Professional Documents
Culture Documents
SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini
SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini
Question Results
Question: Score 0 of 1
(skipped)
A finished material is to be planned in a controlled manner in the SAP
ECC system in the context of requirements planning. The planned orders are
scheduled using what is known as basic date scheduling (not lead-time
scheduling).
Response:
When a customer order is created for the finished product, the dependent
requirements are automatically triggered for the components in the bill of material
without a planning run.
If individual material components are explicitly assigned to operations during BOM and
routing maintenance, the requirement dates of the dependent requirements for these
components are scheduled at each of the operation start dates.
Question: Score 0 of 1
(skipped)
Which object in customizing controls the determination of planned
total overhead process costs for production orders?
Please choose the correct answer.
Response:
Accounting type
Costing variant
Settlement profile
Cost log
https://www.erpprep.com/node/873/take 1/14
3/1/2020 SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini | ERPPrep
Question: Score 0 of 1
(skipped)
Which one of the following scheduling types cannot be assigned as
default to an order type (production order)?
Please choose the correct answer.
Response:
Midpoint
Forward
Backward
Question: Score 0 of 1
(skipped)
Which option for selecting a routing exists when you create a
production order?
Please choose the correct answer.
Response:
Manual selection based on the list of routings maintained in the material master
Question: Score 0 of 1
(skipped)
Which information is contained in production versions for selecting
routings and bills of material?
Please choose the correct answer.
Response:
The plant for which the routing and BOM have to be created
All the control parameters for selecting routings and bills of material
The explosion date on which the validity of the routing and bill of material is checked
Question: Score 0 of 1
(skipped)
What can you use to organize material staging for production orders?
There are 3 correct answers to this question.
https://www.erpprep.com/node/873/take 2/14
3/1/2020 SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini | ERPPrep
Response:
Material documents
Transfer orders
KANBAN
Pull list
Question: Score 0 of 1
(skipped)
You want to use production/resource tools in your manufacturing
process. Which production type do you use?
Response:
Repetitive manufacturing
Production order
Process order
KANBAN
Question: Score 0 of 1
(skipped)
Which production order function can no longer be carried out after the
order is released?
Please choose the correct answer.
Response:
Switching sequences.
Question: Score 0 of 1
(skipped)
Which of the following statements best defines SAP ERP?
Please choose the correct answer.
Response:
SAP ERP is an application that supports all processes involving direct customer contact
https://www.erpprep.com/node/873/take 3/14
3/1/2020 SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini | ERPPrep
SAP ERP is an application that a company can use to manage its business processes
efficiently.
SAP ERP is a system in which advanced planning and optimization processes can be
mapped.
SAP ERP is a system hardware that includes components such as Purchasing, Sales
and Distribution, Materials Management, and Production.
Question: Score 0 of 1
(skipped)
The company you advise wants to carry out the material availability
check automatically in the production order at various points in time.
Response:
Confirmation of the operation that the materials being checked are assigned to
Question: Score 0 of 1
(skipped)
Which of the following scheduling types can only be used in capacity
planning?
Please choose the correct answer.
Response:
Midpoint
Forward
Backward
Question: Score 0 of 1
(skipped)
Which activities lead to a reduction of the capacity requirements for
an operation?
There are 3 correct answers to this question.
https://www.erpprep.com/node/873/take 4/14
3/1/2020 SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini | ERPPrep
Response:
Question: Score 0 of 1
(skipped)
What data can be posted directly via the Plant Data Collection (PP-
PDC) interface?
Please choose the correct answer.
Response:
Goods receipts
Maintenance notifications
Confirmations
Goods issues
Question: Score 0 of 1
(skipped)
A project team member analyzes the following situation in SAP ECC in
the stock/requirements list for a finished product: there is only one customer order
and one fixed planned order with a similar quantity amount.
The customer order and the planned order both have deadlines on work days but
not on the same work day; the planned order has a later deadline.
The project team member cannot find a rescheduling message referring to this
deadline misalignment in the stock/requirements list. What reasons could there be
for the missing message?
Response:
Requirement planning has not yet been carried out to update the rescheduling
message.
The time misalignment falls within the tolerance window defined in Customizing.
https://www.erpprep.com/node/873/take 5/14
3/1/2020 SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini | ERPPrep
Question: Score 0 of 1
(skipped)
In what sequence are the steps of material requirements planning
performed in SAP ECC?
Please choose the correct answer.
Response:
1. Availability check
2. Lot sizing
3. Determination of the procurement type
4. Scheduling
Question: Score 0 of 1
(skipped)
An enterprise wants to absorb the uncertainty caused by fluctuating
demand for a finished product by means of a buffer variable in SAP ECC. They
suggest a dynamic safety stock.
Response:
The static safety stock per day and the safety time
Question: Score 0 of 1
(skipped)
You want to procure your material components based on a forecast for
the finished material derived from historical sales. When customers order, you
produce the finished product and reserve it for that particular order.
Response:
https://www.erpprep.com/node/873/take 6/14
3/1/2020 SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini | ERPPrep
Question: Score 0 of 1
(skipped)
Which of the following functions are available in the SAP ECC system
for leveling overloads in individual work centers with the capacity planning tools?
There are 3 correct answers to this question.
Response:
Midpoint scheduling
Question: Score 0 of 1
(skipped)
You want to use the function "Read PP master data" in the production
order. However, while calling the function you receive an error message. What
could be the reason?
Please choose the correct answer.
Response:
Question: Score 0 of 1
(skipped)
Which of the following structural elements does a process order have?
There are 3 correct answers to this question.
Response:
Item data
https://www.erpprep.com/node/873/take 7/14
3/1/2020 SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini | ERPPrep
Parallel sequences
Relationships
Phases
Question: Score 0 of 1
(skipped)
What happens when a repetitive manufacturing planned order is
assigned to a production line in the planning table?
There are 2 correct answers to this question.
Response:
Question: Score 0 of 1
(skipped)
In production order processing, for which of the following objects can
you enter a confirmation?
There are 3 correct answers to this question.
Response:
Work Center
Individual Capacity
Order
Operation / Suboperation
Trigger Point
Question: Score 0 of 1
(skipped)
For a specific end product, you want to use a planning time fence and
fixing type 1 to ensure that the planning situation in SAP ECC calms down in a
short-term time window.
Two customer orders arrive at short notice and their receipts should really be
within the planning time fence, due to their date/time.
https://www.erpprep.com/node/873/take 8/14
3/1/2020 SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini | ERPPrep
Response:
Within the planning time fence, the newly created planned orders are automatically
frozen by requirements planning (roll forward).
Newly created planned orders cannot be created by requirements planning before the
end of the planning time fence, at the earliest.
The MRP controller has no possibility of creating planned orders within the planning
time fence.
Requirements planning only examines changes that are relevant to scheduling within
the planning time fence; the customer orders are covered in time.
Question: Score 0 of 1
(skipped)
For which planning strategy does the reduction of planned
independent requirements always occur with the goods receipt?
Please choose the correct answer.
Response:
Question: Score 0 of 1
(skipped)
Where can you define the default storage location for the material
component of a production order?
There are 3 correct answers to this question.
Response:
Routing
Question: Score 0 of 1
(skipped)
In which ways can you implement confirmations for production
orders?
https://www.erpprep.com/node/873/take 9/14
3/1/2020 SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini | ERPPrep
Response:
Through the SAP Integrated Business Planning (SAP IBP) cloud solution
Through automatic process messages using SAP NetWeaver Process Integration (PI)
Question: Score 0 of 1
(skipped)
How can you limit the number of master data objects to be created
when the manufacturing process is the same for many different products?
Please choose the correct answer.
Response:
Question: Score 0 of 1
(skipped)
With which functions of the process order can you fulfill the
requirements of the Good Manufacturing Practices (GMP) standard?
Response:
Availability check
Batch record
Resource selection
Digital signature
Question: Score 0 of 1
(skipped)
The master data for an in-house production process is to be set up in
the SAP ECC system. To do this, you should create a suitable routing that plans for
five operations in an initial sequence (10, 20, 30, 40, 50).
https://www.erpprep.com/node/873/take 10/14
3/1/2020 SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini | ERPPrep
What sequence type would you use to create the second sequence in the system?
Please choose the correct answer.
Response:
Substitute sequence
Alternative sequence
Parallel sequence
Standard sequence
Question: Score 0 of 1
(skipped)
Which types of objects can be changed with Engineering Change
Management (ECM)?
There are 3 correct answers to this question.
Response:
Task list
Work center
Production version
Bill of material
Material master
Question: Score 0 of 1
(skipped)
In the task list, there is the possibility to work with suboperations.
What can you do in more detail by using suboperations?
There are 2 correct answers to this question.
Response:
Costing
Capacity planning
Scheduling
Question: Score 0 of 1
(skipped)
https://www.erpprep.com/node/873/take 11/14
3/1/2020 SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini | ERPPrep
Response:
The planning of MPS and non-MPS items is always carried out in one planning run.
Question: Score 0 of 1
(skipped)
In your enterprise, a planning strategy is used in SAP ECC that
enables joint planning of all MRP scheduled assemblies for a finished product to
trigger procurement of these assemblies.
It is important to ensure that the finished product is only produced when there is a
customer order present.
Response:
Question: Score 0 of 1
(skipped)
Where can you maintain available capacities in an SAP ECC system?
There are 2 correct answers to this question.
Response:
Routing
Pooled capacity
Work center
https://www.erpprep.com/node/873/take 12/14
3/1/2020 SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini | ERPPrep
Question: Score 0 of 1
(skipped)
During the processing of production orders planned and actual costs
are determined. On which of the following objects can you collect these costs?
Response:
Production order
Work center
Planned order
Question: Score 0 of 1
(skipped)
Which of the following elements can be used in a process order?
There are 3 correct answers to this question.
Response:
Process instructions
Parallel sequences
Relationships
Suboperations
Phases
Question: Score 0 of 1
(skipped)
For which of the following objects can you enter a confirmation?
There are 2 correct answers to this question.
Response:
Production order
Trigger Point
Work Center
Question: Score 0 of 1
(skipped)
What repetitive manufacturing options can you use to carry out line
loading in the SAP ECC system and thus generate Run Schedule Quantities (RSQ)
https://www.erpprep.com/node/873/take 13/14
3/1/2020 SAP ERP Production Planning and Manufacturing (PP) Certifications Practice Exam - Mini | ERPPrep
Response:
Question: Score 0 of 1
(skipped)
In SAP ECC, you calculate the standard available capacity for a work
center capacity using the following data:
Response:
8 hours
5.6 hours
6.16 hours
7 hours
Money Back Guarantee Testimonial FAQs Privacy Policy Terms and Conditions About Us Join Us
Contact Us
https://www.erpprep.com/node/873/take 14/14