Earthwork in Excavation in Foundation - Total Foundation - Total Substructure Brickwork With Cement Mortar

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 7

Details of

Dimensions
Item no Description of Work No. Length

1 Earthwork in excavation in foundation - 77.62512


Total
2 Foundation - 77.62512
Total
3 Substructure Brickwork with Cement Mortar

1st footing - 79.72512


2nd footing - 80.42512
Plinth walls (Below G.L.) - 81.12512
Plinth walls ( Above G.L.) - 81.12512
Total
4 s - 81.12512
Subtracting extra DPC(25mm)
Door 1 2 0.9
Door 2 1 1.25
Door 3 1 1.17
Door 4 1 3.13
Total
5 Super structure Brickwork with Lime mortar - 82.07512
Subtracting extra
Door 1 2 0.9
Door 2 1 1.25
Door 3 1 1.17
Door 4 1 3.13
Total
Details of Measurements
Dimensions
Breadth Height/Depth Quantities Unit

0.9 1 69.862608 m3
69.862608 m3
0.9 0.3 20.9587824 m3
20.9587824 m3

0.6 0.2 9.5670144 m3


0.5 0.2 8.042512 m3
0.4 0.3 9.7350144 m3
0.4 0.6 19.4700288 m3
46.8145696 m3
0.4 _ 32.450048 m2

0.4 0.72 m2
0.4 0.5 m2
0.4 0.468 m2
0.4 1.252 m2
29.510048
0.2 4 65.660096 m3

0.2 1.8 0.648 m3


0.2 1.8 0.45 m3
0.2 1.8 0.4212 m3
0.2 2.1 1.3146 m3
62.826296 m3
Remarks
Total Centre lIne length =
83.92512
No. of Junctions :
200 to 200 wall = 5
200 to 300 wall = 9
Total length = centre line distance - 5*breadth1/2 - 9*breadth2/2
breadth1 = breadth of 200 wall
breadth = breadth of 300 wall
Details of Meas
Dimensions
Item no Description of Work No. Length Breadth

1 Earthwork in excavation in foundation - 58.6664 0.9


Total
2 Foundation - 58.6664 0.9
Total
3 Substructure Brickwork with Cement Mortar

1st footing - 59.1164 0.6


2nd footing - 59.2664 0.5
Plinth walls (Below G.L.) - 59.4164 0.4
Plinth walls ( Above G.L.) - 59.4164 0.4
Total
4 D.P.C - 59.4164 0.4
Subtracting extra DPC(25mm)
Door 5 2 1.3 0.4
Door 6 1 1.2 0.4
Door 7 1 1.17 0.4
Total
5 Super structure Brickwork with Lime mortar - 59.5664 0.3
Subtracting extra
Door 5 2 1.3 0.3
Door 6 1 1.2 0.3
Door 7 1 1.17 0.3
Window 1 1 1.3 0.3
Window 2 1 1.95 0.3
Window 3 1 1.56 0.3
Window 4 1 2.3 0.3
Total
Details of Measurements
mensions
Height/Depth Quantities Unit

1 52.79976 m3
52.79976 m3
0.3 15.839928 m3
15.839928 m3

0.2 7.093968 m3
0.2 5.92664 m3
0.3 7.129968 m3
0.6 14.259936 m3
34.410512 m3
_ 23.76656 m2

1.04 m2
0.48 m2
0.468 m2
21.77856
4 71.47968 m3

1.8 1.404 m3
1.8 0.648 m3
1.8 0.6318 m3
1.3 0.507 m3
1.3 0.7605 m3
1.3 0.6084 m3
2.1 1.449 m3
65.47098 m3
Remarks
Total Centre lIne length =
60.0164
No. of Junctions :
300-300 Junction =3
total length = centre distance - 3*breadth/2
Net Quantity Required
S. No. Work Quantity Unit

1 Earthwork in excavation in foundation 122.65 m3

2 Foundation 36.77 m3

3 Substructure Brickwork with Cement Mortar 81.22 m3

4 D.P.C 51.28 m2

5 Super structure Brickwork with Lime mortar 128.29 m3