for construction successfully completed just after the
segments, including the design, supply and
using traditional formwork methods, Chinese Lunar New Year. ■
commissioning of the erection gantry; VSL proposed speeding up
construction by using a combination of S t u a r t Pe a r s o n
• construction of the cast in-situ upper part
VSL Climbform system for the large VS L H o n g Ko n g
of the piers and pier-heads as well as the central core and Mivan system
two central span pylons; formwork for the beams and slabs VSL Climbform and Mivan Formwork
as well as for the columns and lift were used to speed up construction of this
• installation of post-tensioning and lobby / staircase areas. 32-storey office Building.
stay cables.

By providing our customers with a package


integrating all interfaces between the
different technical activities, we are able to
13-17 - CHILE -
save them both time and money. PT in Special Structures PT SLABS FOR THE B O U L E VA R D K E N N E DY C O M P L E X
We are proud to announce that the bridge Owned by Inmobiliaria Calle, the
complex comprises a 42-storey main

18-19
was completed 4 month ahead of schedule
tower incorporating the Marriott Hotel,
and to the full satisfaction of our client. two 18-storey twin office towers and a
We can do the same for you - anytime, four-level underground carpark.
anywhere. The main contractor, Constructora ACS,
Your local awarded VSL the design, supply and
installation of the post-tensioning
Alain le Pivert construction
slabs for the twin towers and the
CEO and Chairman of the Board partner underground levels, representing a
in Portugal 58,000-m2 area.
While the main tower was designed
using traditional reinforced concrete,
post-tensioning was the only solution
P U B L I S H E D B Y
for the construction of the twin towers
VSL International Ltd. Regional Editors: P. Bron - Western Europe, Africa
Bernstrasse 9, 3421 Lyssach and Latin America
given the need to provide for a 4.5-m
G. Pash - Australia and Pacific
Switzerland Tel: +61 2 9484 59 44 Tel: +33 1 69 19 43 00 cantilever and increased distances
and Co-ordination:
VSL Management J-P. Trin - South East Asia
between columns. PT was also the
S. Alezrah
41, avenue du Centre Tel: +33 1 30 12 09 42 Tel: +33 1 30 12 09 41 best solution for the underground
78067 St-Quentin-en-Yvelines
France A. Payne - North East Asia Design: levels, as it allowed excavation works
Red Line
Editor: A. Le Pivert Tel: +852 2590 22 22
Tel: +33 1 41 14 01 80 to be considerably reduced. ■
Tel: +33 1 30 12 09 30
H. Wlodkowski - Central East Linguistic Consultant: Located in Santiago next to a shopping concept in Chile by grouping together a
Technical Editor: H. R. Ganz Europe and Middle East N. Hargreaves
Tel: +33 1 30 12 09 30 Tel: +41 34 447 99 11 Tel: +33 1 43 66 88 05 centre, the Boulevard Kennedy Project hotel, office areas, conference rooms A n d re s A ve n d a ñ o
will introduce a new business services and other services in a single complex. VS L C h i l e

2 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 3
HEAVY LIFTING HEAVY LIFTING

- FRANCE - - CHINA -
LIFTING THE V E T R OT E X FAC TO RY USING VERSO™ N A N J I N G YA N G T Z E R I V E R S E C O N D C R O S S I N G P R O J E C T
On January 1, 2000, VSL celebrated the new Located some 11-km down- The segments are welded to the Cycle times are anticipated to be
existing deck, rope stays installed one pair of segments every seven days
millennium by jacking up the 50 columns stream from the existing
and tensioned. The lifting frames are per pylon. As erection is scheduled
supporting the steel structure of the Vetrotex Nanjing First Yangtze River then launched out and the process to take place on both pylons over
Factory by 340 mm. This factory is a multi-storey Bridge, the Nanjing Yangtze repeated. the same period, a total of four lifting
industrial building manufacturing glass fibre. River Second Crossing frames is needed.

A s i t d o e s n o t r e q u i r e c a b l e c o n n e c t i o n s , t h e Ve R S O ™ s y s t e m
consists of two bridges Simultaneous lift
of two 272-t segments The close collaboration between
is very simple to install and can independently control (north and south) and a road VSL’s Heavy Lifting department in
the movements of up to one hundred jacks.
section repressenting a total Singapore and VSL’s Special Projects
length of 12,517 m. division in China resulted in an
impressive project that incorporates
The North Bridge is a conventional the highest levels of construction
post-tensioned cast in-situ concrete safety, quality and performance. ■
A Ve R S O ™ S y s t e m l i f t i n g u n i t bridge constructed using the balanced
cantilever method with travelling Ro n a l d Le e ( VS L C h i n a )
VSL supplied and assembled the steel formwork. Its 2,212-m overall length is a n d D a v i d Tra y n e r ( VS L S i n g a p o re )
brackets, dismantled and refitted all divided in three 165-m main spans.
pipe-work and external wall cladding, The South Bridge is a prefabricated
carried out the 340 mm jacking and steel segment cable-stayed bridge.
installed the new concrete bases for With a main span of 628 m and a total
all the columns. ■ length of 1,238 m, it is ranked as the
The South Bridge
longest cable-stayed span in China under construction.
Al a i n S t a m m and the third longest in the world.
VS L Fra n c e In December 1998, VSL was awarded a
contract for the design,
commissioning and supervision of the
VSL Technical Centre Europe (TCEU) segment erection system and rental of
carried out the engineering studies the heavy lifting equipment for the
required to jack up the Vetrotex South Bridge. This marked the start of
In order to modernise its Chambery The project’s reduced jacking Factory’s steel structure by 340 mm. VSL’s proactive involvement in the
factory (south-east France), Vetrotex, tolerance was achieved using TCEU’s scope of works comprised: introduction of advanced construction
a Saint-Gobain subsidiary, decided VSL France’s new lifting equipment: • modelling of the structure, using ROBOT methods into Mainland China.
to increase the floor to ceiling height the VeRSO™ jacking system. finite elements software, both for the
of a manufacturing bay by 340 mm jacking and for the new permanent Segment erection
to install new equipment. VeRSO™ - Shared intelligence configuration. The goal was to define the A standard segment weighs 272 t, and
loads to be supported and check structural
VSL successfully met the challenge computer-aided jacking system is 38 m wide, 15 m long and 3.5 m high.
stability during all stages, taking climatic
and carried out the jacking works The VeRSO™ system comprises a conditions (winds up to 44.7 m/s, snow…) For the segment lifting operation
on 1 January without the slightest central control station and a number of and the seismic environment into account. (approx. 40 m above sea level), VSL
problem. individually computer-aided jacking • definition of all temporary works needed used two SLU lifting units mounted on
units, each contributing to the general to transmit jacking loads to the columns. self-launching cantilever lifting
The 30 x 40-m and 15-m high jacking process. All jacking units are These temporary works were analysed and frames. Lifting rates are set at a
manufacturing bay is a 900-t steel radio controlled by a central processor. defined to optimise VSL’s scope of works, maximum of 19 m/h and an
structure resting on 50 columns. Each jacking unit is equipped with a both economically and in terms of automated driven coiler enables the
The lifting process was carried out process computer, a high pressure completion times. lifting spreader beams to be rapidly
by simultaneously jacking up the hydraulic pump (700 bars), a digital • definition of all new final column lowered to hook up the segments.
50 columns with a maximum displacement sensor, an electronically connections in their new positions as well The 69 segments are lifted from a
as structural strengthening due to changed
allowable tolerance of 1 mm between regulated oil flow valve, an oil tank barge positioned below the bridge
wind conditions on completion of the
any two jacking points. and ancillaries, two-way radio building jacking operation.
deck and handled in space by
VSL installed 70 hydraulic jacks (with command and a 24 Ah electric battery. adjusting the SLU jacks and the lifting
• technical assistance during the lifting
capacities ranging from 10 to 100 t) process.
points on the spreader beams.
under the steel brackets welded to the In addition to fully designing the jacking The segment erection requires a
Va n e s s a B u c h i n
columns. The jack mounting system was operation, including computer analysis and Christophe Candolfi
simultaneous lift on both ends of the
designed to withstand wind stresses of the frame, wind calculations, steel VS L TC E U cantilevering bridge deck with the out
of up to 160 km per hour on the bay. brackets design and shop drawings, of balance load limited to 10%.

4 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 5
HEAVY LIFTING HEAVY LIFTING

- FRANCE - - CHINA -
LIFTING THE V E T R OT E X FAC TO RY USING VERSO™ N A N J I N G YA N G T Z E R I V E R S E C O N D C R O S S I N G P R O J E C T
On January 1, 2000, VSL celebrated the new Located some 11-km down- The segments are welded to the Cycle times are anticipated to be
existing deck, rope stays installed one pair of segments every seven days
millennium by jacking up the 50 columns stream from the existing
and tensioned. The lifting frames are per pylon. As erection is scheduled
supporting the steel structure of the Vetrotex Nanjing First Yangtze River then launched out and the process to take place on both pylons over
Factory by 340 mm. This factory is a multi-storey Bridge, the Nanjing Yangtze repeated. the same period, a total of four lifting
industrial building manufacturing glass fibre. River Second Crossing frames is needed.

A s i t d o e s n o t r e q u i r e c a b l e c o n n e c t i o n s , t h e Ve R S O ™ s y s t e m
consists of two bridges Simultaneous lift
of two 272-t segments The close collaboration between
is very simple to install and can independently control (north and south) and a road VSL’s Heavy Lifting department in
the movements of up to one hundred jacks.
section repressenting a total Singapore and VSL’s Special Projects
length of 12,517 m. division in China resulted in an
impressive project that incorporates
The North Bridge is a conventional the highest levels of construction
post-tensioned cast in-situ concrete safety, quality and performance. ■
A Ve R S O ™ S y s t e m l i f t i n g u n i t bridge constructed using the balanced
cantilever method with travelling Ro n a l d Le e ( VS L C h i n a )
VSL supplied and assembled the steel formwork. Its 2,212-m overall length is a n d D a v i d Tra y n e r ( VS L S i n g a p o re )
brackets, dismantled and refitted all divided in three 165-m main spans.
pipe-work and external wall cladding, The South Bridge is a prefabricated
carried out the 340 mm jacking and steel segment cable-stayed bridge.
installed the new concrete bases for With a main span of 628 m and a total
all the columns. ■ length of 1,238 m, it is ranked as the
The South Bridge
longest cable-stayed span in China under construction.
Al a i n S t a m m and the third longest in the world.
VS L Fra n c e In December 1998, VSL was awarded a
contract for the design,
commissioning and supervision of the
VSL Technical Centre Europe (TCEU) segment erection system and rental of
carried out the engineering studies the heavy lifting equipment for the
required to jack up the Vetrotex South Bridge. This marked the start of
In order to modernise its Chambery The project’s reduced jacking Factory’s steel structure by 340 mm. VSL’s proactive involvement in the
factory (south-east France), Vetrotex, tolerance was achieved using TCEU’s scope of works comprised: introduction of advanced construction
a Saint-Gobain subsidiary, decided VSL France’s new lifting equipment: • modelling of the structure, using ROBOT methods into Mainland China.
to increase the floor to ceiling height the VeRSO™ jacking system. finite elements software, both for the
of a manufacturing bay by 340 mm jacking and for the new permanent Segment erection
to install new equipment. VeRSO™ - Shared intelligence configuration. The goal was to define the A standard segment weighs 272 t, and
loads to be supported and check structural
VSL successfully met the challenge computer-aided jacking system is 38 m wide, 15 m long and 3.5 m high.
stability during all stages, taking climatic
and carried out the jacking works The VeRSO™ system comprises a conditions (winds up to 44.7 m/s, snow…) For the segment lifting operation
on 1 January without the slightest central control station and a number of and the seismic environment into account. (approx. 40 m above sea level), VSL
problem. individually computer-aided jacking • definition of all temporary works needed used two SLU lifting units mounted on
units, each contributing to the general to transmit jacking loads to the columns. self-launching cantilever lifting
The 30 x 40-m and 15-m high jacking process. All jacking units are These temporary works were analysed and frames. Lifting rates are set at a
manufacturing bay is a 900-t steel radio controlled by a central processor. defined to optimise VSL’s scope of works, maximum of 19 m/h and an
structure resting on 50 columns. Each jacking unit is equipped with a both economically and in terms of automated driven coiler enables the
The lifting process was carried out process computer, a high pressure completion times. lifting spreader beams to be rapidly
by simultaneously jacking up the hydraulic pump (700 bars), a digital • definition of all new final column lowered to hook up the segments.
50 columns with a maximum displacement sensor, an electronically connections in their new positions as well The 69 segments are lifted from a
as structural strengthening due to changed
allowable tolerance of 1 mm between regulated oil flow valve, an oil tank barge positioned below the bridge
wind conditions on completion of the
any two jacking points. and ancillaries, two-way radio building jacking operation.
deck and handled in space by
VSL installed 70 hydraulic jacks (with command and a 24 Ah electric battery. adjusting the SLU jacks and the lifting
• technical assistance during the lifting
capacities ranging from 10 to 100 t) process.
points on the spreader beams.
under the steel brackets welded to the In addition to fully designing the jacking The segment erection requires a
Va n e s s a B u c h i n
columns. The jack mounting system was operation, including computer analysis and Christophe Candolfi
simultaneous lift on both ends of the
designed to withstand wind stresses of the frame, wind calculations, steel VS L TC E U cantilevering bridge deck with the out
of up to 160 km per hour on the bay. brackets design and shop drawings, of balance load limited to 10%.

4 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 5
HEAVY LIFTING GEOTECHNICAL

- SWITZERLAND - - CHILE -
S P E C TAC U L A R DREIROSEN BRIDGE
A S S E M B LY O F T H E E L P O RT E Z U E L O R E TA I N E D E A RT H W A L L

E l P o r t e z u e l o R e t a i n e d E a r t h Wa l l - P h a s e 1

Owned by Inmobiliaria Auco S.A., The first phase (3,500 m2) leads up This project represents an important
the Portezuelo Condominium is from one side up to a reinforced retained earth reference for VSL Chile
currently one of the largest building concrete ornamental arc shape located as it is the highest RE wall constructed
projects being constructed in a new at the centre of the ramp. The architect in an urban area in the country. ■
residential area of Santiago City. divided the wall into three similar
The first stage was the construction height sections in order to create A n d re s A ve n d a ñ o
of two 17-storey buildings and this two garden terraces between them. VS L C h i l e
will be followed by the completion
of eight new buildings over the next
five years.

One of the most difficult problems - SWITZERLAND -


to resolve was the design of the
access ramp to these two buildings. E L E C T R I C A L LY I S O L A T E D A N C H O R S
This essentially consists of a 450-m F O R T H E S E E L I S B E R G M O T O R W AY T U N N E L
Second truss in lifted position and being moved into bridge axes.
long ramp with access from both
sides, sloping up from 0.60 m to The 9.3-km long twin tunnel is part Based on the results of test anchors,
The Dreirosen Bridge crosses the the river Rhine on the French side, Once the first new bridge is 18 m. Among the different proposed of the A2 motorway running from the free length was set at 12 and 14 m
river Rhine in the centre of Basle, were transported to the site on two commissioned in 2001, the old solutions, the VSL Retained Earth Basle to the Italian border. with an 8-m bond length. All anchors
Switzerland. However, the existing barges. Each barge was equipped superstructure will be dismantled Wall system was chosen as the most It crosses a 450-m long marl stratum, have threaded anchor heads for
65-year old bridge no longer meets with 2 lifting towers, each supporting and in January 2002, VSL will repeat economical and aesthetic alternative which, despite the prestressed VSL subsequent load adjustments.
today’s traffic requirements and it one SMU-330 lifting/lowering unit. the same operation for the proposal. anchors installed in 1979, continues A total of 16 surveillance anchors,
was decided to replace the old As the barges had to pass under an second bridge. ■ to swell and raise the concrete road each with a load cell and an electrical
structure by two parallel 3-span existing bridge, the lifting towers The 6,000-m2 total surface area is pavement. To contain the uplift and resistance measuring installation,
double deck bridges. These will were split into two so that each half Fe r d i n a n d Tre n k l e r divided into two phases. While the extend the service life of the existing were installed, enabling forces and
eventually link the Swiss motorway could be pivoted backwards. VS L S w i t z e r l a n d second phase is expected to begin at anchors, the owner, the Canton of the integrity of the corrosion
system with German and French the end of the year, VSL was awarded Nidwalden, decided to install protection encapsulation to be
motorways. Once the lifting towers were the design of the wall, the supply of additional anchors. continuously monitored. Works were
repositioned at the bridge site, VSL materials (square panels, mesh and carried out between November 1999
In late January 2000, VSL placed the lifted the truss by 10 m, and after the accessories) and the supervision VSL supplied and stressed and mid-February 2000. ■
two 540-t and 128-m long steel barges were properly positioned, of the installation works for the 376 electrically isolated permanent
trusses for the first bridge. The lowered the structure onto piers and first phase by the main contractor, and regroutable 5-12 type anchors, Fra n z F i s c h l i
trusses, fabricated 4 km further down abutments. Constructora Manquehue Tres S.A. each with a working load of 1,310 kN. VS L S w i t z e r l a n d

6 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 7
HEAVY LIFTING GEOTECHNICAL

- SWITZERLAND - - CHILE -
S P E C TAC U L A R DREIROSEN BRIDGE
A S S E M B LY O F T H E E L P O RT E Z U E L O R E TA I N E D E A RT H W A L L

E l P o r t e z u e l o R e t a i n e d E a r t h Wa l l - P h a s e 1

Owned by Inmobiliaria Auco S.A., The first phase (3,500 m2) leads up This project represents an important
the Portezuelo Condominium is from one side up to a reinforced retained earth reference for VSL Chile
currently one of the largest building concrete ornamental arc shape located as it is the highest RE wall constructed
projects being constructed in a new at the centre of the ramp. The architect in an urban area in the country. ■
residential area of Santiago City. divided the wall into three similar
The first stage was the construction height sections in order to create A n d re s A ve n d a ñ o
of two 17-storey buildings and this two garden terraces between them. VS L C h i l e
will be followed by the completion
of eight new buildings over the next
five years.

One of the most difficult problems - SWITZERLAND -


to resolve was the design of the
access ramp to these two buildings. E L E C T R I C A L LY I S O L A T E D A N C H O R S
This essentially consists of a 450-m F O R T H E S E E L I S B E R G M O T O R W AY T U N N E L
Second truss in lifted position and being moved into bridge axes.
long ramp with access from both
sides, sloping up from 0.60 m to The 9.3-km long twin tunnel is part Based on the results of test anchors,
The Dreirosen Bridge crosses the the river Rhine on the French side, Once the first new bridge is 18 m. Among the different proposed of the A2 motorway running from the free length was set at 12 and 14 m
river Rhine in the centre of Basle, were transported to the site on two commissioned in 2001, the old solutions, the VSL Retained Earth Basle to the Italian border. with an 8-m bond length. All anchors
Switzerland. However, the existing barges. Each barge was equipped superstructure will be dismantled Wall system was chosen as the most It crosses a 450-m long marl stratum, have threaded anchor heads for
65-year old bridge no longer meets with 2 lifting towers, each supporting and in January 2002, VSL will repeat economical and aesthetic alternative which, despite the prestressed VSL subsequent load adjustments.
today’s traffic requirements and it one SMU-330 lifting/lowering unit. the same operation for the proposal. anchors installed in 1979, continues A total of 16 surveillance anchors,
was decided to replace the old As the barges had to pass under an second bridge. ■ to swell and raise the concrete road each with a load cell and an electrical
structure by two parallel 3-span existing bridge, the lifting towers The 6,000-m2 total surface area is pavement. To contain the uplift and resistance measuring installation,
double deck bridges. These will were split into two so that each half Fe r d i n a n d Tre n k l e r divided into two phases. While the extend the service life of the existing were installed, enabling forces and
eventually link the Swiss motorway could be pivoted backwards. VS L S w i t z e r l a n d second phase is expected to begin at anchors, the owner, the Canton of the integrity of the corrosion
system with German and French the end of the year, VSL was awarded Nidwalden, decided to install protection encapsulation to be
motorways. Once the lifting towers were the design of the wall, the supply of additional anchors. continuously monitored. Works were
repositioned at the bridge site, VSL materials (square panels, mesh and carried out between November 1999
In late January 2000, VSL placed the lifted the truss by 10 m, and after the accessories) and the supervision VSL supplied and stressed and mid-February 2000. ■
two 540-t and 128-m long steel barges were properly positioned, of the installation works for the 376 electrically isolated permanent
trusses for the first bridge. The lowered the structure onto piers and first phase by the main contractor, and regroutable 5-12 type anchors, Fra n z F i s c h l i
trusses, fabricated 4 km further down abutments. Constructora Manquehue Tres S.A. each with a working load of 1,310 kN. VS L S w i t z e r l a n d

6 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 7
BRIDGES BRIDGES

- P E O P L E ’ S D E M O C R AT I C REPUBLIC OF LAOS -
COMPLETION OF THE PA K S E B R I D G E

VSL expertise helps open up South-East Asia

The deck assembly of the


Pakse Bridge in Champasak,
the southern province of
Laos, was completed in
February 2000, four month
ahead of schedule. The
opening of the 1,380-m long
precast segmental bridge
later this year will be a key
factor in the development of
this region as it will ease
travel and trade between
Thailand, Vietnam and
Cambodia.

The 1,380-m long Pakse Bridge


and its launching gantry
after finishing deck erection.

8 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 9
BRIDGES BRIDGES

- P E O P L E ’ S D E M O C R AT I C REPUBLIC OF LAOS -
COMPLETION OF THE PA K S E B R I D G E

VSL expertise helps open up South-East Asia

The deck assembly of the


Pakse Bridge in Champasak,
the southern province of
Laos, was completed in
February 2000, four month
ahead of schedule. The
opening of the 1,380-m long
precast segmental bridge
later this year will be a key
factor in the development of
this region as it will ease
travel and trade between
Thailand, Vietnam and
Cambodia.

The 1,380-m long Pakse Bridge


and its launching gantry
after finishing deck erection.

8 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 9
BRIDGES BRIDGES

normal segments and 14.5 m for main


span segments. The height varies from
6.5 to 3 m at mid-span.

A total of 975 t of strands and


stressbars were used on the Project.

VSL’s Package
VSL’s substantial scope of works for the
Pakse Bridge includes:
• construction and dismantling of the
precast segment casting yard;
• production of 384 precast segments;
VSL Heavy Lifting equipment • erection of precast segments, including 8 nationalities were involved
The People’s Democratic Republic of installed for lowering of design, supply and commissioning of the in the construction of On the other hand, access during the
stay stressing platform the Pakse Bridge.
Laos is a landlocked country in the erection gantry; dry or low water level season is
centre of the Indochinese peninsula, • geometry control; difficult because of the many
and shares a common border with Although the pier heads are cast • construction of the cast in-situ portion Construction Schedule sandbanks that become exposed in
Thailand, Vietnam, Cambodia, Burma in-situ, the 384 segments are cast in of the deck including the installation of The climate in southern Laos is clearly the Mekong. Pakse’s physical isolation
and China. Pakse, the most southern moulds in the precast segment bearings and expansion joints; divided into two seasons: the rainy also meant that the VSL team had to
regional capital of Laos, is the transit production yard on site. • construction of pylons; season from May to October, and the carefully programme their work as
point for traffic in the southern area of The segments are installed with • installation of dry season from November to April. most of the construction materials, i.e.
the country: Vientiane, the capital, lies internal and external prestressing, and stay cables (50 t); During the year, the water level of consumables, machines, equipment
to the north, Vietnam to the east, incorporate the stay cables for the • construction of the Mekong varies by more than 10 m and others, had to be imported from
the top 11.5-m
Cambodia to the south and Thailand main span segments. of piers 1 to 12;
and the strong currents during the Thailand or from overseas.
to the west. The area is rich in natural The weight of a segment varies rainy season can make access by These extreme conditions had an
• Post-tensioning:
resources and the new bridge, one of between 60 and 105 t, with a length 930 t. boat and barges very difficult and impact on the construction schedule
two crossing the Mekong, is an of 2.5 or 3.5 m, a width of 11.5 m for time-consuming. but the careful planning and good
integral part of a regional management by the capable and
infrastructure upgrade currently being dedicated VSL Project Team led to the
undertaken to allow the Laotian
people to more fully develop these
Segment erection of the Pakse Bridge segment erection being completed in
February 2000, 4 month ahead of
384 segments had had to be precast for Pakse Bridge,
resources by providing access to trade schedule. ■
each using 25-40 m3 of concrete.
ports in neighbouring countries. Pe t e r M a h a r
VS L T h a i l a n d
Segment erection Main span Segment erection Approach span
A 1,380-m segmental bridge
Lying a few kilometres south of the 85000 71750 P(N–1) P(N) P(N+1)
85000 56750 Main participants:
existing ferry route, the Pakse Bridge Lift up and move • Grant aid: The Government of Japan,
stretches 1,380 m from the Phonthong first segment into axis Pick up Japan International Cooperation Agency
of MSL, only then of first segment
to the Pakse side. The bridge is a pick up second
(JICA)
precast segmental bridge with an segment • Client: Ministry of Communications
extra-dosed main span erected using Transportation, Post and Construction
the balanced cantilever method and Move first segment • Supervising Agency: Communications
supported by a total of 13 piers. This Lower segment into axis of MSL, Department, MCTPC
into place, only then pick up
continuous rigid frame post-tensioned second segment
• Consultant: Nippon Koei Co., Ltd.,
cast wet joint and
Japan in association with Construction
concrete box girder consists of stress temporary PT
Project Consultants Inc., Japan
four bridges, separated by hinges at Place segments,
• Contractor: Shimizu Corporation - Hazama
mid-span. The standard span length is cast wet joint and
Corporation Joint Venture, Japan
stress temporary PT
102 m with a main span of 143 m. After placing
segment N+2, install • Principal Sub-Contractor:
• Bridge 1, including A1 abutment: and stress stay VSL (Thailand) Co., Ltd. (segment
70 - 102 - 102 - 51 = 325 m. cable segment N Stress permanent PT production, pier head, deck)
• Bridges 2 and 3: Transfer load from
gantry to bridge
51 - 102 - 102 - 51 = 306 m each.
• Bridge 4, including the main span
and A2 abutment: Repeat above steps
51 - 123 - 143 - 91.5 - 34.5 = 443 m. Casting closure pour until cantilever finished
The main span segments are wider 143000 cast closure pour,
102000 102000
stress external PT
than the standard segments to
accommodate the stay blisters.

10 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 11
BRIDGES BRIDGES

normal segments and 14.5 m for main


span segments. The height varies from
6.5 to 3 m at mid-span.

A total of 975 t of strands and


stressbars were used on the Project.

VSL’s Package
VSL’s substantial scope of works for the
Pakse Bridge includes:
• construction and dismantling of the
precast segment casting yard;
• production of 384 precast segments;
VSL Heavy Lifting equipment • erection of precast segments, including 8 nationalities were involved
The People’s Democratic Republic of installed for lowering of design, supply and commissioning of the in the construction of On the other hand, access during the
stay stressing platform the Pakse Bridge.
Laos is a landlocked country in the erection gantry; dry or low water level season is
centre of the Indochinese peninsula, • geometry control; difficult because of the many
and shares a common border with Although the pier heads are cast • construction of the cast in-situ portion Construction Schedule sandbanks that become exposed in
Thailand, Vietnam, Cambodia, Burma in-situ, the 384 segments are cast in of the deck including the installation of The climate in southern Laos is clearly the Mekong. Pakse’s physical isolation
and China. Pakse, the most southern moulds in the precast segment bearings and expansion joints; divided into two seasons: the rainy also meant that the VSL team had to
regional capital of Laos, is the transit production yard on site. • construction of pylons; season from May to October, and the carefully programme their work as
point for traffic in the southern area of The segments are installed with • installation of dry season from November to April. most of the construction materials, i.e.
the country: Vientiane, the capital, lies internal and external prestressing, and stay cables (50 t); During the year, the water level of consumables, machines, equipment
to the north, Vietnam to the east, incorporate the stay cables for the • construction of the Mekong varies by more than 10 m and others, had to be imported from
the top 11.5-m
Cambodia to the south and Thailand main span segments. of piers 1 to 12;
and the strong currents during the Thailand or from overseas.
to the west. The area is rich in natural The weight of a segment varies rainy season can make access by These extreme conditions had an
• Post-tensioning:
resources and the new bridge, one of between 60 and 105 t, with a length 930 t. boat and barges very difficult and impact on the construction schedule
two crossing the Mekong, is an of 2.5 or 3.5 m, a width of 11.5 m for time-consuming. but the careful planning and good
integral part of a regional management by the capable and
infrastructure upgrade currently being dedicated VSL Project Team led to the
undertaken to allow the Laotian
people to more fully develop these
Segment erection of the Pakse Bridge segment erection being completed in
February 2000, 4 month ahead of
384 segments had had to be precast for Pakse Bridge,
resources by providing access to trade schedule. ■
each using 25-40 m3 of concrete.
ports in neighbouring countries. Pe t e r M a h a r
VS L T h a i l a n d
Segment erection Main span Segment erection Approach span
A 1,380-m segmental bridge
Lying a few kilometres south of the 85000 71750 P(N–1) P(N) P(N+1)
85000 56750 Main participants:
existing ferry route, the Pakse Bridge Lift up and move • Grant aid: The Government of Japan,
stretches 1,380 m from the Phonthong first segment into axis Pick up Japan International Cooperation Agency
of MSL, only then of first segment
to the Pakse side. The bridge is a pick up second
(JICA)
precast segmental bridge with an segment • Client: Ministry of Communications
extra-dosed main span erected using Transportation, Post and Construction
the balanced cantilever method and Move first segment • Supervising Agency: Communications
supported by a total of 13 piers. This Lower segment into axis of MSL, Department, MCTPC
into place, only then pick up
continuous rigid frame post-tensioned second segment
• Consultant: Nippon Koei Co., Ltd.,
cast wet joint and
Japan in association with Construction
concrete box girder consists of stress temporary PT
Project Consultants Inc., Japan
four bridges, separated by hinges at Place segments,
• Contractor: Shimizu Corporation - Hazama
mid-span. The standard span length is cast wet joint and
Corporation Joint Venture, Japan
stress temporary PT
102 m with a main span of 143 m. After placing
segment N+2, install • Principal Sub-Contractor:
• Bridge 1, including A1 abutment: and stress stay VSL (Thailand) Co., Ltd. (segment
70 - 102 - 102 - 51 = 325 m. cable segment N Stress permanent PT production, pier head, deck)
• Bridges 2 and 3: Transfer load from
gantry to bridge
51 - 102 - 102 - 51 = 306 m each.
• Bridge 4, including the main span
and A2 abutment: Repeat above steps
51 - 123 - 143 - 91.5 - 34.5 = 443 m. Casting closure pour until cantilever finished
The main span segments are wider 143000 cast closure pour,
102000 102000
stress external PT
than the standard segments to
accommodate the stay blisters.

10 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 11
PT
I N S P E C I A L
BRIDGES STRUCTURES

- J A PA N -
TA K A M AT U B R I D G E Without post-tensioning, many special structures could not
be built. VSL has adapted post-tensioning principles to a wide
the Takamatu Bridge has a 260-m long range of civil engineering structures such as LNG/LPG tanks,
arch span, making it the longest water reservoirs, wastewater plant digesters, underground
concrete arched bridge span in Japan
and the 10th in the world.
tunnels, off-shore platforms, concrete floating barges and dams.
For the first time in Japan, the erection
of the arch rib was executed by For these types of structures, requiring strict quality control and
combining Truss and Melan methods. flawless performance, post-tensioning provides cost savings,
speeds up construction, improves durability and is virtually
VSL’s method was adopted for the
installation of external cables at the maintenance-free.
arch rib, as well as for the upper deck
slab back stay cables, diagonal Over the years, VSL has been involved in a number of highly
suspension cables and main cables, prestigious and complex concrete structures. These include the
and the transverse prestressing cables
at deck level.
world’s largest concrete barge (the NKossa barge in France),
The arch rib is already completed and one of the largest concrete multi-cell rectangular reservoirs
the upper part is under construction. (the Warragamba waste water plant in Australia), the
T h e Ta k a m a t u B r i d g e h a s t h e l o n g e s t c o n c r e t e a r c h s p a n e v e r b u i l t i n J a p a n .
The overall project, for which first catenary moored floating platform (the Troll Oil Production
G r a n d C e n t r a l To w e r - S o u t h A f r i c a
construction works began in March
This reinforced concrete fixed arch Taisei Corporation and Kawada 1999, is schedule for completion by Horizontal PT for this 40-m high unusual platform in Norway), one of the longest pre-assembled
bridge is located in the northern part Construction Co. Ltd Joint Venture. October 2000. ■
cone-shaped structure. concrete immersed tunnels (the MTR 502 in Hong Kong) and
of Miyazaki Prefecture in Kyushu. the first egg-shape digesters in Singapore (the Kranji Egg).
Owned by Nishiusuki Branch Agency, With a length of 463.2 m and a width of M o t o h a r u Ko n o
Miyazaki Prefecture, it is built by the 6.25 m (roadway) plus 1.5 m (sidewalk), VS L J a p a n

- S PA I N -
- USA - L N G TA N K AT C A RTAG E N A
M AY S V I L L E S T AY CABLE BRIDGE - KENTUCKY This allows each tendon to be
stressed in one operation to its final
VSL recently completed the first half The bridge consists of 2 cast-in-place load configuration. The Stronghold
of a cable-stayed bridge in Maysville, pylons rising 93 m (305 ft.) above G3-1000 jacks were adapted in CTT’s
Kentucky. The 710-m long bridge the water line. factory in Barcelona to fit the VSL
(2,330-ft) spans the Ohio River and There are a total of 80 stays ranging Anchorages. The 270 vertical tendons
uses VSL’s Monostrand System 200. in size from 24 to 43 strands. (VSL E6-19) are anchored at the top
The Maysville bridge is the first of the tank. A total of 540 anchorages
cable-stayed bridge in the United The anchor piers and approach spans will be stressed and 54 additional
States to use co-extruded stay pipe were constructed concurrently with vertical tendons (9 per buttress)
and strand-by-strand installation. the pylons. The structural steel edge installed. Galvanised steel U tubes
girders are 167 cm and 213 cm and thermo-retractable duct couplers
VSL’s scope of works included stay (66 inch and 84 inch) in height and have been placed in order to ease the
testing, design and manufacturing, the floor beams are spaced at 4.8-m strand threading and assure the water
and shop prefabrication of anchors. centres (16 ft.). The main span grid The 135,000-m3 LNG tank requires 1,000 t of vertical and horizontal tendons. tightness of the galvanised duct.
VSL also provided stay installation structural steel sections are 15 m long VSL’s works started at the end of 1998.
equipment, stressing equipment, by 16.7 m wide (50-ft. x 55-ft.) and Located in Cartagena, on Spain’s The main contractor, Ferrovial-Agroman Up to now, 42 (out of 57) horizontal
and technical assistance for the weigh approximately 41 t. Overall eastern coast, this LNG tank is an (one of Spain’s major contractors) tendons have been installed, stressed
stay installation. roadway width is 14.6 m (48 ft.). ■ extension to the plant owned by sub-contracted all the transversal and and grouted. The last horizontal
Enagas, the Spanish Gas Company. horizontal PT to VSL. tendons and all the vertical tendons
Consisting of steel edge girders, John Crigler The horizontal cables are anchored will be installed, stressed and grouted
transverse floor beams and precast VS t r u c t u ra l L l c . The tank, designed to store a total in three alternate buttresses placed in the last quarter of 2000 and the first
deck panels, the 320-m long main volume of 135,000 m3 of liquefied at 120° from one another. The 57 units quarter of 2001. ■
span superstructure (1,050 ft.) The first US stay cable bridge using
natural gas, is a 40-m high concrete (VSL E6-31 tendons) are stressed
was erected using the balanced co-extruded pipe and strand-by- cylinder with an internal diameter of simultaneously using three 1,000-t Pe d ro Fe r re r
cantilever method. strand installation 67 m and 6 vertical buttresses. capacity jacks. C T T S t ro n g h o l d

12 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 13
PT
I N S P E C I A L
BRIDGES STRUCTURES

- J A PA N -
TA K A M AT U B R I D G E Without post-tensioning, many special structures could not
be built. VSL has adapted post-tensioning principles to a wide
the Takamatu Bridge has a 260-m long range of civil engineering structures such as LNG/LPG tanks,
arch span, making it the longest water reservoirs, wastewater plant digesters, underground
concrete arched bridge span in Japan
and the 10th in the world.
tunnels, off-shore platforms, concrete floating barges and dams.
For the first time in Japan, the erection
of the arch rib was executed by For these types of structures, requiring strict quality control and
combining Truss and Melan methods. flawless performance, post-tensioning provides cost savings,
speeds up construction, improves durability and is virtually
VSL’s method was adopted for the
installation of external cables at the maintenance-free.
arch rib, as well as for the upper deck
slab back stay cables, diagonal Over the years, VSL has been involved in a number of highly
suspension cables and main cables, prestigious and complex concrete structures. These include the
and the transverse prestressing cables
at deck level.
world’s largest concrete barge (the NKossa barge in France),
The arch rib is already completed and one of the largest concrete multi-cell rectangular reservoirs
the upper part is under construction. (the Warragamba waste water plant in Australia), the
T h e Ta k a m a t u B r i d g e h a s t h e l o n g e s t c o n c r e t e a r c h s p a n e v e r b u i l t i n J a p a n .
The overall project, for which first catenary moored floating platform (the Troll Oil Production
G r a n d C e n t r a l To w e r - S o u t h A f r i c a
construction works began in March
This reinforced concrete fixed arch Taisei Corporation and Kawada 1999, is schedule for completion by Horizontal PT for this 40-m high unusual platform in Norway), one of the longest pre-assembled
bridge is located in the northern part Construction Co. Ltd Joint Venture. October 2000. ■
cone-shaped structure. concrete immersed tunnels (the MTR 502 in Hong Kong) and
of Miyazaki Prefecture in Kyushu. the first egg-shape digesters in Singapore (the Kranji Egg).
Owned by Nishiusuki Branch Agency, With a length of 463.2 m and a width of M o t o h a r u Ko n o
Miyazaki Prefecture, it is built by the 6.25 m (roadway) plus 1.5 m (sidewalk), VS L J a p a n

- S PA I N -
- USA - L N G TA N K AT C A RTAG E N A
M AY S V I L L E S T AY CABLE BRIDGE - KENTUCKY This allows each tendon to be
stressed in one operation to its final
VSL recently completed the first half The bridge consists of 2 cast-in-place load configuration. The Stronghold
of a cable-stayed bridge in Maysville, pylons rising 93 m (305 ft.) above G3-1000 jacks were adapted in CTT’s
Kentucky. The 710-m long bridge the water line. factory in Barcelona to fit the VSL
(2,330-ft) spans the Ohio River and There are a total of 80 stays ranging Anchorages. The 270 vertical tendons
uses VSL’s Monostrand System 200. in size from 24 to 43 strands. (VSL E6-19) are anchored at the top
The Maysville bridge is the first of the tank. A total of 540 anchorages
cable-stayed bridge in the United The anchor piers and approach spans will be stressed and 54 additional
States to use co-extruded stay pipe were constructed concurrently with vertical tendons (9 per buttress)
and strand-by-strand installation. the pylons. The structural steel edge installed. Galvanised steel U tubes
girders are 167 cm and 213 cm and thermo-retractable duct couplers
VSL’s scope of works included stay (66 inch and 84 inch) in height and have been placed in order to ease the
testing, design and manufacturing, the floor beams are spaced at 4.8-m strand threading and assure the water
and shop prefabrication of anchors. centres (16 ft.). The main span grid The 135,000-m3 LNG tank requires 1,000 t of vertical and horizontal tendons. tightness of the galvanised duct.
VSL also provided stay installation structural steel sections are 15 m long VSL’s works started at the end of 1998.
equipment, stressing equipment, by 16.7 m wide (50-ft. x 55-ft.) and Located in Cartagena, on Spain’s The main contractor, Ferrovial-Agroman Up to now, 42 (out of 57) horizontal
and technical assistance for the weigh approximately 41 t. Overall eastern coast, this LNG tank is an (one of Spain’s major contractors) tendons have been installed, stressed
stay installation. roadway width is 14.6 m (48 ft.). ■ extension to the plant owned by sub-contracted all the transversal and and grouted. The last horizontal
Enagas, the Spanish Gas Company. horizontal PT to VSL. tendons and all the vertical tendons
Consisting of steel edge girders, John Crigler The horizontal cables are anchored will be installed, stressed and grouted
transverse floor beams and precast VS t r u c t u ra l L l c . The tank, designed to store a total in three alternate buttresses placed in the last quarter of 2000 and the first
deck panels, the 320-m long main volume of 135,000 m3 of liquefied at 120° from one another. The 57 units quarter of 2001. ■
span superstructure (1,050 ft.) The first US stay cable bridge using
natural gas, is a 40-m high concrete (VSL E6-31 tendons) are stressed
was erected using the balanced co-extruded pipe and strand-by- cylinder with an internal diameter of simultaneously using three 1,000-t Pe d ro Fe r re r
cantilever method. strand installation 67 m and 6 vertical buttresses. capacity jacks. C T T S t ro n g h o l d

12 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 13
PT PT
I N S P E C I A L I N S P E C I A L
STRUCTURES STRUCTURES

- AUSTRALIA - - VIETNAM -
DUNGOWAN DAM NGHISON CEMENT PLANT
Dungowan Dam is located 60 km Southeast of Tamworth, in central New South Wales (NSW). The Nghison Cement Plant Project in VSL was awarded the contract for two 44-m high clinker silos
Vietnam’s Thanh Hoa Province was an alternative design using post- (23-m diameter), two 46-m high
The dam is owned by the Tamworth City Council and supplies a significant proportion
completed in April 2000 by the tensioning for the Plant’s seven silos. blending silos (18-m diameter)
of the city’s water requirement. Shimizu / Vinaconex / Hacc J.V. VSL’s Technical Centre in Singapore and one 37-m high limestone silo
The project represents a world first for the installation of special permanent anchors. designed the 7 prestressed concrete (24-m diameter).
silos in co-operation with the Shimizu Along with the Morning Star cement
In 1996, a wedge failure occurred The DPWS design was unusual, as the also capable of travelling the 62.5-m Head Office Technical department. plant, completed in 1997, and the
on the eastern ridge of the dam design parameter required that, on depth of hole. The airlift basically Slipforming and heavy lifting Hoang Mai cement plant, currently
which supports the fuse-plug. completion, the anchors formed a vacuumed the drill hole clean. methods were proposed as under construction, Nghison
The NSW Department of Public Works single continuous bond length. This Due to the secondary grouting economical solutions to lift the represents VSL’s third reference
& Services (DPWS), on behalf of the ensured that no rock mass movement requirement of these anchors and the assembled roof at the same time as in Vietnam.
Tamworth Council, designed the could take place due to cable plunging effect needed to successfully the slipform operations, reducing the Benefiting from the VSL Group’s
remedial works to be carried out extension. This requirement was met install such flat long anchors, VSL construction time for each silo to an network and experience, VSL Vietnam
and was also engaged as the by the secondary grouting of the free decided to pre-grout the bond length average of one month. confirmed its ability to locally provide
Project Manager. anchor length on completion of the prior to installation. This was achieved its customers with top quality
In 1998, the DPWS contracted one stressing works. by building a project specific fabrication Under the leadership of Project engineering solutions and high
of VSL’s competitors to carry out Manager Geoff Mc Kinnirey, quality works. ■
the excavations and anchoring for the VSL installed 430 t of PT strands
remedial works. In early 1999 the for two 60-m high cement silos L a u re n t P E G U R E T
DPWS went into dispute with the (22-m and 28-m diameter), VS L Vi e t n a m
contractor who was unable to
complete an extremely complicated
part of the works. By the end of
July 1999 the DPWS had terminated - INDIA -
the contract and engaged VSL to carry
out the remainder of the works. DA B H O L , P H A S E 2 L N G TA N K
The project entailed VSL taking on Three 200,000-m3 gas-fuelled power with the main contractor’s works (hydraulic jacks, pumps, strand
the role of main contractor and production LNG tanks are currently schedule. pushing machine, strand decoilers and
establishing a full site compound in under construction in Dabhol, about grout mixers) and technical assistance
this remote area. The remedial works 500 km south of Mumbai. In addition to the supply of PT including site supervision during duct
involved stabilisation with rock bolts Owned by the Dabhol Power Company, materials, including anchorages, installation and PT operations. ■
and mesh, the grouting up of the this type of tank is the first of its kind corrugated steel ducts for horizontal
previous contractor’s failed anchor The permanent anchors (8 x 15.2mm bed and using a special steel in India. LNG Tanks are considered as and vertical U-shaped tendons, VSL is R. M. Ganesh
systems, the installation of five rock and 58m long) with a 8.0-m bond transportation/installation cradle. highly critical and sensitive structures, also providing all PT equipment VS L I n d i a
anchors and the construction of length and a 50-m free length have the After completion of the stressing and and VSL PT systems were able to meet
five large reinforced concrete particularity of only being inclined at monitoring requirements, the anchors the stringent requirements.
reaction pads. 20 degrees below the horizontal. had to receive secondary grouting. The 80-m diameter and 40-m high
The drilling works required a 200-mm Again, due to the length and flatness tanks have a 600-mm wall thickness
diameter hole to be accurately drilled to of the anchors, the DPWS specified a throughout and a 900-mm thick ring
62.5 m in highly fractured ground and at grout flow of 5 litres per minute. beam at the top. The walls are
this flat inclination. This was achieved Once the inner annulus was full, horizontally and vertically stressed
using a customised “fatboy” directly a constant pressure of 100 kPa had to with VSL6-19S tendons, representing
behind the down-the-hole hammer and be maintained on the grout column for a total of 166 horizontal tendons
large diameter stabilised drill rods. a 45-minute period to ensure that (125-m long) and 64 vertical tendons
On completion of the anchor hole, the trapped air and water were forced out (40-m high). The PT tonnage per tank
next challenge was to successfully of the sheathing corrugations. is approximately 600 metric tonnes.
clean the hole of all drilling debris. These permanent anchors are a world Each tank is cast in 11 lifts and each
Standard industry practice techniques first for such a low inclination at this casting height lift is restricted to
could not be used due to the flatness length. ■ 3.75m. Strand installation and
of these long anchors. VSL constructed stressing operations are scheduled
an air-lift system small enough to fit Mick Holland to begin once the tank walls are
inside the 200-mm diameter hole but VS L A u s t ra l i a completed and will strictly comply

14 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 15
PT PT
I N S P E C I A L I N S P E C I A L
STRUCTURES STRUCTURES

- AUSTRALIA - - VIETNAM -
DUNGOWAN DAM NGHISON CEMENT PLANT
Dungowan Dam is located 60 km Southeast of Tamworth, in central New South Wales (NSW). The Nghison Cement Plant Project in VSL was awarded the contract for two 44-m high clinker silos
Vietnam’s Thanh Hoa Province was an alternative design using post- (23-m diameter), two 46-m high
The dam is owned by the Tamworth City Council and supplies a significant proportion
completed in April 2000 by the tensioning for the Plant’s seven silos. blending silos (18-m diameter)
of the city’s water requirement. Shimizu / Vinaconex / Hacc J.V. VSL’s Technical Centre in Singapore and one 37-m high limestone silo
The project represents a world first for the installation of special permanent anchors. designed the 7 prestressed concrete (24-m diameter).
silos in co-operation with the Shimizu Along with the Morning Star cement
In 1996, a wedge failure occurred The DPWS design was unusual, as the also capable of travelling the 62.5-m Head Office Technical department. plant, completed in 1997, and the
on the eastern ridge of the dam design parameter required that, on depth of hole. The airlift basically Slipforming and heavy lifting Hoang Mai cement plant, currently
which supports the fuse-plug. completion, the anchors formed a vacuumed the drill hole clean. methods were proposed as under construction, Nghison
The NSW Department of Public Works single continuous bond length. This Due to the secondary grouting economical solutions to lift the represents VSL’s third reference
& Services (DPWS), on behalf of the ensured that no rock mass movement requirement of these anchors and the assembled roof at the same time as in Vietnam.
Tamworth Council, designed the could take place due to cable plunging effect needed to successfully the slipform operations, reducing the Benefiting from the VSL Group’s
remedial works to be carried out extension. This requirement was met install such flat long anchors, VSL construction time for each silo to an network and experience, VSL Vietnam
and was also engaged as the by the secondary grouting of the free decided to pre-grout the bond length average of one month. confirmed its ability to locally provide
Project Manager. anchor length on completion of the prior to installation. This was achieved its customers with top quality
In 1998, the DPWS contracted one stressing works. by building a project specific fabrication Under the leadership of Project engineering solutions and high
of VSL’s competitors to carry out Manager Geoff Mc Kinnirey, quality works. ■
the excavations and anchoring for the VSL installed 430 t of PT strands
remedial works. In early 1999 the for two 60-m high cement silos L a u re n t P E G U R E T
DPWS went into dispute with the (22-m and 28-m diameter), VS L Vi e t n a m
contractor who was unable to
complete an extremely complicated
part of the works. By the end of
July 1999 the DPWS had terminated - INDIA -
the contract and engaged VSL to carry
out the remainder of the works. DA B H O L , P H A S E 2 L N G TA N K
The project entailed VSL taking on Three 200,000-m3 gas-fuelled power with the main contractor’s works (hydraulic jacks, pumps, strand
the role of main contractor and production LNG tanks are currently schedule. pushing machine, strand decoilers and
establishing a full site compound in under construction in Dabhol, about grout mixers) and technical assistance
this remote area. The remedial works 500 km south of Mumbai. In addition to the supply of PT including site supervision during duct
involved stabilisation with rock bolts Owned by the Dabhol Power Company, materials, including anchorages, installation and PT operations. ■
and mesh, the grouting up of the this type of tank is the first of its kind corrugated steel ducts for horizontal
previous contractor’s failed anchor The permanent anchors (8 x 15.2mm bed and using a special steel in India. LNG Tanks are considered as and vertical U-shaped tendons, VSL is R. M. Ganesh
systems, the installation of five rock and 58m long) with a 8.0-m bond transportation/installation cradle. highly critical and sensitive structures, also providing all PT equipment VS L I n d i a
anchors and the construction of length and a 50-m free length have the After completion of the stressing and and VSL PT systems were able to meet
five large reinforced concrete particularity of only being inclined at monitoring requirements, the anchors the stringent requirements.
reaction pads. 20 degrees below the horizontal. had to receive secondary grouting. The 80-m diameter and 40-m high
The drilling works required a 200-mm Again, due to the length and flatness tanks have a 600-mm wall thickness
diameter hole to be accurately drilled to of the anchors, the DPWS specified a throughout and a 900-mm thick ring
62.5 m in highly fractured ground and at grout flow of 5 litres per minute. beam at the top. The walls are
this flat inclination. This was achieved Once the inner annulus was full, horizontally and vertically stressed
using a customised “fatboy” directly a constant pressure of 100 kPa had to with VSL6-19S tendons, representing
behind the down-the-hole hammer and be maintained on the grout column for a total of 166 horizontal tendons
large diameter stabilised drill rods. a 45-minute period to ensure that (125-m long) and 64 vertical tendons
On completion of the anchor hole, the trapped air and water were forced out (40-m high). The PT tonnage per tank
next challenge was to successfully of the sheathing corrugations. is approximately 600 metric tonnes.
clean the hole of all drilling debris. These permanent anchors are a world Each tank is cast in 11 lifts and each
Standard industry practice techniques first for such a low inclination at this casting height lift is restricted to
could not be used due to the flatness length. ■ 3.75m. Strand installation and
of these long anchors. VSL constructed stressing operations are scheduled
an air-lift system small enough to fit Mick Holland to begin once the tank walls are
inside the 200-mm diameter hole but VS L A u s t ra l i a completed and will strictly comply

14 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 15
PT PT
I N S P E C I A L I N S P E C I A L
STRUCTURES STRUCTURES

- AUSTRALIA - - SINGAPORE -
C R O N U L L A S E W E R AG E T R E AT M E N T PL A N T UL U PA N DA N S E W AG E T R E AT M E N T W O R K S
Following the Lend Lease Projects (LLP) All the walls are cast in-situ with the The post-tensioning uses VSL’s
award for upgrading the Cronulla exception of the internal bioreactor bonded multistrand system. This is
Sewerage Treatment Plant, baffle walls which are precast on encased inside VSL PT-Plus plastic
discussions were held with members the slab. ducts to provide an additional
of the infrastructure project team Once works had begun on site and corrosion barrier. Because of its lower
towards the end of 1998 to investigate after the slab was poured, the decision friction characteristics, the use of
alternatives to their conventionally was taken to increase the bioreactor VSL’s PT-Plus plastic ducts meant that
reinforced concrete design for water structure to five cells, providing a total the number of horizontal tendon
retaining structures. of 21.6 million litres. The final size was anchorages could be reduced by 50%.
This led to VSL submitting an 50 m by 60 m with 7.2-m high walls, Due to the egg-like shape of the
alternative PT design for four and with 36-m diameter and 5.6-m digesters, the hydrostatic pressure from
5.7 million-litre circular clarifier tanks high clarifiers. the sludge creates tensile membrane
and a 4-cell 17.3 million-litre Works are progressing according to the forces in the walls in both horizontal
rectangular bioreactor structure. schedule thanks to the co-ordination and median directions. These are
Given that alternative PT structures between VSL’s on-site Project Manager balanced by VSL PT strands. While
are technically superior as they and the design team. As a result of its normal Ec type anchorages have been
require fewer joints and offer overall high performance level, VSL’s scope Owned by Singapore’s Ministry of the supported on twelve 1.3-m diameter in- used for the median cables, the
cost savings, LLP was receptive of works has been extended to include Environment, the Ulu Pandan Sewage situ bored reinforced concrete piles. 3,60o horizontal cables are individually
to VSL’s design and construct Aerial view of Cronulla Sewerage the design and construction of a Treatment Works is the third of its kind Although its height is approximately anchored and stressed using Z-type
structures package. Tr e a t m e n t P l a n t . 78.5-m long x 34-m wide biosolids to be built in Singapore. It is intended 30.7 m, only 11 m will extend above anchorages. This solution is well
An alliance was formed between structure, comprising two-way post- to meet the expected increase in ground level once it is completed. adapted to egg-shaped digesters as no
Hornick Constructions -a local specialist beginning simultaneously mid-June 99 tensioned base slabs and 2.4-m high wastewater generated by the rapid The digester walls vary in thickness external blisters are required and the
tank builder who has extensive on both the clarifier and bioreactor horizontally post-tensioned walls. residential, commercial and industrial from 600 mm near the base to 500 mm number of stressing pockets in the wall
experience in the construction of water structures. VSL expects to have a portion of the development of the area. near the top and are constructed using is minimised. In all, approximately 350 t
retaining structures- and VSL to offer a The clarifier and bioreactor base slabs site works completed by June 2000. ■ The main Contractor, Sembcorp a 35-grade concrete with a 40-mm of strands were used for each digester.
“total solution”. are designed with two-way post- Construction Pte Ltd., awarded VSL the cover. The wall thickness was The project began in December 1998
The contract was secured at the end of tensioning, while the walls only have Ro s s I o a k i m design, supply and installation of the determined to ensure a simple to build and construction will take 18 months. ■
the 1st quarter of 1999 with site works horizontal post-tensioning. VS L A u s t ra l i a PT Plus System for the 8 egg-shaped and watertight structure that would
sludge digesters. Each digester has a allow the concrete to be easily poured Pa t r i c k Wo o
maximum diameter of 21 m and is and vibrated. VS L S i n g a p o re

- MOZAMBIQUE -
MOZAL ALUMINA SILO - USA -
The Mozambique Aluminum (Mozal) E R I E Z O N E 3 TA N K
Smelter project is situated in Maputo,
Mozambique. Owned by Mozambique VSL recently completed construction 5-12 strand tendons horizontally in The wall was cast in eight individual
Aluminum Ltd, it will provide much of the 5.7 million-litre Erie Reservoir the wall, and flat PT-Plus duct with full-height segments, including
needed export revenue for the (1.5 million-gallon) in Colorado. SO6-4 anchorages vertically in the wall. 4 pilaster segments, and the floor and
country. The overall dimensions of the state-of- A special grout containing microsilica roof slabs were each cast in a single
art, fully encapsulated structure are was used. pour to eliminate the maintenance
The 45,000-t capacity aluminium oxide 34-m (110-ft.) in diameter by 7-m high problems associated with horizontal
storage silo, built by Group Five Civils (23-ft.). construction joints.
and Conform J.V, is post-tensioned The project engineer, Denver-based
using VSL’s multistrand bonded Bates Engineering Incorporated, The scope of VSL’s works included
system. The 40-m high silo has an required enhanced corrosion placing the post-tensioning systems
internal diameter of 40.6 m and a wall The walls of the silo were slipformed VSL supplied the materials and carried protection of the post-tensioning and mild reinforcement, as well as
thickness of 400 mm. over a 15-day period. This was out the threading, stressing and systems to maximise the service life of friction testing and providing the
It is post-tensioned with 98 horizontal followed by the casting of a ring beam grouting operations from August to the structure. VSL provided this post-tensioning systems. ■
rings of 21 Ø and 12.9-mm strand to support the cast in-situ dome roof. November 1999. ■ through the use of the VSL S-6
tendons alternating over 180 degrees, Strands (130 t) were then pushed into B r i a n C ox monostrand system in the floor and D a n H a rg e r
i.e. 4 buttresses. the cast-in ducts. VS L S o u t h A f r i c a roof slabs, circular PT-Plus duct with VS t r u c t u ra l L l c .

16 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 17
PT PT
I N S P E C I A L I N S P E C I A L
STRUCTURES STRUCTURES

- AUSTRALIA - - SINGAPORE -
C R O N U L L A S E W E R AG E T R E AT M E N T PL A N T UL U PA N DA N S E W AG E T R E AT M E N T W O R K S
Following the Lend Lease Projects (LLP) All the walls are cast in-situ with the The post-tensioning uses VSL’s
award for upgrading the Cronulla exception of the internal bioreactor bonded multistrand system. This is
Sewerage Treatment Plant, baffle walls which are precast on encased inside VSL PT-Plus plastic
discussions were held with members the slab. ducts to provide an additional
of the infrastructure project team Once works had begun on site and corrosion barrier. Because of its lower
towards the end of 1998 to investigate after the slab was poured, the decision friction characteristics, the use of
alternatives to their conventionally was taken to increase the bioreactor VSL’s PT-Plus plastic ducts meant that
reinforced concrete design for water structure to five cells, providing a total the number of horizontal tendon
retaining structures. of 21.6 million litres. The final size was anchorages could be reduced by 50%.
This led to VSL submitting an 50 m by 60 m with 7.2-m high walls, Due to the egg-like shape of the
alternative PT design for four and with 36-m diameter and 5.6-m digesters, the hydrostatic pressure from
5.7 million-litre circular clarifier tanks high clarifiers. the sludge creates tensile membrane
and a 4-cell 17.3 million-litre Works are progressing according to the forces in the walls in both horizontal
rectangular bioreactor structure. schedule thanks to the co-ordination and median directions. These are
Given that alternative PT structures between VSL’s on-site Project Manager balanced by VSL PT strands. While
are technically superior as they and the design team. As a result of its normal Ec type anchorages have been
require fewer joints and offer overall high performance level, VSL’s scope Owned by Singapore’s Ministry of the supported on twelve 1.3-m diameter in- used for the median cables, the
cost savings, LLP was receptive of works has been extended to include Environment, the Ulu Pandan Sewage situ bored reinforced concrete piles. 3,60o horizontal cables are individually
to VSL’s design and construct Aerial view of Cronulla Sewerage the design and construction of a Treatment Works is the third of its kind Although its height is approximately anchored and stressed using Z-type
structures package. Tr e a t m e n t P l a n t . 78.5-m long x 34-m wide biosolids to be built in Singapore. It is intended 30.7 m, only 11 m will extend above anchorages. This solution is well
An alliance was formed between structure, comprising two-way post- to meet the expected increase in ground level once it is completed. adapted to egg-shaped digesters as no
Hornick Constructions -a local specialist beginning simultaneously mid-June 99 tensioned base slabs and 2.4-m high wastewater generated by the rapid The digester walls vary in thickness external blisters are required and the
tank builder who has extensive on both the clarifier and bioreactor horizontally post-tensioned walls. residential, commercial and industrial from 600 mm near the base to 500 mm number of stressing pockets in the wall
experience in the construction of water structures. VSL expects to have a portion of the development of the area. near the top and are constructed using is minimised. In all, approximately 350 t
retaining structures- and VSL to offer a The clarifier and bioreactor base slabs site works completed by June 2000. ■ The main Contractor, Sembcorp a 35-grade concrete with a 40-mm of strands were used for each digester.
“total solution”. are designed with two-way post- Construction Pte Ltd., awarded VSL the cover. The wall thickness was The project began in December 1998
The contract was secured at the end of tensioning, while the walls only have Ro s s I o a k i m design, supply and installation of the determined to ensure a simple to build and construction will take 18 months. ■
the 1st quarter of 1999 with site works horizontal post-tensioning. VS L A u s t ra l i a PT Plus System for the 8 egg-shaped and watertight structure that would
sludge digesters. Each digester has a allow the concrete to be easily poured Pa t r i c k Wo o
maximum diameter of 21 m and is and vibrated. VS L S i n g a p o re

- MOZAMBIQUE -
MOZAL ALUMINA SILO - USA -
The Mozambique Aluminum (Mozal) E R I E Z O N E 3 TA N K
Smelter project is situated in Maputo,
Mozambique. Owned by Mozambique VSL recently completed construction 5-12 strand tendons horizontally in The wall was cast in eight individual
Aluminum Ltd, it will provide much of the 5.7 million-litre Erie Reservoir the wall, and flat PT-Plus duct with full-height segments, including
needed export revenue for the (1.5 million-gallon) in Colorado. SO6-4 anchorages vertically in the wall. 4 pilaster segments, and the floor and
country. The overall dimensions of the state-of- A special grout containing microsilica roof slabs were each cast in a single
art, fully encapsulated structure are was used. pour to eliminate the maintenance
The 45,000-t capacity aluminium oxide 34-m (110-ft.) in diameter by 7-m high problems associated with horizontal
storage silo, built by Group Five Civils (23-ft.). construction joints.
and Conform J.V, is post-tensioned The project engineer, Denver-based
using VSL’s multistrand bonded Bates Engineering Incorporated, The scope of VSL’s works included
system. The 40-m high silo has an required enhanced corrosion placing the post-tensioning systems
internal diameter of 40.6 m and a wall The walls of the silo were slipformed VSL supplied the materials and carried protection of the post-tensioning and mild reinforcement, as well as
thickness of 400 mm. over a 15-day period. This was out the threading, stressing and systems to maximise the service life of friction testing and providing the
It is post-tensioned with 98 horizontal followed by the casting of a ring beam grouting operations from August to the structure. VSL provided this post-tensioning systems. ■
rings of 21 Ø and 12.9-mm strand to support the cast in-situ dome roof. November 1999. ■ through the use of the VSL S-6
tendons alternating over 180 degrees, Strands (130 t) were then pushed into B r i a n C ox monostrand system in the floor and D a n H a rg e r
i.e. 4 buttresses. the cast-in ducts. VS L S o u t h A f r i c a roof slabs, circular PT-Plus duct with VS t r u c t u ra l L l c .

16 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 17
YOUR LOCAL CONSTRUCTION PARTNER YOUR LOCAL CONSTRUCTION PARTNER

VSL Sistemas Portugal VSL for the installation of external


post-tensioning bars using high
density of polyethylene ducts.
Post-tensioning bars were designed
Since 1985, along both sides of the beams and the
VSL has continued to develop as anchorages were incorporated into
concrete blocks.
a strong and successful post-tensioning Using internal bars, these blocks were
transversal post-tensioned into
sub-contractor in Portugal. beam’s web.

● Fonte Nova Viaduct in Lisbon: Although the structure was


structural repairs highly damaged, it could not
and strengthening (1999) be demolished due to the
The Fonte Nova Viaduct, owned by unacceptable traffic
the Lisbon Municipal Council, forms disruption this would cause.
part of one of the most important The main contractor, Soproel,
roads around Lisbon, linking the responsible for the structural
International Airport to major repairs and strengthening of
Portuguese highways. the bridge, sub-contracted
The presence of VSL in the Given Prequipe’s strong position in its
Portuguese market goes back to the specialised market and the gradual
early seventies, when it was growth of the Portuguese public The new subsidiary, called A second phase is programmed committed to a quality policy and
introduced through an important works sector, VSL International Ltd. “VSL Prequipe S.A.”, went through from 2004/5 to 2010 with more should very soon become the
local company, Novobra S.A., which acquired a majority holding in the continuous growth over this period private motorway concessions, first post-tensioning sub-contractor
acted as an exclusive licensee. company in 1990, and subsequently and, in 1997, its turnover attained a and large-scale projects such as the to obtain ISO 9002 Certification in
acquired a 100% holding in 1995. peak of USD 12 million. new Lisbon airport, a high speed Portugal.
Following Novobra’s bankruptcy in At the same time, the VSL Group was railway programme, as well as one
1984, a new company, Prequipe S.A., also the 50% shareholder of another or even two new bridges across the This will be the result of a policy of
took over the VSL license and rapidly Portuguese company, Stronghold river Tagus. confidence and continuous
developed as a small dynamic Portugal S.A. In August 1998, In order to prepare for this investment by the VSL Group in
structure specialised in post- the Group decided to amalgamate construction boom, VSL Sistemas Portugal over the last ten years. ■
tensioning activities. Stronghold Portugal and Portugal increased its staff level at
VSL Prequipe. This merger between the end of 1999 and now has a total C a r l o s M o n i z & Ze n ó b i a Q . M a r t i n s
the two entities led to the creation of 79 employees. VS L S i s t e m a s Po r t u g a l
of “VSL Sistemas Portugal S.A.”.
A part from maintaining a leading
Following the slump of Portuguese position in its core business and
● Combóio Viaduct in Madeira civil works market in 1998 and 1999 related activities (post-tensioning,
Island: PT and stay cables which seriously affected the bearings and joints, retained earth
(1999/2000) company’s activity (USD 6.3 million), and geotechnical services, heavy
The Combóio Viaduct is the VSL Sistemas should now benefit lifting, special equipment, etc…)
first Portuguese bridge to be the deck axis. The 21.5-m wide deck from a major 5-year infrastructures the company also wishes to increase
equipped with VSL Stay Cables. is a single post-tensioned box beam investment programme. its stay cable activity and diversify
Owned by the Madeira Regional and will carry two traffic lanes in This includes new projects such its services and products, especially
Government and built by Soares da each direction. as private motorway concessions, in the structural repairs sector.
Costa, this viaduct is located in a In addition to the post-tensioning sports infrastructures for Euro 2004,
rather densely populated area of The viaduct, designed as a stay cable and stay cable works (replaceable the expansion of the Lisbon metro, In addition to its corporate vision,
Funchal city and forms part of the bridge, has a 92-m long main span strand-by-strand stay cables), the construction of the Porto metro, recent developments based on
Funchal ring road programme and two 25-m high pylons above the VSL Sistemas Portugal will also railway rehabilitation and modern tools (internet and intranet
currently under construction. deck, each supporting 2 x 7 stays in supply the bearings and joints. preparations for high speed solutions), and specialised contractor
train tracks. qualifications, VSL Sistemas is also

18 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 19
YOUR LOCAL CONSTRUCTION PARTNER YOUR LOCAL CONSTRUCTION PARTNER

VSL Sistemas Portugal VSL for the installation of external


post-tensioning bars using high
density of polyethylene ducts.
Post-tensioning bars were designed
Since 1985, along both sides of the beams and the
VSL has continued to develop as anchorages were incorporated into
concrete blocks.
a strong and successful post-tensioning Using internal bars, these blocks were
transversal post-tensioned into
sub-contractor in Portugal. beam’s web.

● Fonte Nova Viaduct in Lisbon: Although the structure was


structural repairs highly damaged, it could not
and strengthening (1999) be demolished due to the
The Fonte Nova Viaduct, owned by unacceptable traffic
the Lisbon Municipal Council, forms disruption this would cause.
part of one of the most important The main contractor, Soproel,
roads around Lisbon, linking the responsible for the structural
International Airport to major repairs and strengthening of
Portuguese highways. the bridge, sub-contracted
The presence of VSL in the Given Prequipe’s strong position in its
Portuguese market goes back to the specialised market and the gradual
early seventies, when it was growth of the Portuguese public The new subsidiary, called A second phase is programmed committed to a quality policy and
introduced through an important works sector, VSL International Ltd. “VSL Prequipe S.A.”, went through from 2004/5 to 2010 with more should very soon become the
local company, Novobra S.A., which acquired a majority holding in the continuous growth over this period private motorway concessions, first post-tensioning sub-contractor
acted as an exclusive licensee. company in 1990, and subsequently and, in 1997, its turnover attained a and large-scale projects such as the to obtain ISO 9002 Certification in
acquired a 100% holding in 1995. peak of USD 12 million. new Lisbon airport, a high speed Portugal.
Following Novobra’s bankruptcy in At the same time, the VSL Group was railway programme, as well as one
1984, a new company, Prequipe S.A., also the 50% shareholder of another or even two new bridges across the This will be the result of a policy of
took over the VSL license and rapidly Portuguese company, Stronghold river Tagus. confidence and continuous
developed as a small dynamic Portugal S.A. In August 1998, In order to prepare for this investment by the VSL Group in
structure specialised in post- the Group decided to amalgamate construction boom, VSL Sistemas Portugal over the last ten years. ■
tensioning activities. Stronghold Portugal and Portugal increased its staff level at
VSL Prequipe. This merger between the end of 1999 and now has a total C a r l o s M o n i z & Ze n ó b i a Q . M a r t i n s
the two entities led to the creation of 79 employees. VS L S i s t e m a s Po r t u g a l
of “VSL Sistemas Portugal S.A.”.
A part from maintaining a leading
Following the slump of Portuguese position in its core business and
● Combóio Viaduct in Madeira civil works market in 1998 and 1999 related activities (post-tensioning,
Island: PT and stay cables which seriously affected the bearings and joints, retained earth
(1999/2000) company’s activity (USD 6.3 million), and geotechnical services, heavy
The Combóio Viaduct is the VSL Sistemas should now benefit lifting, special equipment, etc…)
first Portuguese bridge to be the deck axis. The 21.5-m wide deck from a major 5-year infrastructures the company also wishes to increase
equipped with VSL Stay Cables. is a single post-tensioned box beam investment programme. its stay cable activity and diversify
Owned by the Madeira Regional and will carry two traffic lanes in This includes new projects such its services and products, especially
Government and built by Soares da each direction. as private motorway concessions, in the structural repairs sector.
Costa, this viaduct is located in a In addition to the post-tensioning sports infrastructures for Euro 2004,
rather densely populated area of The viaduct, designed as a stay cable and stay cable works (replaceable the expansion of the Lisbon metro, In addition to its corporate vision,
Funchal city and forms part of the bridge, has a 92-m long main span strand-by-strand stay cables), the construction of the Porto metro, recent developments based on
Funchal ring road programme and two 25-m high pylons above the VSL Sistemas Portugal will also railway rehabilitation and modern tools (internet and intranet
currently under construction. deck, each supporting 2 x 7 stays in supply the bearings and joints. preparations for high speed solutions), and specialised contractor
train tracks. qualifications, VSL Sistemas is also

18 N ° 1 • 2 0 0 0 N ° 1 • 2 0 0 0 19
Your solution network
HEADQUARTERS
VSL International Ltd.
Bernstrasse 9 - LYSSACH - CH 3421 - Switzerland
Phone : 41 - 34 - 447 99 11 - Fax : 41 - 34 - 445 43 22
http:\\www.vsl-intl.com I S S U E O N E 2 0 0 0

Australia / South East North East Central East Western Europe,


Pacific territories Asia Asia Europe and Africa and
Middle East Latin America
REGIONAL OFFICE REGIONAL OFFICE REGIONAL OFFICE
VSL Prestressing (Aust.) Pty. Ltd. VSL Singapore Pte. Ltd. VSL North East Asia
6 Pioneer Avenue 75 Bukit Timah Road 3/F Stelux House REGIONAL OFFICE REGIONAL OFFICE
THORNLEIGH, NSW 2120 04-08 Boon Siew Building 698 Prince Edward Road East VSL (Switzerland) Ltd L’Odyssée - Bât. A
AUSTRALIA Singapore 229833 San Po Kong / Kowloon Bernstrasse 9 2-12 Chemin des Femmes
Phone: +61 - 2 - 9484 59 44 SINGAPORE HONG KONG Lyssach - CH 3421 91886 MASSY Cedex
Fax: +61 - 2 - 9875 38 94 Phone: +65 336 29 23 Phone: +852 - 2590 22 22 SWITZERLAND FRANCE
Fax: +65 337 64 61 Fax: +852 - 2590 95 93 Phone: +41 - 34- 447 99 11 Phone: +33 - 1 - 69 19 43 00
AUSTRALIA - Queensland Fax: +41 - 34- 447 99 65 Fax: +33 - 1 - 69 19 43 01
VSL Prestressing (Aust.) Pty. Ltd. BRUNEI HONG KONG
GEEBUNG VSL Systems (B) Sdn. Bhd. VSL Hong Kong Ltd. AUSTRIA ARGENTINA
Phone: +61 - 7 - 3265 64 00 BRUNEI DARUSSALAM San Po Kong / Kowloon Universale GSB VSL Sistemas Especiales de
Fax: +61 - 7 - 3265 75 34 Phone: +673 - 2 - 380 153 Phone: +852 - 2590 22 88 VIENNA Construcción Argentina SA
- 381 827 Fax: +852 - 2590 02 90 Phone: +43 - 1 - 878 170 BUENOS AIRES
AUSTRALIA - New South Fax: +673 - 2 - 381 954 Fax: +43 - 1 - 878 17 782 Phone: +54 - 11 - 4326 - 06 09
Wales JAPAN Fax: +54 - 11 - 4326 - 26 50
VSL Prestressing (Aust.) Pty. Ltd. INDIA VSL Japan Corporation CZECH REPUBLIC
THORNLEIGH VSL India Private Ltd. TOKYO VSL Systemy (CZ) s. r. o. BELGIUM
Phone: +61 - 2 - 9484 59 44 CHENNAI Phone: +81 - 3 - 3346 - 8913 PRAGUE NV Procedes VSL SA
Fax: +61 - 2 - 9875 38 94 Phone: +91-44 859 2538 / 39 Fax: +81 - 3 - 3345 - 9153 Phone: +420 - 2 - 67 07 24 20 BERCHEM
Fax: +91-44 859 2537 Fax: +420 - 2 - 67 07 24 06 Phone: +32 3 230 36 34
AUSTRALIA - Southern KOREA Fax: +32 3 230 89 65
Division INDONESIA VSL Korea Co. Ltd. GERMANY
VSL Prestressing (Aust.) Pty. Ltd. PT VSL Indonesia SEOUL VSL Systems GmbH CHILE
NOBLE PARK JAKARTA Phone: +82 - 2 - 553 8200 BERLIN VSL Sistemas Especiales de
Phone: +61 - 3 - 9795 03 66 Phone: +62 - 21 - 570 07 86 Fax: +82 - 2 - 553 8255 Phone: +49 30 53 006-0 Construcción SA
Fax: +61 - 3 - 9795 05 47 Fax: +62 - 21 - 573 12 17 Fax: +49 30 53 006-37 SANTIAGO
MAINLAND CHINA Phone: +56 - 2 - 233 10 81
GUAM MALAYSIA VSL Engineering Corp., PRC POLAND Fax: +56 - 2 - 233 67 39
Structural Technologies Inc. VSL Engineers (M) Sdn. Bhd. Anhui Province, HEIFEI VSL Polska Sp. z o.o.
TUMON KUALA LUMPUR Phone: +86 - 551 - 557 6008 WARSAW GREAT BRITAIN
Phone: +1 - 671- 646 8010 Phone: +603 - 242 47 42 Fax: +86 - 551 - 557 6018 Phone: +48-22 817 84 22 VSL Systems (UK) Ltd
Fax: +1 - 671- 646 8060 Fax: +603 - 242 93 97 Fax: +48-22 817 83 59 CAMBRIDGESHIRE
PHILIPPINES Phone: +44 - 1 - 480 860 990
SINGAPORE VSL Philippines Inc. SWITZERLAND Fax: +44 - 1 - 480 861 092
VSL Singapore Pte. Ltd. MANDALUYONG CITY VSL (Switzerland) Ltd.
SINGAPORE Phone: +632 638 76 90 LYSSACH GREECE
Phone: +65 - 336 29 23 Fax: +632 638 76 91 Phone: +41 - 34 - 447 99 11 VSL Systems A/E
North America Fax: +65 - 337 64 61 Fax: +41 - 34 - 445 43 22 ATHENS
TAIWAN Phone: +30 - 1 - 363 84 53
THAILAND VSL Taiwan Ltd VSL (Suisse) SA. Fax: +30 - 1 - 360 95 43
VStructural Llc. PENTHAZ
Regional Office VSL (Thailand) Co. Ltd. TAIPEI
BANGKOK Phone: +886 - 2 - 2759 6819 Phone: +41 - 21 - 862 80 00 MEXICO
BALTIMORE, MD Fax: +41 - 21 - 862 80 02 VSL Corporation Mexico S.A
Phone: +1 - 410 - 247 - 1016 Phone: +66 - 2 - 237 32 88/89/90 Fax: +886 - 2 - 2759 6821
Fax: +66 - 2 - 238 24 48 de C.V
Fax: +1 - 410 - 247 - 1136 UNITED ARAB EMIRATES MEXICO
VIETNAM
VSL Representative Office VSL Middle East Office Phone: +52 - 5 - 396 86 21
DALLAS, TX DUBAI Fax: +52 - 5 - 396 84 88
VStructural Llc. HANOI
Phone: +84 - 4 - 8245 488 Phone: +971 - 4 - 282 08 03
Phone: +1 - 972 - 647 - 0200 Fax: +971 - 4 - 282 94 41 NETHERLANDS
Fax: +1 - 972 - 641 - 1192 Fax: +84 - 4 - 8245 717
VSL Benelux B.V
AT LEIDEN

Photos: M. Grabowski, D. Mc Allan, Photo Basilic AG, Skycam, L. Zylberman, G. Leitao, J. Jung, X.
DENVER, CO Phone: +31 - 71 - 576 89 00
VStructural Llc. Fax: +31 - 71 - 572 08 86
Phone: +1 - 303 - 456 - 9887
Fax: +1 - 303 - 456 - 9796 NORWAY
VSL Norge A/S
WASHINGTON, DC STAVANGER
VStructural Llc. Phone: +46 - 87 - 53 02 50
Phone: +1 - 703 - 451 - 4300 Fax: +46 - 87 - 53 49 73
Fax: +1 - 703 - 451 - 0862
PORTUGAL
VSL Sistemas Portugal SA
S. DOMINGO DE RANA
Phone: +351 - 21 - 445 83 10
France Fax: +351 - 21 - 444 63 77

SOUTH AFRICA
VSL France S.A. VSL Systems (South Africa) Pty Ltd.
EGLY Kya Sand, RANDBURG
Phone: +33 - 1 - 69 26 14 00 Phone: +27 - 11 - 708 21 00
Fax: +33 - 1 - 60 83 89 95 Fax: +27 - 11 - 708 21 20

SPAIN
CTT Stronghold
BARCELONA
Phone: +34 - 93 - 200 87 11
Fax: +34 - 93 - 209 85 90

SWEDEN
Internordisk Spännarmering AB
STOCKHOLM
Phone: +46 - 8 - 753 02 50
Fax: +46 - 8 - 753 49 73

Pakse Bridge - Laos