Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/320442710

Impact of underground construction and TBM tunnelling on surface structures


in Kolkata East-West Metro

Article · October 2017

CITATIONS READS

0 551

2 authors:

Alvaro Casasus Harvinder Rana


AECOM ASIA AECOM
6 PUBLICATIONS   4 CITATIONS    1 PUBLICATION   0 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

New formulation to assess the tunnelling impact in buildings View project

Kolkata East West Metro Project View project

All content following this page was uploaded by Alvaro Casasus on 17 October 2017.

The user has requested enhancement of the downloaded file.


Seminar on Kolkata East-West Metro.

Impact of underground construction and TBM tunnelling on surface


Structures in Kolkata East-West Metro.

Dr. Alvaro Casasus


Associate Director, Geotechnical, AECOM, Gurgaon, India.
Harvinder Rana
Design Engineer, Geotechnical, AECOM, Gurgaon, India.

ABSTRACT: Kolkata East West Metro includes the contract UG-1. Design and Construction of
Underground Section from Howrah Maidan Station to West end of Central Station in Kolkata. The
project includes two bored tunnels mined with two Earth Pressure Balanced TBMs and with a
drive length of 3,100 meters approximately. The ground is made of one upper layer of soft clay
and another deeper one of stiff clay presenting also some silty sandy pockets. Through that
ground the TBMs mined at depths varying from 10 to 30 meters depth and underneath various
structures, including flyovers with deep foundations, rail tracks, dilapidated buildings and heritage
structures. This paper summarises and reviews the methodology followed to evaluate the impact
caused by the tunnel excavation on those structure, the problem faced during mining and
preventive measures taken on site to minimize the structural impact.

1 INTRODUCTION required in order take the proper measures


Excavating tunnels in clay is a challenging before, during and after mining the tunnel.
work, especially when the tunnels are crossing
an old city like Kolkata, having many ancient 2 GEOLOGICAL AND GEOTECHNICAL
buildings, old structures and monuments. Also it PROPERTIES OF KOLKATA EAST
is a very congested city, with traffic and people WEST METRO
on the streets which makes difficult the access
with machinery for any intervention from the Kolkata is located over the "Bengal basin", a
ground surface. pericratonic tertiary basin.
As far as the ground is concerned, the clay is The quaternary sediments in Kolkata consist
a soft material which has a visco-elastic-plastic of clay, silt, and several grades of sand and
behaviour, due to the consolidation gravel. These sediments are sandwiched
phenomenon, and presenting, most of the time, between two clay beds: the lower one at a
a low Young’s modulus which makes it prone to depth of 250–650 meters; the upper one 10–
high strains under stresses. 40 meters of thickness.
Mining tunnels through such material makes The East West Metro alignment is located in
it necessary to take into account the the upper clay layer, and the ground is divided
settlements that happen, in the influence area, into four layers, the first one is called “made
due to tunnel construction. These Settlements ground” and presents a thickness of 2 to 5
will be time dependent, and will affect the meters. This is classified as Unit 1 and is it
adjacent structures. That affection will depend formed by cohesion less material with 12Mpa of
on the stiffness of the clay and how efficiently E modulus and 28 degrees of friction angle.
the control of the TBM parameters is done. The second layer is soft clay, classified as
In any case an impact assessment of the Unit 2, it is an organic silty clay/ clayey silt
structures has to be done to know in advance material, with a thickness of around 15 meters
how much the ground settlement will be and a long term E modulus of 8 Mpa.
damaging the structures. Thus classification The third layer it is formed by a stiff clay, it is
this damage with some engineering approaches a silty clay/clayey silt material, this layer goes
1
Seminar on Kolkata East-West Metro.

up to 40 meters deep and it is classified as Unit diameter, tunnel excavated diameters, is equal
3A. The drained E modulus of this layer is equal to 6,380 millimetres (mm), while the tail of the
to 55Mpa at average. shield has a diameter of 6,330 mm, hence from
In the alignment there are also some pockets the cutter head to the tail shield there are 25
of silty sandy material, Unit 3B, with same E millimetres of gap in which the ground can
modulus as Unit 3A but higher permeability. close freely. The reason of having a tapered
In the figure 2 it can be seen a general shield instead of a straight one is to reduce the
scheme of the ground. ground friction and the possibility of getting
trapped in case the ground closes around it.
Finally the segmental lining ring is placed
right at the end of the shield, that ring has an
external diameter of 6,100 mm, so from the
shield tail to the outer face of the segmental
lining there is another gap of 115 mm. This gap
is filled with what it is called, liquid A and liquid
B. Liquid A is a cement grout and liquid B
sodium silicate to accelerate the gel time of the
grout, to give confinement to the segment and
stop deformations as soon as possible.
Hence can be assumed that the last 115 mm
of gap will not create any volume loss, since it
Figure: 2 Ground profile Kolkata East West Metro
is filled with the cementitious grout, however it
may also produce some ground loss because of
3 CONCEPT OF VOLUME LOSS the grout shrinkage and improper filling of the
When a continuous ground is excavated, its gap, this loss is termed as tail loss.
in situ stresses redistributes along the periphery There is another volume loss to take into
of the excavated area, experiencing a reduction account, the face excavation volume loss, once
on radial stresses and an increment on the tunnel is excavated the ground on the
tangential ones, this stresses redistribution will excavated face will try to extrude inside the
create radial strains which will cause tunnel tube. This phenomena can be controlled
deformations which we know as convergences. as long as the proper face pressure is used.
The ground will close inwards to the opening
and this closure is what we define as volume
loss. If this phenomenon is allowed without any
support, the ground will keep closing until it
reaches a new stresses in equilibrium state.
However, if the ground strength parameters are
not able to resist those stresses then the
excavated opening will collapse.
In tunnelling what is done is; we place a
support/lining to resist the percentage of Figure 1: Volume loss scheme along the TBM
stresses, which the ground cannot resist. But
there is a gap of time and space in between the So we can conclude here is; the only volume
moment when the tunnel is excavated and the loss which cannot be controlled in an EPB
lining/support is placed. During this mentioned machine is the shield loss. The convergences
gap, the ground is free to deform and volume that take place from the cutter head up to the
loss will take place in this period of time. shield tail in the case of the EPB used in the
In the case of tunnels mined with a TBM Kolkata East West Metro UG-1 can be up to a
machine, Earth Pressure Balanced (EPB), like maximum of 25 mm. This figure represents a
in the Kolkata East West Metro, the spatial gap volume loss of 1.56%. During the impact
in between the ground excavation and assessment on the structures a volume loss of
installation of the support, is equal to the length 1.5% was considered systematically.
of the shield. In our particular case it is a The volume loss in the excavated face can
Herrenknecht EPB with a shield length of 7,594 contribute around 0.1% to 0.2% more, as
millimetres. On the other hand the cutter head
2
Seminar on Kolkata East-West Metro.

mentioned above it will depend very much on mm, that represents a volume loss of 0.83%,
the operational face pressure the EPB is using. and the ground will not close around the shield,
Having a gap of 25 mm in which the ground being the final gap to fill with grout equal to
can freely close around the shield does not 115 + 25 19 = 121 millimeters.
mean it will do it totally, that will depend on the On the other hand what we have analysed
ground parameters and stresses. so far are long term or drained E modulus
Dr. Kirsch (1898) presented the elastic parameters for the different layers, here we are
solution for the stresses around a circular hole going to discuss what happens with the short
made in a loaded infinite plate. Later Brady – term or undrained parameters.
Brown, based in Kirsch solutions, developed As it is well known that the deformations on
formulations for calculating displacements clays have a time dependent behaviour and
around the circular opening. that happens because of the consolidation
phenomenon.
= [(1 + ) ( )( 4 ) cos 2 ] According with Karl von Terzaghi's Principle,
(1)
in clays when there is an increment of stresses
at the very beginning this increment will be
This formulation can be used for producing an increment in the pore pressure
computations of the maximum radial only, remaining the effective stresses constant.
displacement as per ground parameters and However little by little the stresses from the
stresses and the maximum volume loss, by water are dissipated into the ground particles,
integration of those displacements along the increasing the effective stresses and the
circular opening. deformations. That phenomenon is known as
If the displacements are higher than 25 consolidation and the time it takes to happened
mm then the ground will close around the depends on the ground permeability and the
shield, acting this one as temporally level of stresses.
supported until the segmental ring is The conclusion is that the deformation of the
placed and the gap is filled with cement clays is also linked with the time the clays
grout. If the gap is filled properly more remain unsupported.
displacements of the ground should not If we consider undrained or short term
happen, j ust the one equivalent to the parameters for the Kolkata clays then we will
grout shrinkage, which is not more than a have a reduction on 25% of the deformations.
few mi llimetres. Since according with the GIR the undrained E
Considering 12 meters depth in Unit 2 and modulus is 25% higher than the drained one.
the long term E modulus, applying equation (1) Considering this maximum deformation of 42
we obtain a maximum radial deformation of the and 16 mm in Units 2 and 3A can be calculated
tunnel equal to 53 mm. Here we have to call the respectively.
attention on the elastic analysis done; we are
not taking into account the plastic deformation 4 PREDICTION OF GROUND
of the clay. SETTLEMENTS ON THE SURFACE
These 53 mm deformation implies that the
ground will close around the shield and the The volume loss created during boring of the
shield will act as temporally support until the tunnel will end up creating ground settlements
ground reaches the shield tail where the on the surface. Those settlements will depend
segmental ring will be installed and the 115 mm on the quantity of volume loss and type of
gap will be filled with the cement grout. ground.
As already it has been indicated, if the void For that prediction, different software based
is properly filled, not more as 25 mm ground on Finite Element or Finite Differences
inwards deformation should happens and the approach or an accepted empirical method
volume loss would be around 1.5%. based on the Gaussian curve settlement
Now if we consider the layer Unit 3A, as distribution proposed by Peck (1969) can be
already discussed, the long term E modulus is used.
equal to 55 Mpa, doing the same exercise, for a
= (2)
depth of 25 meters we can expect a maximum
elastic deformation of the ground equal to 19

3
Seminar on Kolkata East-West Metro.

The representation of equation (2) can be each tunnel independently and adding the
seen in Figure 3. settlements, represented by each Gaussian
curve, in the overlapping zone.
Following the previous calculations the
Gaussian curves for two tunnels mined in Unit
2, at 12 meters depth is presented in Figure 4,
and two tunnels in Unit 3A at 25 meters depth is
presented in Figure 5.

Figure: 3 Ground settlements profile

Integrating the equation (2) we obtain the


total volume of settlements on the surface,
which is equal to the tunnel volume loss.

= =

(%) Figure: 4 Gaussian curves for two tunnels mined in


4 Unit 2 (12 m Deep)

Finally we obtain the expression of the


maximum settlement on the surface which it is
linked to the ground volume loss.

0.313 (%)
=
(3)
The parameter represents the distance of
the Gaussian curve inflexion point to the tunnel
axis, and it is equal to:

(4)
is a parameter depending on the type of
ground. For the Kolkata East West Metro,
contract UG-1 impact assessment, that value
was taken as 0.5, being as per the literature the Figure: 5 Gaussian curves for two tunnels mined in
most suitable value for clays. That value was Unit 3A (25 m Deep)
checked afterwards with the actual ground
settlements realizing that was it was fitting quite We can draw the conclusion that in Kolkata
well the settlements points in the theoretical East West Metro, contract UG-1, the ground
Gaussian curve sometimes. However in some settlements caused because of twin tunnels
stretches was found that smaller values were excavation, will be expected in the range of 15
better fit. to 30 millimetres.
To take into account the settlements
produced by the two tunnels the methodology
followed was to consider the Gaussian curve of

4
Seminar on Kolkata East-West Metro.

5 IMPACT ASSESSMENT OF Equations (5) and (6) allow calculating the


GROUND SETTLEMENTS ON THE shear and bending stresses on the building
STRUCTURES once the ground settlements are predicted.
The methodology is finalized categorising
In Kolkata Metro tunnelling impact the building damage depending on the
assessment was done for all the structures maximum composed tensile strain imposed to
falling on the tunnels influence area. In that the building. In the Figure 7 it can be seen that
area both shallow structures foundations, classification.
heritage and old dilapidated buildings, as well
as deep structures foundations, flyovers and
other buildings were assessed. For that
assessment both analytical and numerical
approaches were used.

5.1 Assessment of Structures on Shallow


Foundations
The analytical approach followed was based
on J. B. Burland et al. (2002) Ref.1, and Marco
D. Boscardin et al. (1989) Ref. 2. The Figure: 7 Damage chart based on maximum strain.
assessment methodology is based on
representing the building, affected by the According with the methodology from
settlements, as a thick Timoshenko Beam; categories Negligible to slight no further study
shear deformation is not neglected. The beam of the impact is required. However from
will be simple supported in both ends and a Moderate to Very Severe a detailed analysis of
punctual load will be applied to the centre. the tunnel structure interaction is required and
This approach gives reasonable estimation measures to reduce the impact has to be put in
of strains on the building based on the place.
displacement of ground and it has been proven It should be noted that this approach
by Boscardin and Cording with results from field considers the tunnel passing right below the
tests. building which is not always the case.
While assessing the impact of the tunnels on
the influence area located structures, in Kolkata
Metro, it was realized that some of them were in
a different position, with the tunnel crossing
below on the structures edges. Under those
circumstances applying Burland’s equations (5)
and (6) in an accurate way is complicated, so
another formulation, based in the same
approach was develop by General Consultant
team (GC), in other to check the impact on
those structures.
Figure: 6 Schematic Representation of a building
for impact assessment. The methodology is based on considering
The assessment is based on calculating the the buildings as a thick beam fixed in both ends
shear and tensile stresses imposed on the and applying a vertical displacement equal to
building because of the beam deflection that is, the ground settlement in one of them.
the ground settlements.

= 1+
18
(5)
3
= +
12 2 Figure: 8 Representation of building as fixed beam.
(6)
5
Seminar on Kolkata East-West Metro.

The formulation we arrive for shear and negative friction will happens, the ground will
bending strain can be found below: slide along the pile imposing on this an extra
axial force, equal to the limit ground – pile
8 adhesion force; , and reducing the
+ length of pile resisting the foundation forces,
5
that will end up in increasing the pile
(7) settlements. Determining the length of pile in
which the negative friction will take place is the
+ right way of determining the settlements on
piles. In the figure below it can be seen the
(8) phenomenon in which the pile has been
considered as a rigid body; elastic deformations
on it had been neglected. The circle is showing
5.2 Assessment of Structures on Deep the pile length in which negative friction will take
Foundations place.
Tunnelling in the vicinity of piles will impact
those in two different ways, one will be
structurally impact, increasing bending
moments and axial forces, and the other will be
affecting the bearing capacity of the pile
through the ground friction reduction.
The impact will depend on the position of the
pile with respect the tunnel centre, when the
tunnel passes beside the pile, it will deform the
ground creating bending moments on the piles
because of the imposed displacements. Also a
reduction in friction because of horizontal Figure: 10 Ground settlements profile versus pile
stresses relaxation will take place, reducing the settlement. Negative friction.
pile capacity, H. G. Poulus Ref. 3. That lost in
capacity may end up in settlements on the 6 IMPACT ASSESSMENT ON
plies. KOLKATA EAST WEST METRO UG-1

In this section the impact assessment done in


the most important structures along the tunnel
alignment in Kolkata East West Metro UG-1 is
detailed.
Colvin Court Building
The building is basically load bearing brick
masonry structure with steel beam supporting
the floor slab. This G+3 storied building, with
shallow foundations, is mainly for Eastern
Railway’s senior officer’s Bungalows.
Figure: 9 Lateral impact of a tunnel in piles.

However assessing the settlements that


piles founded structure will suffer because of
the excavation of a tunnel is not an easy task.
The main difficulty it’s in the understanding and
quantification of the pile – ground interaction.
Using numerical models will overestimate those
settlements unless the code can simulate the
ground sliding along the pile. Here comes the
concept of negative friction, the movements of
the pile and the ground will be different,
Picture: 1 Colvin Court front view
whenever the vertical displacement of the
ground is higher than the one of the pile, then
6
Seminar on Kolkata East-West Metro.

Figure: 10 Plant view tunnels and Colvin Court Figure: 11 Position of tunnels with respect Bankim
The tunnels crossed below the building at a Setu Bridge piles.
depth of 14.5 meters, inside the Unit 2 layer. To assess the impact of the tunnels on the
For the impact assessment 1.5% of volume loss structure a FEM model was done using Plaxis
was considered and a maximum of 30 2D. The results on the model predicted a single
millimetres settlements was expected with a pile maximum settlement of 15 millimetres,
negligible damage in the building. However the while the actual settlement after the tunnels
TBMs were in the “learning curve” at that crossed the area was 5 millimetres maximum.
moment, during that initial situation the TBM That shows the, already discussed, limitations
parameters are not yet adjust in the optimum of the FEM software to simulate properly the
way. The final maximum settlement recorded interaction between pile and ground, not being
was 70 millimetres, around 3.5% of volume possible to simulate the detaching of the ground
loss. The damages on the building were under from the pile structure in the negative friction
slight category in the end, some cracks, less length. At this stage TBMs were running
than 5 millimetres thick, were reported. smoothly, after the learning period, and
Bankim Setu Bridge settlements on the ground were showing
This is a RCC bridge which crosses the volume losses less than 1.5%. No damage was
Buckland road over the train tracks, and it is reported on the referred bridge. However as
founded on 25 meters long piles. precaution the bridge was closed to the traffic
during the period of time the TBMs were mining
beneath.
DRM Building
This is a G+2 building, structure, which is
formed by load bearing external brick masonry
walls with steel column inside the building
supporting steel beams and floor slabs, the
foundation consists on a continuous shallow
foundation. The building is mainly occupied by
GRPF police station at ground floor level and
DRM office at first and second floor level.

Picture: 2 Bankim Setu Bridge

The tunnels cross below the bridge at 24


meters below the ground level and the nearest
pile to the tunnels is at 3.83 meters of horizontal
distance. The tunnels are in the Unit 3A, the
stiff clay with SPT around 30, E modulus
around 50 Mpa and 250Kpa of undrained shear
strength. Figure: 12 Plan view of DRM building respect
tunnels.

7
Seminar on Kolkata East-West Metro.

The tunnels depth along the building varies simply supported made up of composite
from 27 to 30 meters and the layer in which the structure, steel and concrete.
tunnels mined is Unit 3A, stiff clay with SPT
values up to 50.

Figure: 14 Plan view of Brabourne Road Flyover


Picture: 3 DRM Building view respect tunnels.
GC did the impact assessment of this The effect of tunnelling on the pile
structure, predicting total ground settlements of foundations has been simulated with 2D finite
around 30 millimetres and damage on the element modelling approaches. The analysis
building in the very slight category. was carried out for different sections under
Brabourne flyover to assess the settlements on
the flyover piles. The ground parameters at this
point belong to very stiff clay with SPT values
up to 70.

Figure: 13 Settlements prediction below DRM


building.
Even though predicted settlements were a
bit high, the position of the tunnels were
favourable, the differential settlements suffered
by the building were around 3.5 millimetres.
Because of operational constrains this
building could not be evacuated during the
mining process, however preventive measures
were implemented like horizontal nets to
prevent any spalls from falling down. The TBMs
Figure: 15 Brabourne Road Flyover cross section
crossed the building registering settlements as
From the analysis it was observed that the
predicted and no major damages on the
maximum settlement in the pile is equivalent to
building were reported.
the maximum settlements in the ground which
Brabourne Road Flyover
was predicted to be 20 mm.
This flyover is located along the tunnel
alignment after Hoogly River. The tunnels pass
beneath 6 piers of the road flyover. The ground
layer crossed is stiff clay, Unit 3A, in this
section. The crown of the tunnel at this location
varies from 30 to 32 meters deep. Clear
spacing between the pile bottom and tunnel
crown varies from 7.5 meters to 9 meters. The
superstructure of Brabourne Flyover Bridge is
8
Seminar on Kolkata East-West Metro.

Figure: 16 FEM analyses for piles settlement


However after the TBMs crossed below the
flyover, a maximum of 10 mm settlement was
observed during real time ground monitoring.
The software predicted higher values of
settlements in the piles as it does not allow the
piles to detach from the soil. This results in the
movement of piles together with the mesh
resulting in higher settlements.
The TBMs crossed the bridge without any
damages reported. However as precaution the
bridge was cut to the traffic during mining. Picture: 4 Dilapidated buildings along Raja
Dilapidated buildings along Raja Woodmount St. view
Woodmount St. Writers Building and St. Andrews Church
There are some buildings nearby Brabourne At the time of writing this paper there is still a
Road Flyover which were a concern during challenge pending in the project, and this is
mining beneath them because of the poor crossing the heritage buildings; Writers and St.
condition of them. The structure of those Andrews Church.
buildings was in a quite bad state being the Writers building is an edifice with a great
buildings a risk itself before the tunnels crossed political significant and memories of Indian
below them. Independence Movement. Both buildings are
founded with shallow foundations 1.5 to 2.0
meters deep.
The twin tunnels will pass beneath the
buildings edges at a depth of 17 meters from
the ground surface before entering in New
Mahakaran Station.

Figure: 17 Plan view of Dilapidated buildings


along Raja Woodmount St.
Also the ground layer crossed was stiff clay,
Unit 3A, in this section. The crown of the tunnel
at this location varies from 30 to 32 meters
deep.
The previous assessments of these buildings Figure: 18 Plan view of Writers and St. Andrews
showed maximum settlements of 20 Church with respect to the tunnels.
millimetres, with 1.5% volume loss, and an At this location the TBMs will be mining
impact category of negligible. However because partially in Unit 3A, 3B and Unit 2 on the tunnel
of the poor condition of the building evacuating crown. The SPT values are ranging from 10 in
them during the mining process was considered the Unit 2 up to 30 in Unit 3A.
as a protective measure. The contractor has prepared a FEM using
The actual settlements recorded after the Plaxis 2D to assess the expected settlements in
TBMs crossed was up to 7 millimetres, and no Writers Building, from this model they have
damage on the buildings, beyond the ones they obtained a maximum settlement of around 22
already had before the TBMs, was reported. millimetres on the ground surface. With those
That means a volume loss around 0.7%, and it settlements they have performed an impact
can be back calculated an E modulus of around assessment obtaining a maximum tensile stress
90 Mpa. that gives an idea about the stiffness of of 0.114% falling the building under the slight
the clay in that stretch. category of damage. That means that non-

9
Seminar on Kolkata East-West Metro.

structural cracks on the building are expected, injecting a low pressure grout, 1 to 2 bars
being any possible damage easily repair with a cement water ratio of 0.5 in weight.
afterwards. This measure was applied in all the
critical buildings showing good results.
Figure: 20 Peripheral grouting scheme.

Figure: 19 Writers Building FEM settlements


assessment.

7 PRE-EMPTIVE AND MIITGATION


MEASSURES
During mining below all the critical buildings
and structures some pre-emptive and mitigation
measures were put in place to minimize the 6. Buildings evacuation and bridges traffic
settlements and the consequences of those in cut; whenever was possible all the critical
the structures. buildings crossed by the TBMs were
Summarized of these measures is presented evacuating while the machines were
below: mining and all the bridges were cut to the
1. Reducing time; it was quickly learnt the traffic.
time dependant behaviour of the clay, 7. Continuous monitoring of ground and
finding that reducing the gap of time structures movements during mining; that
between excavating a ring and placing was done during the whole mining
the lining the settlements were also process and in almost real time for the
reduced. That happened especially in the most critical structures.
unit 2.
2. According with previous point, stoppages 8 REFERENCES
of TBM should be avoided in the vicinity
of any sensitive structure. Ref 1. Burland J.B., Standing J.R. and Jardine
3. TBM parameters has to be control in a F.M. (eds): Building response to tunneling.
very close manner, face pressure, volume Case studies from the Jubilee Line Extension,
of material excavated and volume and London.
pressure of grout injected in the annular
gap are directly related with the Ref 2. Boscardin, M.D. and Cording E.G.
settlements on the ground surface. (1989): Building Response to Excavation
4. Propping in buildings, this measure Induced Settlement.
consist on place some propping in
arches, windows, big structural spans, Ref 3. Poulos, H.G. and Deng, W. (2004). An
near pillars,… the main objective of these Investigation on Tunnelling-Induced
is to make the building more rigid as Reduction of Pile Geotechnical Capacity.
structure not following the ground
settlements and reducing the cracking. Ref 4. Kirsch G. Die theorie der elastizitat und
This measure is complemented with the die bedurfnisse der festigkeitslehre. Veit Ver
next one. Deut Ing 1898; 42: 797-807.
5. Peripheral surface grouting along the
buildings, this measure will aim to fill any
gap which can exist or create during/after
mining in between the ground and the
buildings foundation. It consists on
10

View publication stats

You might also like