HIRAC - Hazard Identification, Risk Assessment and Control

MS.No. ~~ Project: CLARK INTERNATIONAL AIRPORT EXPANSION PROJECT Prepared By: Michael Dave P. Montemayor
Revision: 0 Location: CLARK PAMPANGA Approved By: Maria Cristina L. Estacio
Activity: FIRE PROTECTION WORKS

S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
A. . FABRICATION
A.1 Fabication Fabrication of major component supports and hangers will be at its fabrication plant located at Lot 7A-2 Sooner Farm Compound, Brgy. Timbao, Biñan, Laguna. These fabricated items shall
be delivered to site ready for assembly and installation. Quest-Air Technology intend to mobilize at site a fleet of metal fabrication to include fusion machine threading machine and welding
machine. All items that would require onsite measurements and/or closed coordination shall then be fabicated onsite. A

B.1. PIPING WORKS: Pipe Surface Preparation/Protection


1 Worker mobilization and preparation Lack of Supervision, Information and training. Personal Injury 3 3 9 Provide HSE Induction for all workers onsite to communicate the 3 1 3 A
of working place. site rules and safe system of work.
Lack of PPE. Provide specific training for workers for reinforcement activities to
have an idea about about the hazards related to the work.

Unfamiliar with the site rules Property damage Suficient and suitable supervision shall be full time to cover the
working hours.
TBT to be conducted regularly before each shift.
Provision of mandatory PPE and other PPE as required for the work
activities.
Emergency response and first aid facilities must be briefed to the
workers.
Adequate welfare facilities made available.
2 Obtaining Appropraite permit (PTW) Deviation from permit Damaging exixting services 4 4 16 Ensure all permits are in place before comencement of activities. 4 1 4 A

Unauthorized Activities Unaouthorized entry Municipal, fire department permits must be established if
necessary.
Invalid Permit Floor, Power failure Permit to be validated and activities approved.
Poor implimentation of PTW System Fire Internal permits validated for all the activities.
Personal injury Confined space permit system to be followed if the activities in a
confined space.
S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
Equipment's/tools to be inspected and certified prior to use.

Engineer / Supervisor / EHS Officer must ensure that all work


activities are carried out by a competent personnel under his strict
supervisions.
Identify any underground utilities.
Conduct TBT, communicate the Method Statement and job Hazard
analysis to all workers.
3 Handling of Materials (mechanical) Failure of lifting gear Serious injuries 4 3 12 Ensuring test certificate for all lifting gear/ tools tackles are 2 2 4 A
available and valid. Visual inspection of lifting gears prior to use.

Incompetency/ / lack of knowledge of rigger. Personal injury Checking the competency of person & equipment

Fall of load due to failure of lifting gears or Property damage Inspection by TPCA every 6 Months/Visual inspection of lifting
faulty attachments. gears prior to use.
Hit by hanging load. Close supervision is ensured.
Improper balance of load. To ensure safety checklist before commencing of work.
4 Handling of Materials (Manual). Personal injury Physical injury 3 3 9 Using proper PPEs, 2 2 4 A
Property damage Providing adequate Manpower for the lifting of loads
Back pain, sprain etc. Avoided handling of heavy loads by workmen.
Close supervision is ensured. Monitoring/supervision is a must,
explain hazard prior to start any manual handling.

Use of mecahnical equipments instead such as lifting table, pallet


trucks etc.
Restrict weight to less kg/person to avoid excessive use of force.

Access ways must be free from any obstructions,wet and uneven


surfaces.
Check material or item to be lifted i.e. size, shape, and weight.

Proper manual lifting technique.


Avoid excessive reaching, pushing and pulling.
Do not give the force to the spine, instead lift load with force on
the legs , keep spine straight, head up.
Manage/supervise fatigue and repetitive actions of workers
manual task.
Ensure that the load do not obstruct the line of sight.
S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
Check fot pinch points while unloading/placing materials.

Proper PPE's must be provided.


5 Use of hand tools Incorrect use of hand tools. Serious harm to people 3 4 12 Use of mechanical means to avoid manual handling as practically 4 1 4 A
possible.
Damaged tools Never use damage tools.
Poorly maintained tools. Never use fabricated tools.
Fabricated tools Damage and fabricated tools should be removed from the site
immediately to avoid re use, or isolate all damage tools.

Not using proper PPE Right tool for the right task will be followed..
Forced postures Pre-start inspection.
Training.
Supervision
Use proper PPE prior to start work
6 Painting Works Fire: Flammable paints, Tinner. Serious Injuries,Damage to 4 4 16 Manufacturers MSDS must be present on the area. Ensure fire 3 1 3 A
Property fighting equipment is present and clearly marked. Fire
plan/emergency plan must be familiar to all workers. Escape
routes clearly marked and free of obstructions. A "No Smoking"
sign and No sSmoking Policy whilst on work must be implemented.

Spills Environmental impact. 3 4 12 Dip trays to avoid ground contamination. Follow HAZMAT 2 1 2 A
handling, storage and disposal. Waste paint tins and thinners to be
consider as hazardous materials. Romoval of combustibvle
materials/waste from painting storage areas. Storage area must be
kept away from any sourse of ignitions ventilated, and signages
installed. Proper disposal of paint waste must be observed
(contact local authority for approved disposal).

Airborne particle Adverse lung deseases. 3 4 12 Ventillation/Air circulation on work areas must be in acceptable 2 2 4 A
Inhilation of fumes lavel. Refresher/Training course must be given.

Permit to Work is a must prior to start the work,especially when


working on areas which has limited air ventillation.

TBT and supervision is a must prior to start any painting works.

Appropriate PPE's must be given,especially breathing apparatus.


S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
Skin damage or contamination Skin irritation 3 3 9 Correct training in use of P.P.E equipment to be 2 1 2 A
provided.
Eye damage from splashing paint. Eye injury 3 3 9 Ensure correct PPE is used and is suitable for the task. 2 2 4 A
Falls of ladders 3 3 9 Correct training in the use of portable ladders & 3 1 3 A
working from heights.
Falls Trips over materials when 3 3 9 Ensure warning signs are erected or the area is 3 1 3 A
brushing barricaded off. Ensure when working under others, safety head
or rolling on paint protection is worn

7 Portable Electrical power tools and Electricity Serious harm to people. 4 4 16 Care to be taken during uPVC and carbon steel cutting to avoid 4 1 4 A
electrical equipement. Electric shock hand injuries. All tools shall be fitted with adequate fuse protect.  
Connection of electrical tools to be routed through ELCB.

Fire, Flammable/explosive atmosphere Loss or damage to assests. 3 4 12 Only trained workers shall use the steel cutting job. Do not use 4 1 4 A
heat generating equipment without Hot Work Permit.
Do not work near flammables, compressed gases, in explosive
atmospheres or confined spaces without specialist advice.

Contact with moving parts / rotating parts. Electrical shock, Short circuit 3 4 12 All power feeds, electrical, pneumatic or hydraulic power tools are 4 1 4 A
due to electricity. . Personal maintained in good good condition. All tools shall be class 2 double
injury-bruise, cuts. insulated Or have reinforced insulation.
Laceration & Abrasion due to
use of faulty tools

Flying particles,Flying debris, swarf etc. Eye, hand or facial injury. 3 4 12 Loose clothing and long hair to be kept clear of moving parts of 4 1 4 A
Hair or loose clothing power tools.
entagled in moving parts.
Dust, Materials and Small
Projectiles

Use of incorrect power tools Eye injuries from dust, swarf 3 3 9 Eye protection to be worn at all times where there is a reasonably 3 2 6 A
or other fragments. foreeable risk of eye injury. Face shield/goggle shall be worn
Abrasions and Cuts while working.
S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
Noise Hearing damage 3 3 9 Wear hearing protection if above 80dB(A) or if uncomfortably loud 3 2 6 A
(request assessment if in doubt).
Advise nearby persons of hazard.
Supervisors should inform users of risks from noise.
Operatives to be trained in the correct use of power tools.

Vibration Hand/Arm Vibration 4 3 12 Tools producing high levels of vibration to have padded handle to 1 4 4 A
Syndrome (HAVS) reduce the risk of vibration.
Carpal Tunnel Syndrome

Ergonomic Muscular-skeletal injury 3 3 9 Reduce exposure time for all workers using the equipment. 2 3 6 A

Slips, trips and falls Minor injury 3 3 9 Ensure work area is free (as is practicable) from trailing cables, 1 3 3 A
Major injury tools, materials, debris and spills.
Fatal injury All work should be from a suitable and stable work platform.
The use of ladders restricted to trained users and must be cleared
with supervisor.
Monitoring by supervisor and EHS Officer.

To ensure the PTW system compliance.


Ensure Fire Fighting equipment is present and clearly marked

To implement safety checklist before commencing of work.

8 Installation of Fittings Pinch points, trap hand, fingers and feet Personal injuries minor / 2 2 4 Permit to work requirements shall be reviewed and discussed prior 2 2 4 A
major to commencement of the works via toolbox talks.

Improper manual handling of materials / Provide temporary supports and platforms, scaffoldings and access
equipment ladders whenever required.
Incompetent personnel The use of appropriate PPE'S should be imposed to all personnel
involved in the pipe sleeves installation works.

Hit by steel Full boby harness sahall be used if working on heights.

Hit by pipe sleeves Work area shall be barricaded and isolated with safety warning
tape.
Fall from height Proper illumination of the work area and access/escape/exit areas
shall be provided while working at night or in poor illumination.

Inadequate supervision Engineering controls


Personal injuries minor /
major

S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
Manual handling Area of activity should be isolated or barricaded.
Inadequate supports All edges and opening shall be secure to avoid any free fall.

For height work all personnel involved in the work shall have
minimum internal working at height training.

9 Installation of Pipes,Fixing of Pinch points, trap hand, fingers and feet Personal injuries minor / 3 3 9 Permit to work requirements shall be reviewed and discussed prior 2 2 4 A
brackets and drilling of supports. major to commencement of the works via toolbox talks.

Improper manual handling of materials / Provide temporary supports and platforms, scaffoldings and access
equipment ladders whenever required.
Incompetent personnel The use of appropriate PPE'S should be imposed to all personnel
involved in the pipe sleeves installation works.

Hit by steel Full boby harness sahall be used if working on heights.

Hit by pipe sleeves Work area shall be barricaded and isolated with safety warning
tape.
Fall from height Proper illumination of the work area and access/escape/exit areas
shall be provided while working at night or in poor illumination.

Inadequate suoervision Engineering controls


Manual handling Area of activity should be isolated or barricaded.
Inadequate supports All edges and opening shall be secure to avoid any free fall.

For height work all personnel involved in the work shall have
minimum internal working at height training.

Crush and fall in between due to improper Serious injury 3 3 9 Using proper lifting techniques with proper tools and certified 2 2 4 A
lifting and pipe condition. lifting tackles. Set and layout pipe hangers shall be establish and
secure prior to lift the pipe. Temporary supports and hangers is
not permitted.

Stike by flying particles Eye Injury Work Crews Will Use Appropriate PPE. (Hand Gloves, Safety
Goggles)
Falls, Slips, Trips Serious injury 3 3 9 Ensure that housekeeping is done on frequently basis to prevent 3 1 3 A
the walkways from being obstructed.
S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
10 Installation of pipe and pipe’s Caught in Between, Falling objects Finger injury, Injury caused 5 3 15 Beware of pinch point, Wear of gloves, Proper tools box to be 3 2 6 A
supports from height by falling object used, Provide fire cloth.
follow by welding from height, Skin Burn, Eye Ensure fire watch man. Immediately remove excess materials,
Irritations, Health tools and proper
Impairment-Inhalation, Fire. housekeeping. Use proper tools and equipments.Safe work
platform. Ensure Appropriate Barricade and Sign Boards Placed
Around All Hot Works Activities. Provide Adequate Fire Protection
(Provision Of Sand, Fire Blanket, Fire Watchmen and Fire
Extinguishers). Daily Inspection Of Welding Machines and Earthing
Prior To Start Of Work. Welders Shall Be Trained and Competent.
Welders Shall Have A Valid Certification. Welding Cables Shall Be
Inspected And Color Coding To Ensure Good Condition. Obtain Hot
Works Permit Prior To Beginning Works. First Aid Kit Will Be
Available.

Strike by flying Fire , Eye injury, skin 4 3 12 Use of proper PPE - Welding masks, Welding gloves,Welding
particles during welding, Electrical irritation, inhilation of shield, Safety Glass
welding fumes,Electrocution -Proper ventilation
-Permit to work system
-Periodic checking of electrical tools

11 Hot Works: Welding, Gas Cutting, Working on hot surfaces/ flames/ molten metalBurns / arc flash 4 4 16  Adopting administrative control measures like work permits, 2 3 6 A
Grinding, Heating and Alike Use of electricity. Cardiac arrest due to electric 4 4 16 method statements,
Provision workconductors
of double earth procedures,and
imparting training, Current
RCCBs (Recsidual 1 4 4 A
shock, Burn Circuit Devic) to avoid electric shock. Pre-inspection of machines,
cables by a qualified electrician.

Emission of fumes and gases Respiratory / lung illness / 3 3 9 Giving proper training using the proper eye protection methods 2 3 6
acute & chronic effects on like welding shield, Providing UV filter safety glass for all workers.
human body roviding proper signage. roviding appropriate PPE.

Handling and storage of gas cylinders Explosion of gas cylinders 3 4 12 sing gas cylinder trolleys. Shifting gas cylinders with mechanical 1 3 3 A
may lead to fatal / severe aids. Storage of DA/Oxygen cylinders separately in upright
injuries. Fall of cylinders on position. Using appropriate PPE while handling the gas cylinders.
workmen may lead to Securing the gas cylinders to avoid fall of cylinder.
injuries.

Flash back / fire Explosion of gas cylinders 2 4 8 Using standard NRVs on the cylinder side. Flash back arresters are 1 4 4 A
may lead to fatal / severe providing on the cutting torch. Adequate fire extinguishers are
injuries. ensuring before start of work. Ensuring the deployment of skilled
personnel for gas cutting. Providing barricades and maintain good
housekeeping.
S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
Use of electrical driven machines. Cardiac arrest due to electric 2 4 8 Provision of double earth conductors & RCCBs to avoid electric 1 4 4 A
shock, Electrocution. shock. Pre-inspection of machines, cables by a qualified
electrician.

Rotating equipment with breakable flying Cut injuries due to Incorrect 2 4 8 Selection, usage and maintenance of flying wheels. Checking the 1 4 4 A
wheels, Flying of Melton metals, run / operation quality, RPM capacity of grinding wheel before issuing from store.
Performing ring tests for the grinding wheels and ensuring its
standard.

Injury due to flying particles Giving proper training using the proper eye protection methods
& cut off wheels. like welding shield, Providing UV filter safety glass for all workers.
roviding proper signage. roviding appropriate PPE.

Fire hazard due to the hot Follow hotwork permit.


metal particles
12 Manual Handling Ligament strains. Muscle strains. Physical Injury 3 3 9 Full training and instruction provided in both induction and on- 3 1 3 A
Fatigue. going
Abdominal hernias. safety training.
Prolapsed/ herniated discs. Design out the need for manual handling where possible
Paralysis. Mechanical aids used wherever possible
Workers adhere to guideline weights & to only lift what they are
able to lift
Assess the load
Weights marked on all loads.
Lift smaller loads.
Cutting pipes to length
Mandatory PPE worn

13 Material Lifting Failure of lifting gear, Fall of load due to Injury due to hit by the 3 3 9 Lifting of any materials should be done only by means of chain or 3 2 6
failure of lifting gears or faulty attachments. falling materials. Risk of hoist appropriately supported. Avoid standing right below to items
Hit by hanging load. Improper balance of load. tipping over Failed lift due to being raised. Always use proper slings other approved media for
failure of lifting gear binding the items to be lifted. Ensure adequate lighting and
ventillation whenever working in confined spaces. Carryout works
in such areas, only when free entrance and exit and to the area is
ensured and entry/exit is continually manned during the whole
working period.
S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
14 Erection of • Unauthorized • Fall from 4 3 12 Ensure that scaffold is erected by certified scaffolders under the 4 1 4
Scaffolds personnel. height/ fall of competent supervision.
• Unsecured erection materials/ Ensure that the erection sequence is followed.
sequence. struck by Ensure that the materials are hauled up by rope and pulleys.
• Stacking of materials scaffold Keep only authorized person on erection site. Ban stacking of
on working platforms. components materials on working platforms.
• Unsecured mobile during erection/ Ensure that the area is cleared off materials and proper
scaffold platforms. slip, trip and housekeeping is maintained.
fall. If mobile scaffold platforms are erected, ensure the wheels are
chocked before someone getting access to the working platform.
Do not move the scaffold while someone is working on it.
Ensure the scaffolds are modified only by competent scaffolders.
Ensure the scaffolds are inspected every 7th day by scaffold
supervisor and tagged.

15 Working at heights Using scaffolds Fall of person or material. Personal injury 4 3 12 Ensuring fall protection devices are properly used by all the 3 2 6
and portable ladder Fall from height,Topple of scaffolds, failure of Serious Injury workforce working
Any scaffolding at height.
members ( i.e.Suitable work platform
pipes, clamps, shall must
boards etc.) be be
out rigger supports. provided with toe
on standard boards.
Overturnung of scaffold or ladder Prior to use, or
anyacceptable
scaffoldinglevel.
works must be checked by competent
Material falling scaffolding inspector.
Provide Handrails as a means of protection whenever there is an
Contact overhead power lines. openings
Castor or edges
wheels shallwhich the risk
be armed withofbreaks.
fall is present.
Mobile scaffold shall not
Proper access and egress, approved type of ladders. Adequate
access ladders
Closely shallbe
monitored the fitted
activity, Supervision.
Use of Personal Fall Arrest System (PFAS) and PPE's.
14 Working interfaces with others trades Inadequate access for other contractor Injury or loss of life due to 4 2 8 Quest Air operations will interface with other trade contractors 1 2 2 A
/ contractors hazardous situations / operations
inadequate signages and
Site are not fully secured. barriers. To protect other works Quest Air shall set up exclusion zones
around hazardous activities and post relevant signages.

Inadequate site access control Quest Air employees shall not access exclusion zones set up by
other trades.
Quest Air employees shall not interfere with or use any equipment
or materilas owned by other trade contractors.

B.2. Coring and Cutting Works


1 Coring and Cutting Pinch points, trap hand, fingers and feet Personal injuries minor / 3 3 9 Permit to work requirements shall be reviewed and discussed prior 2 2 4 A
major to commencement of the works via toolbox talks.
S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
Improper manual handling of materials / Provide temporary supports and platforms, scaffoldings and access
equipment ladders whenever required.

Incompetent personnel The use of appropriate PPE'S should be imposed to all personnel
involved in the pipe sleeves installation works.

Hit by steel Full boby harness sahall be used if working on heights.

Hit by concrete Work area shall be barricaded and isolated with safety warning
tape.
Fall from height Proper illumination of the work area and access/escape/exit areas
shall be provided while working at night or in poor illumination.

Inadequate supervision Engineering controls


Manual handling Area of activity should be isolated or barricaded.
Inadequate supports All edges and opening shall be secure to avoid any free fall.

For height work all personnel involved in the work shall have
minimum internal working at height training.

Crush and fall in between due to improper Serious injury 3 3 9 Using proper lifting techniques with proper tools and certified 2 2 4 A
lifting and equipment condition. lifting tackles. Set and layout pipe hangers shall be establish and
secure prior to lift the pipe. Temporary supports and hangers is
not permitted.

Stike by flying particles Eye Injury Work Crews Will Use Appropriate PPE. (Hand Gloves, Safety
Goggles)
Falls, Slips, Trips Serious injury 3 3 9 Ensure that housekeeping is done on frequently basis to prevent 3 1 3 A
the walkways from being obstructed.
Contact with moving parts / rotating parts. Electrical shock, Short circuit 3 4 12 All power feeds, electrical, pneumatic or hydraulic power tools are 4 1 4 A
due to electricity. . Personal maintained in good good condition. All tools shall be class 2 double
injury-bruise, cuts. insulated Or have reinforced insulation.
Laceration & Abrasion due to
use of faulty tools

B.3. Hydro Testing of Pipes:


S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
1 Pre-Test Checks and Inspections Valve failure due to excess pressure Serious Injury 4 4 16 Make available a highlighted drawing of area intended for 2 2 4 A
hydrostatic pressure
testing. Obtain Pressure Test Permit Prior To Start Of Work. First
Aid Kit Will Be Available.Isolate the area, Conduct TBT to all
involved person Compressed Air Training As Tool Box Talks Topic.

Prior to commencing testing operations, the Company


Representative shall inspect test heads to confirm all components
are in good condition and meet working
pressure requirements.

Confirm that the following conditions are checked prior to testing:


Manifolds and other facilities are properly installed and will be
adequately protected
from damage in the event that violent failures or water surges
occur. There are no unrestrained coupled fill lines. Fill lines are
able to contain initial water pack pressure.Methods of isolating
facilities being tested from test equipment and pumps are
adequate. nspect and x-ray all temporary welds on test headers
subject to test pressures.

2 LEAK TEST Pinch points, trap hand, fingers and feet Personal injuries / minor or 2 2 4 Permit to work requirements shall be reviewed and discussed prior 2 2 4 A
major to commencement of the works via toolbox talks.

Improper manual handling of materials / equi Provide temporary supports and platforms, scaffoldings and access
ladders whenever required.

Incompetent personnel The use of appropriate PPE'S should be imposed to all personnel
involved in the pipe sleeves installation works.

Hit by structure All personnel employed an all pressure testing works shall be
experience in their applicable trade.

Hit by flanges Works area shall be barricaded and isolated with safety warning
tape
Valve slip or failure Proper illumination of the work area and access/escape/exit areas
shall be provided while working at night or in poor illumination.

Inadequate supervision Engineering Controls


Faulty guages No one should be nearby the working area.
S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
More pressure than required, Inadequate All supports should be complying with the requirements
supports
3 Pressure Testing Valve failure due to excess pressure. Serious Injury 4 4 16 Before attempting any test, the Testing Supervisor will review the 2 2 4 A
test specifications and procedures with the Test Inspector, Chief
Inspector, and any other relevant personnel to be certain that all
equipment is adequate and duties are organized and understood.
Inform all personnel of assignments, responsibilities, and test
requirements.

Ensure that any requirements for guarding against over-pressure


are observed. Hydro test test Area shall be barricaded and provide
warning boards to prevent personnel entry. High-pressure pipe
and fittings shall be used for connection of the pressure pump,
manifolds, and test equipment.

Rupture of pressurised system during Potentially causing injury to 3 3 9 Ensure that connection adaptors are the correct and inspected 3 1 3 A
operation of the hand pump operator or by standers prior to test. Ensure all persons in the working environment are
suitably protected from flying debris and hydraulic media in the
event of rupture.

Damage to surrounding Ensure that any flexible hoses or pipework are suitably rated for
equipment/ working maximum working pressure. Rating of fittings, pressure gauges,
environment vent valves, gaskets shall be suitable for the test pressure.

Ensure all other equipment used is regularly maintained,


inspected, tested and calibrated in accordance with
manufacturer’s procedures or as defined otherwise. Calibrated
pressure gauges and Pressure safety valves only shall be used.

Wearing of safety glasses for operator and those in the working


environment mandatory.

All the temporary welding shall be performed by qualified welders.

Pressure should be raised gradually under control to allow time for


pipes to strain and time for personnel to check for leaks.

Supervisors shall be present at work location during hydro testing


activities are done.
S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
Pinch points, trap hand, Personal 2 2 4 Permit to work requirement shall be reviewed 2 2 4 A
fingers and feet. injuries/ minor and discussed prior to commencement of the
or major works via tool box Talks.

Improper manual Provide temporary supports and platforms,


handling of scaffoldings and access ladders wherever
materials/equipments. required.
Incompetent personnel. The use of appropriate PPE’s should be imposed to all personnel
• Hit by Structure involved in the water pressure testing works.
• Hit by flanges All personnel employed in all pressure testing
• Valve slip or failure works shall be experienced in their applicable trade.
• Inadequate supervision Work area shall be barricaded and isolated with safety warning
• Faulty gauges tape.
• More pressure than Proper illumination of the work area and access/escape/ exit areas
required shall be provided while working at night.
• Inadequate supports Engineering controls.
No one should be near by the working area.
Site Engineer shall monitor the activity and unauthorized entry
should be prohibited.

B.4. FLUSHING

1 Depressurizing / Dewatering Injury due to slips, trips and falls. Injury due to Operatives /Staff/ Visitors 3 2 6 All temporary fill and dewater piping should be connected with 2 1 2 A
manual handling Others welded/screwed joints.
Verify the length and integrity of welded/screwed connections
prior to depressurizing.
Properly de-pressurize connecting lines before attempting to seal
or break joint Components.
When bleeding the pressure from a section of the line, use
extreme caution, especially when deflectors such as ells are used.
Slowly bleed pressure following a test.
Confirm that the diversion of water and will follow a safe pathway
Always verify that complete depressurization has occurred through
the use of pressure gauges and visible checks.
The atmosphere shall be monitored for safety during any blow
down, bleed off or depressurization.
During the initial planning stage of a de-watering operation, an
analysis of the existing and temporary piping system should be
performed to identify the pressure associated with fluids and other
forces that could adversely affect the integrity of the pipeline or
the stability of the drainage and its components.
Securely support and tie down dewatering lines at the discharge
end to prevent uncontrolled movement during dewatering.
The following guidelines should be followed in de-watering
activities:
Anchor the de-watering lines. It is accepted industry practice to
adequately anchor or secure de-watering piping to prevent
movement and separation of the piping. Establish effective
anchoring systems based on expected forces and ensure that the
systems are used during de-watering projects.
Ensure condition of couplings and parts. All couplings and parts of
the de-watering system need to be properly selected for their
application. The associated piping which the couplings connect is a
Depressurizing / Dewatering Operatives /Staff/ Visitors 3 2 6 All temporary fill and dewater piping should be connected with 2 1 A
Others welded/screwed joints.
Verify the length and integrity of welded/screwed connections
prior to depressurizing.
Properly de-pressurize connecting lines before attempting to seal
or break joint Components.
S/N When bleeding the pressure from a section of the line, use
extreme caution, especially when deflectors such as ells are used.

Remarks (Acceptable: A/ Not-


Base Risk Slowly bleed pressure following a test. Residual Risk
Confirm that the diversion of water and will follow a safe pathway
Always verify that complete depressurization has occurred through

Acceptable: NA)
the use of pressure gauges and visible checks.

1 to 25

1 to 25
The atmosphere shall be monitored for safety during any blow

1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure
down, bleed off or depressurization.
During the initial planning stage of a de-watering operation, an
analysis of the existing and temporary piping system should be

Probability

Probability
performed to identify the pressure associated with fluids and other

Severity

Severity
Risk

Risk
forces that could adversely affect the integrity of the pipeline or
the stability of the drainage and its components.
Securely support and tie down dewatering lines at the discharge
end to prevent uncontrolled movement during dewatering.
The following guidelines should be followed in de-watering
activities:
Anchor the de-watering lines. It is accepted industry practice to
adequately anchor or secure de-watering piping to prevent
movement and separation of the piping. Establish effective
anchoring systems based on expected forces and ensure that the
systems are used during de-watering projects.
Ensure condition of couplings and parts. All couplings and parts of
the de-watering system need to be properly selected for their
application. The associated piping which the couplings connect is a
significant variable in the entire mechanical piping system. The
couplings are manufactured in a controlled environment, and
variations in the quality of the couplings should be limited. Ensure
that couplings are within manufacturer's tolerances and free of
damage that may result in connection failure.
Notify all personnel that the area is all clear.

C. ENVIRONMENTAL RISK ASSESSMENT


1 Impacts on Air • Excavation Works • Fugitive dust 4 2 8 Provide dust masks 2 2 4 A
Quality (Dust) • Handling of excavated emissions Dust suppression before and during
materials • Visible dust excavations
• Stockpiling of excavated plumes Watering and covering stockpiled material
soils • Deterioration of with mesh
breathable air Covered transport and hauling of excavated
quality material using green mesh after applying
water
Earth moving activities to be halted in high
winds facing sensitive receptors.
S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
2 Noise • Some site activities may • Potential 4 4 16 Carry out Noise assessments using Sound meter. 4 1 4 A
generate excessive serious harm to If found to be excessive >85db ensure that workers are using ear
noise (Generator, Angle people if control measures protection Regular
Grinder, Heavy Equipment, are not carried out correctly visits to job site to ensure measures are
Compressor, Concrete • Noise can create a safety being maintained.
Cutter etc) risk if it makes it difficult for Signage to be erected.
workers to Noise risk assessments to identify any potentially noisy operations
communicate will be completed as required
effectively or stops them Noise control systems implemented via insulation and shielding
hearing warning where possible to reduce the effects of noise on the operator and
signals. other(s) working in area
Selection of appropriate plant and equipment
Information, instruction, training and supervision
Planned maintenance and inspection regimes
Reduce time period of operative use of plant
Selection and use of PPE as a last resort

3 Chemical • Chemicals • Eye contact 4 4 16 All Chemicals will be stored in designated containers. 4 1 4 A
Handling • Fumes • Skin contact Restrict access to storage areas to authorized personnel.
• Empty COSHH • Ingestion Copies of MSDS and COSHH assessments shall be available at the
containers disposal • Burn place of storage
• Illness Ensure that all hazardous substances are stored in a suitable and
• Irritation safe place.
RISK MATRIX
Very Likely - 5 5 10 15 20 25
Likely - 4 4 8 12 16 20
PROBABILITY
Possible - 3 3 6 9 12 15
à
Unlikely - 2 2 4 6 8 10
Very Unlikely - 1 1 2 3 4 5
1 2 3 4 5
Moder
Negligible Slight High Very High
ate
SEVERITY à

Risk Risk Level Action


May be acceptable but review task to see if risk can be reduced further,Consideration should be given as to whether the risk can be lowered but the cost of additional risk
reduction measures should be taken into account. The risk reduction measures should be implemented within a defined time period. Arrangements should be made to
1 to 6 Low Risk ensure that the controls are maintained, particularly ifthe risk levels are associated with harmful consequences.

Substantial efforts should be made to reduce the risk. Risk reduction measures should be implemented urgently within a defined time period and it might be necessary to
consider suspending or restricting the activity or to apply interim risk controls, until this has been completed . Considerable resources migh have to be allocated to
8 to 12 Medium Risk additional controls.Arrangements should be made to ensure that the controls are mantained , particularly if the risk levels are associated with extremely harmful
consequences and very harmful concequences.
S/N

Remarks (Acceptable: A/ Not-


Base Risk Residual Risk

Acceptable: NA)
1 to 25

1 to 25
1 to 5

1 to 5

1 to 5

1 to 5
Sub-Activity Potential Hazard Risk Proposed Control Measure

Probability

Probability
Severity

Severity
Risk

Risk
Substantial efforts should be made to reduce the risk. Risk reduction measures should be implemented urgently within a defined time period and it might be necessary to
consider suspending or restricting the activity or to apply interim risk controls, until this has been completed . Considerable resources migh have to be allocated to
8 to 12 Medium Risk additional controls.Arrangements should be made to ensure that the controls are mantained , particularly if the risk levels are associated with extremely harmful
consequences and very harmful concequences.

This risks are unnaceptable. Substancial improvement s in risk controls are necessary so that the risk is reduced to an uncceptable level. The work activity should be halted
until risk controls are implemented that reduce the risk so that it no longer very high. If it is not possible to reduce the risk the work should remain prohibited
15 to 25 High Risk