Professional Documents
Culture Documents
Facilities Project
Facilities Project
Facilities Project
Facilities Planning
Spring 2020
NAME: ID’S
Ibrahim Sami U16200472
Hussam Shehadeh U16200529
Ali Mohamed Almaazmi U17101072
In this project we will design the layout of the production area of a company, that
manufactures baking machines, constrained to given area of 2400m2 and production volume
of 1000 units per year. Number of parts and their detailed description of baking machines is
given in the Bill of Material table of Appendix A. Their assembling information is in
Assembly Chart of Appendix B. Area requirements of machines used to manufacture different
parts is given in Appendix C. Appendix D gives the details of operations and their sequence
used to produce different parts of Baking Machine.
2
Contents
Abstract......................................................................................................................................2
Table Of Figure..........................................................................................................................5
List Of Tables.............................................................................................................................6
1.1 Introduction......................................................................................................................7
1.2 Objectives.........................................................................................................................7
1.3 Constraints........................................................................................................................7
1.4 Assumptions.....................................................................................................................7
2.2.5 From-To-Chart........................................................................................................15
3.1 Departments...................................................................................................................16
3
4.1 Alternative 1...................................................................................................................19
References................................................................................................................................24
4
Table Of Figure
Figure 1: Relationship Dia.........................................................................................................9
Figure 2: Relationship Dia(1).....................................................................................................9
Figure 3: Relationship Dia(2).....................................................................................................9
Figure 4: Bread Baking Machine.............................................................................................11
Figure 5: Departments Information..........................................................................................16
Figure 6: Department Relation.................................................................................................17
Figure 7: FactoryPLAN Legend...............................................................................................17
Figure 8: Relationship Diagram...............................................................................................18
Figure 9: Relationship Chart....................................................................................................18
Figure 10: Alternative Layout 1...............................................................................................19
Figure 11: Alternative Layout 2...............................................................................................21
Figure 12: Alternative Layout 3...............................................................................................22
5
List Of Tables
Table 1: Relationship Dia...........................................................................................................8
Table 2: Relationship Dia(1)......................................................................................................8
Table 3: Relationship Dia(2)......................................................................................................8
Table 4: Bill of Material...........................................................................................................12
Table 5: Departments Space Requirements.............................................................................12
Table 6: Route Sheet(Cylinder)...............................................................................................13
Table 7: Route Sheet(Dough Container)..................................................................................13
Table 8: Route Sheet(Holder)..................................................................................................14
Table 9: Route Sheet(Pushing Plate).......................................................................................14
Table 10: From-To-Chart.........................................................................................................15
Table 11: Distance Chart for Layout 1.....................................................................................20
Table 12: Distance Chart for Layout 2.....................................................................................21
Table 13 Distance Chart for Layout 3......................................................................................22
6
CHAPTER 01: Project Background
1.1 Introduction
Layout plan of a production company is it’s floor plan devised to determine and arrange the
desired machineries and equipment of a plant. It permits the quickest flow of sub-parts and
materials to produce the final product with minimal cost material handling. In order to design
a facility layout different factors are taken into account like production area, production
volume, materials and machineries requirements, labors and building requirements. An ideal
layout plan allows improved productivity, high machines utilization and flexibility for
volume and products.
1.2 Objectives
The main objectives of this project are to:
1.3 Constraints
Facility Layout plan for this project is constrained to following factors:
1.4 Assumptions
Following assumptions are made in solving the problem:
All outsourced parts and materials are initially transferred to raw-material department.
Finished parts and outsourced parts are moved to assembly department for
assembling.
Material flow between assembly department and finished product is marked as
important I.
Area of aisles, walls and inventory space is included in the given area.
7
Material flow is considered from center of one department to another and is
rectilinear.
Enter and exit aren’t pre-defined and will be adjusted with optimal layout.
A B C D E F
A 1000 1800 300
B 300 300
C 1500
D 1500
E
F
2. Based on these flows, the relationship diagram representing qualitative relation can be
as in table below:
A B C D E F
A E A U U O
8
B O U O U
C A U U
D U A
E U
F
3. Next step is the construct nodal diagram. In this diagram the work centers are
represented by nodes and the number of lines between nodes represents the
relationship or closeness value.
3.1 Initially, the blocks have ‘A’ relationship are drawn with four lines connecting
them.
A C D F
Figure 1: Relationship Dia
A C D F
B
Figure 2: Relationship Dia(1)
3.3 Then I and O relations are drawn. The final nodal diagram would be:
A C D F
B E
Figure 3: Relationship Dia(2)
9
specific area of each department. For such situations ‘Pairwise Exchange Method’ is best
suited.
The method used in this project is ‘Pairwise Exchange Method’ it’s steps would be discussed
later in details.
10
2.2 Description of Design Problem
2.2.1 Project Description
A company manufactures bread baking machines. In order to manufacture machines it’s sub-
parts and assemblies are either outsources including motor, electric heater, base, wires, bolts
and nuts, bearings, piston, loaft removers and sockets; while other parts are manufactured
within industry which includes dough container, cylinder, holders and pushing plates. These
are parts and sub-assemblies are then assembled within facility to product final product which
is bread baking machine.
11
2.2.2 Bill of Material
Different parts and their decision to manufacture and purchase is in table:
Finished 400
Product
12
Warehouse
13
2.2.4 Route Sheet for parts
Cylinder
Dough Container
14
Holder
Pushing Plate
15
2.2.5 From-To-Chart
Table 10: From-To-Chart
Drillin Turning Cutting Welding Rolling Bending Millin Assembly Raw Finished
g g
Drilling - 3 1 1 1 1 1 1 1 1
Turning - 2 1 1 1 1 1 1 1
Cutting - 1 1 1 1 1 4 1
Welding - 1 1 1 3 1 1
Rolling - 1 1 1 1 1
Bending - 1 1 1 1
Milling - 1 1 1
assembly - 4 3
Raw - 1
Finished -
16
Chapter 03: Layout Design
3.1 Departments
Departments can be added by clicking Add button. All departments and required information
is entered initially.
17
3.2 Relationship between the departments
Based on the information in From/To Chart relationship among departments is established.
18
3.4 Relationship Diagram
19
Chapter 04: Layout Alternatives
4.1 Alternative 1
Now, we’ve to compute the transportation costs associated with this layout. This can be done
by first of construction From-To-Distance table. Which shows the linear distance between
center of one department to the center of another. From-To-Distance chart for Layout 1 is:
20
Table 11: Distance Chart for Layout 1
A B C D E F G H I J
A 0 10 0 0 17 0 0 53 66 0
B 0 9 22 0 0 59 0 0 0
C 0 11 9 22 0 0 59 0
D 0 12 23 0 44 0 0
E 0 0 0 0 0 0
F 0 0 0 0 0
G 0 12 0 0
H 0 14 20
I 0 0
J 0
By using MS Excel associated cost can be calculated by using ‘=productsum()’ formula of
MS Excel between From-To-Distance and From-To-Flow data.
21
4.2 Alternative 2
A B C D E F G H I J
A 0 58 0 0 40 0 0 10 48 0
B 0 30 0 0 0 31 0 0 0
C 0 7.5 13 30 0 0 28 0
D 0 14 30 0 36 0 0
E 0 0 0 0 0 0
F 0 0 0 0 0
G 0 40 0 0
H 0 58 24
I 0 0
J 0
Total cost for layout 2 is: 1015
22
4.3 Alternative 3
A B C D E F G H I J
A 0 30 0 0 55 0 0 14 45 0
B 0 16 0 0 0 14 0 0 0
C 0 8 16 42 0 0 14 0
D 0 15 50 0 36 0 0
E 0 0 0 0 0 0
F 0 0 0 0 0
G 0 14 0 0
H 0 31 53
I 0 0
J 0
Total cost for layout 3 is: 835
23
Chapter 05: Summary
From this project we’ve learned about layout plan for industrial facility. We’ve learned to
develop Layouts based on the adjacency score using AutoCAD and evaluation of each
alternative. We’ve also learned to compare each alternative by computing cost effectiveness
for each alternative. From this project we’ve learned to extract all required information
necessary for layout planning and based on this information are able to develop relationship
chart, diagram and determining flow from one department to another.
24
References
Dileep R. Sule, 3rd Ed, "Manufacturing facilities, Location, Planning and design."
Apple, J.M., and Deisenrothh, M.P., "A Computerized Plant Layout Analysis and Evaluation
Technique,"
Armour, G.C., and Buffa, E.S., "Aheuristic algorithm and simulation approach to relative
location of facilities," Management Science, 9(2), 215-219, 1963.
David Sly. "AutoCAD - based industrial layout planning and material flow analysis in
FactoryFLOW and PLAN.
25