Check List For Pre-Commissioning / Commissioning Activity: H:/JOBS/Pre-Commissioning Checklist - R0 (J10603)
Check List For Pre-Commissioning / Commissioning Activity: H:/JOBS/Pre-Commissioning Checklist - R0 (J10603)
Check List For Pre-Commissioning / Commissioning Activity: H:/JOBS/Pre-Commissioning Checklist - R0 (J10603)
We have received the SKID as per our above referred PO. along with the Invoice as mentioned above.
According to us, the SKID is ready for commissioning. We have verified the current site status as under.
YES NO
3. All vents supplied loose for safe transportation are properly mounted as
per P&ID/GAD.
4. All instruments items like PG, TG etc supplied loose for safe transportation,
are available and installed.
8. In case you intend to use Nitrogen cylinder, Do you have hose for Connecting Cylinder
to skid? (at skid end ½” NPT (M) connection is needed)
11. Natural Gas available for commissioning (Charging). If NO, when it is expected.
Site
Address:______________________________________________________________________________________
___
__________________________________________________________________________________________
__________________________________________________________________________________________
Note: Kindly arrange for the Gate Pass for our engineer and make it available to us/ him during the visit
for SKID commissioning.
Thanking you,
_______________________________
Name:
Designation: