Professional Documents
Culture Documents
SeminaronKolkataEast WestMetro
SeminaronKolkataEast WestMetro
net/publication/320442710
CITATIONS READS
0 551
2 authors:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Alvaro Casasus on 17 October 2017.
ABSTRACT: Kolkata East West Metro includes the contract UG-1. Design and Construction of
Underground Section from Howrah Maidan Station to West end of Central Station in Kolkata. The
project includes two bored tunnels mined with two Earth Pressure Balanced TBMs and with a
drive length of 3,100 meters approximately. The ground is made of one upper layer of soft clay
and another deeper one of stiff clay presenting also some silty sandy pockets. Through that
ground the TBMs mined at depths varying from 10 to 30 meters depth and underneath various
structures, including flyovers with deep foundations, rail tracks, dilapidated buildings and heritage
structures. This paper summarises and reviews the methodology followed to evaluate the impact
caused by the tunnel excavation on those structure, the problem faced during mining and
preventive measures taken on site to minimize the structural impact.
up to 40 meters deep and it is classified as Unit diameter, tunnel excavated diameters, is equal
3A. The drained E modulus of this layer is equal to 6,380 millimetres (mm), while the tail of the
to 55Mpa at average. shield has a diameter of 6,330 mm, hence from
In the alignment there are also some pockets the cutter head to the tail shield there are 25
of silty sandy material, Unit 3B, with same E millimetres of gap in which the ground can
modulus as Unit 3A but higher permeability. close freely. The reason of having a tapered
In the figure 2 it can be seen a general shield instead of a straight one is to reduce the
scheme of the ground. ground friction and the possibility of getting
trapped in case the ground closes around it.
Finally the segmental lining ring is placed
right at the end of the shield, that ring has an
external diameter of 6,100 mm, so from the
shield tail to the outer face of the segmental
lining there is another gap of 115 mm. This gap
is filled with what it is called, liquid A and liquid
B. Liquid A is a cement grout and liquid B
sodium silicate to accelerate the gel time of the
grout, to give confinement to the segment and
stop deformations as soon as possible.
Hence can be assumed that the last 115 mm
of gap will not create any volume loss, since it
Figure: 2 Ground profile Kolkata East West Metro
is filled with the cementitious grout, however it
may also produce some ground loss because of
3 CONCEPT OF VOLUME LOSS the grout shrinkage and improper filling of the
When a continuous ground is excavated, its gap, this loss is termed as tail loss.
in situ stresses redistributes along the periphery There is another volume loss to take into
of the excavated area, experiencing a reduction account, the face excavation volume loss, once
on radial stresses and an increment on the tunnel is excavated the ground on the
tangential ones, this stresses redistribution will excavated face will try to extrude inside the
create radial strains which will cause tunnel tube. This phenomena can be controlled
deformations which we know as convergences. as long as the proper face pressure is used.
The ground will close inwards to the opening
and this closure is what we define as volume
loss. If this phenomenon is allowed without any
support, the ground will keep closing until it
reaches a new stresses in equilibrium state.
However, if the ground strength parameters are
not able to resist those stresses then the
excavated opening will collapse.
In tunnelling what is done is; we place a
support/lining to resist the percentage of Figure 1: Volume loss scheme along the TBM
stresses, which the ground cannot resist. But
there is a gap of time and space in between the So we can conclude here is; the only volume
moment when the tunnel is excavated and the loss which cannot be controlled in an EPB
lining/support is placed. During this mentioned machine is the shield loss. The convergences
gap, the ground is free to deform and volume that take place from the cutter head up to the
loss will take place in this period of time. shield tail in the case of the EPB used in the
In the case of tunnels mined with a TBM Kolkata East West Metro UG-1 can be up to a
machine, Earth Pressure Balanced (EPB), like maximum of 25 mm. This figure represents a
in the Kolkata East West Metro, the spatial gap volume loss of 1.56%. During the impact
in between the ground excavation and assessment on the structures a volume loss of
installation of the support, is equal to the length 1.5% was considered systematically.
of the shield. In our particular case it is a The volume loss in the excavated face can
Herrenknecht EPB with a shield length of 7,594 contribute around 0.1% to 0.2% more, as
millimetres. On the other hand the cutter head
2
Seminar on Kolkata East-West Metro.
mentioned above it will depend very much on mm, that represents a volume loss of 0.83%,
the operational face pressure the EPB is using. and the ground will not close around the shield,
Having a gap of 25 mm in which the ground being the final gap to fill with grout equal to
can freely close around the shield does not 115 + 25 19 = 121 millimeters.
mean it will do it totally, that will depend on the On the other hand what we have analysed
ground parameters and stresses. so far are long term or drained E modulus
Dr. Kirsch (1898) presented the elastic parameters for the different layers, here we are
solution for the stresses around a circular hole going to discuss what happens with the short
made in a loaded infinite plate. Later Brady – term or undrained parameters.
Brown, based in Kirsch solutions, developed As it is well known that the deformations on
formulations for calculating displacements clays have a time dependent behaviour and
around the circular opening. that happens because of the consolidation
phenomenon.
= [(1 + ) ( )( 4 ) cos 2 ] According with Karl von Terzaghi's Principle,
(1)
in clays when there is an increment of stresses
at the very beginning this increment will be
This formulation can be used for producing an increment in the pore pressure
computations of the maximum radial only, remaining the effective stresses constant.
displacement as per ground parameters and However little by little the stresses from the
stresses and the maximum volume loss, by water are dissipated into the ground particles,
integration of those displacements along the increasing the effective stresses and the
circular opening. deformations. That phenomenon is known as
If the displacements are higher than 25 consolidation and the time it takes to happened
mm then the ground will close around the depends on the ground permeability and the
shield, acting this one as temporally level of stresses.
supported until the segmental ring is The conclusion is that the deformation of the
placed and the gap is filled with cement clays is also linked with the time the clays
grout. If the gap is filled properly more remain unsupported.
displacements of the ground should not If we consider undrained or short term
happen, j ust the one equivalent to the parameters for the Kolkata clays then we will
grout shrinkage, which is not more than a have a reduction on 25% of the deformations.
few mi llimetres. Since according with the GIR the undrained E
Considering 12 meters depth in Unit 2 and modulus is 25% higher than the drained one.
the long term E modulus, applying equation (1) Considering this maximum deformation of 42
we obtain a maximum radial deformation of the and 16 mm in Units 2 and 3A can be calculated
tunnel equal to 53 mm. Here we have to call the respectively.
attention on the elastic analysis done; we are
not taking into account the plastic deformation 4 PREDICTION OF GROUND
of the clay. SETTLEMENTS ON THE SURFACE
These 53 mm deformation implies that the
ground will close around the shield and the The volume loss created during boring of the
shield will act as temporally support until the tunnel will end up creating ground settlements
ground reaches the shield tail where the on the surface. Those settlements will depend
segmental ring will be installed and the 115 mm on the quantity of volume loss and type of
gap will be filled with the cement grout. ground.
As already it has been indicated, if the void For that prediction, different software based
is properly filled, not more as 25 mm ground on Finite Element or Finite Differences
inwards deformation should happens and the approach or an accepted empirical method
volume loss would be around 1.5%. based on the Gaussian curve settlement
Now if we consider the layer Unit 3A, as distribution proposed by Peck (1969) can be
already discussed, the long term E modulus is used.
equal to 55 Mpa, doing the same exercise, for a
= (2)
depth of 25 meters we can expect a maximum
elastic deformation of the ground equal to 19
3
Seminar on Kolkata East-West Metro.
The representation of equation (2) can be each tunnel independently and adding the
seen in Figure 3. settlements, represented by each Gaussian
curve, in the overlapping zone.
Following the previous calculations the
Gaussian curves for two tunnels mined in Unit
2, at 12 meters depth is presented in Figure 4,
and two tunnels in Unit 3A at 25 meters depth is
presented in Figure 5.
= =
0.313 (%)
=
(3)
The parameter represents the distance of
the Gaussian curve inflexion point to the tunnel
axis, and it is equal to:
(4)
is a parameter depending on the type of
ground. For the Kolkata East West Metro,
contract UG-1 impact assessment, that value
was taken as 0.5, being as per the literature the Figure: 5 Gaussian curves for two tunnels mined in
most suitable value for clays. That value was Unit 3A (25 m Deep)
checked afterwards with the actual ground
settlements realizing that was it was fitting quite We can draw the conclusion that in Kolkata
well the settlements points in the theoretical East West Metro, contract UG-1, the ground
Gaussian curve sometimes. However in some settlements caused because of twin tunnels
stretches was found that smaller values were excavation, will be expected in the range of 15
better fit. to 30 millimetres.
To take into account the settlements
produced by the two tunnels the methodology
followed was to consider the Gaussian curve of
4
Seminar on Kolkata East-West Metro.
= 1+
18
(5)
3
= +
12 2 Figure: 8 Representation of building as fixed beam.
(6)
5
Seminar on Kolkata East-West Metro.
The formulation we arrive for shear and negative friction will happens, the ground will
bending strain can be found below: slide along the pile imposing on this an extra
axial force, equal to the limit ground – pile
8 adhesion force; , and reducing the
+ length of pile resisting the foundation forces,
5
that will end up in increasing the pile
(7) settlements. Determining the length of pile in
which the negative friction will take place is the
+ right way of determining the settlements on
piles. In the figure below it can be seen the
(8) phenomenon in which the pile has been
considered as a rigid body; elastic deformations
on it had been neglected. The circle is showing
5.2 Assessment of Structures on Deep the pile length in which negative friction will take
Foundations place.
Tunnelling in the vicinity of piles will impact
those in two different ways, one will be
structurally impact, increasing bending
moments and axial forces, and the other will be
affecting the bearing capacity of the pile
through the ground friction reduction.
The impact will depend on the position of the
pile with respect the tunnel centre, when the
tunnel passes beside the pile, it will deform the
ground creating bending moments on the piles
because of the imposed displacements. Also a
reduction in friction because of horizontal Figure: 10 Ground settlements profile versus pile
stresses relaxation will take place, reducing the settlement. Negative friction.
pile capacity, H. G. Poulus Ref. 3. That lost in
capacity may end up in settlements on the 6 IMPACT ASSESSMENT ON
plies. KOLKATA EAST WEST METRO UG-1
Figure: 10 Plant view tunnels and Colvin Court Figure: 11 Position of tunnels with respect Bankim
The tunnels crossed below the building at a Setu Bridge piles.
depth of 14.5 meters, inside the Unit 2 layer. To assess the impact of the tunnels on the
For the impact assessment 1.5% of volume loss structure a FEM model was done using Plaxis
was considered and a maximum of 30 2D. The results on the model predicted a single
millimetres settlements was expected with a pile maximum settlement of 15 millimetres,
negligible damage in the building. However the while the actual settlement after the tunnels
TBMs were in the “learning curve” at that crossed the area was 5 millimetres maximum.
moment, during that initial situation the TBM That shows the, already discussed, limitations
parameters are not yet adjust in the optimum of the FEM software to simulate properly the
way. The final maximum settlement recorded interaction between pile and ground, not being
was 70 millimetres, around 3.5% of volume possible to simulate the detaching of the ground
loss. The damages on the building were under from the pile structure in the negative friction
slight category in the end, some cracks, less length. At this stage TBMs were running
than 5 millimetres thick, were reported. smoothly, after the learning period, and
Bankim Setu Bridge settlements on the ground were showing
This is a RCC bridge which crosses the volume losses less than 1.5%. No damage was
Buckland road over the train tracks, and it is reported on the referred bridge. However as
founded on 25 meters long piles. precaution the bridge was closed to the traffic
during the period of time the TBMs were mining
beneath.
DRM Building
This is a G+2 building, structure, which is
formed by load bearing external brick masonry
walls with steel column inside the building
supporting steel beams and floor slabs, the
foundation consists on a continuous shallow
foundation. The building is mainly occupied by
GRPF police station at ground floor level and
DRM office at first and second floor level.
7
Seminar on Kolkata East-West Metro.
The tunnels depth along the building varies simply supported made up of composite
from 27 to 30 meters and the layer in which the structure, steel and concrete.
tunnels mined is Unit 3A, stiff clay with SPT
values up to 50.
9
Seminar on Kolkata East-West Metro.
structural cracks on the building are expected, injecting a low pressure grout, 1 to 2 bars
being any possible damage easily repair with a cement water ratio of 0.5 in weight.
afterwards. This measure was applied in all the
critical buildings showing good results.
Figure: 20 Peripheral grouting scheme.