ID Task Task Name Duration Start Finish 20 Jun '22 27 Jun '22 4 Jul '22 11 Jul '22

Mode T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1 Additional Works Breakdown 18 days Sat 18/6/22 Thu 14/7/22
2 New additional concrete sump 3 (done) 2 days Sat 18/6/22 Mon 20/6/22
3 Hacking for drain connection to DBKL main drain 1 day Fri 1/7/22 Fri 1/7/22
4 Connection to DBKL drain FW installation & Casting 2 days Fri 1/7/22 Tue 5/7/22
5 Angle post, base block & mass footing concrete 3 days Tue 5/7/22 Fri 8/7/22
footing installation / Casting
6 Formwork installation for exposed fencing base block 1 day Fri 8/7/22 Sat 9/7/22
7 4 strands PVC barbed wire installation 1 day Mon 11/7/22 Tue 12/7/22
8 Fencing galv. Chain mesh installation 1 day Mon 11/7/22 Tue 12/7/22
9 Bottom fencing barbed wire installation 1 day Tue 12/7/22 Wed 13/7/22
10 Turfing on bottom slope area 1 day Wed 13/7/22 Thu 14/7/22

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: msproj11 Split External Tasks Inactive Summary Manual Summary Progress
Date: Thu 30/6/22
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only