Megha Engineering & Infrastructures Ltd.

Project : Ukai Nizar PS 5 Kukarmunda, Tapi, Gujarat Project Code : 1248


Mahalaxmi Constraction Sand Supplied Details for the Month of FEB&MARCH'21
Location &
Inward No Tripsheet No Date Material Description Meil Qty MT Meil Qty in CFT Party name Rate Amount Truck No Length Width
Purpose

2167 364179 7/2/21 Sand 18.25 416.55 Mahalaxmi Constraction 410 7,482.50 PS 5 GJ30T0537 5.020
2168 364180 7/2/21 Sand 33.92 703.47 Mahalaxmi Constraction 410 13,907.20 PS 5 GJ26T8386 7.02

2198 364186 18/2/21 Sand 37.89 836.71 Mahalaxmi Constraction 410 15,534.90 PS 5 GJ26T8429 7.02

2199 364187 18/2/21 Sand 39.13 863.35 Mahalaxmi Constraction 410 16,043.30 PS 5 GJ26T8386 7.02
2227 364190 25/2/21 Sand 42.46 842.04 Mahalaxmi Constraction 410 17,408.60 PS 5 GJ26T8429 7.02

2228 364191 25/2/21 Sand 39.64 831.38 Mahalaxmi Constraction 410 16,252.40 PS 5 GJ26T8429 7.02
2230 364193 25/2/21 Sand 41.98 847.36 Mahalaxmi Constraction 410 17,211.80 PS 5 GJ26T8429 7.02
2233 364194 26/2/21 Sand 43.12 836.71 Mahalaxmi Constraction 410 17,679.20 PS 5 GJ26T8429 7.02

2235 364196 26/2/21 SAND 41.2 847.36 Mahalaxmi Constraction 410 16,892.00 PS 5 GJ26T8429 7.02

2251 364701 1/3/21 SAND 42.1 863.35 Mahalaxmi Constraction 410 17,261.00 PS 5 GJ26T8429 7.02
2252 364702 1/3/21 SAND 42.67 900.66 Mahalaxmi Constraction 410 17,494.70 PS 5 GJ26T8386 7.02

2254 364704 2/3/21 SAND 42.64 879.34 Mahalaxmi Constraction 410 17,482.40 PS 5 GJ26T8429 7.02

2257 364707 2/3/21 SAND 37.95 758.12 Mahalaxmi Constraction 410 15,559.50 PS 5 GJ30T0537 5.020
2258 364708 2/3/21 SAND 43.65 953.95 Mahalaxmi Constraction 410 17,896.50 PS 5 GJ26T8386 7.02

2259 364709 2/3/21 SAND 42.24 868.68 Mahalaxmi Constraction 410 17,318.40 PS 5 GJ26T8429 7.02
2260 364710 2/3/21 SAND 38.3 774.79 Mahalaxmi Constraction 410 15,703.00 PS 5 GJ30T0537 5.020

2261 364711 2/3/21 SAND 35.83 745.63 Mahalaxmi Constraction 410 14,690.30 PS 5 GJ30T0537 5.020

2264 364714 3/3/21 SAND 36.3 753.96 Mahalaxmi Constraction 410 14,883.00 PS 5 GJ30T0537 5.020
2284 364733 5/3/21 SAND 37.74 810.06 Mahalaxmi Constraction 410 15,473.40 PS 5 GJ26T8429 7.02

2296 364735 9/3/21 SAND 35.26 728.97 Mahalaxmi Constraction 410 14,456.60 PS 5 GJ30T0385 5.020

2297 364736 9/3/21 SAND 38.29 770.62 Mahalaxmi Constraction 410 15,698.90 PS 5 GJ30T0537 5.020

2302 364739 10/3/21 SAND 20.26 412.39 Mahalaxmi Constraction 410 8,306.60 PS 5 GJ30T0537 5.020

2303 364740 10/3/21 SAND 19.22 395.72 Mahalaxmi Constraction 410 7,880.20 PS 5 GJ30T0385 5.020

2308 364745 11/3/21 SAND 28.5 604.00 Mahalaxmi Constraction 410 11,685.00 PS 5 GJ30T0385 5.020
2309 364746 11/3/21 SAND 35.52 749.79 Mahalaxmi Constraction 410 14,563.20 PS 5 GJ30T0537 5.020

2315 364747 12/3/21 SAND 19.38 383.23 Mahalaxmi Constraction 410 7,945.80 PS 5 GJ30T0537 5.020

2316 364748 12/3/21 SAND 20.69 412.39 Mahalaxmi Constraction 410 8,482.90 PS 5 GJ30T0385 5.020

2319 364750 13/3/21 SAND 33.26 731.47 Mahalaxmi Constraction 410 13,636.60 PS 5 GJ26T8386 5.06

2320 364751 13/3/21 SAND 33.22 719.46 Mahalaxmi Constraction 410 13,620.20 PS 5 GJ26T8429 7.02

2333 364760 16/3/21 SAND 27.15 562.35 Mahalaxmi Constraction 410 11,131.50 PS 5 GJ30T0385 5.020
2342 364763 17/3/21 SAND 22.37 454.04 Mahalaxmi Constraction 410 9,171.70 PS 5 GJ30T0385 5.020

2344 364764 17/3/21 SAND 20.41 437.38 Mahalaxmi Constraction 410 8,368.10 PS 5 GJ30T0385 5.020

2361 364770 20/3/21 SAND 42.92 900.66 Mahalaxmi Constraction 410 17,597.20 PS 5 GJ26T8429 7.02

2362 364771 20/3/21 SAND 42.11 879.34 Mahalaxmi Constraction 410 17,265.10 PS 5 GJ26T8386 7.02

2394 364780 25/3/21 SAND 19.57 399.89 Mahalaxmi Constraction 410 8,023.70 PS 5 GJ30T0385 5.020

2395 364781 25/3/21 SAND 27.91 574.84 Mahalaxmi Constraction 410 11,443.10 PS 5 GJ30T0537 5.020

RECEIVED QTY IN MT
Material
PS-5 Site Others Total
SAND 1223.05 0 1223.05