Professional Documents
Culture Documents
PDF Combined Nov 2016
PDF Combined Nov 2016
PDF Combined Nov 2016
V l
Volume 25 ■ N
Number
b 2 www
www.craneworld.com
craneworlld com
NOVEMBER 2016 A KHL Group publication
Below
the
hook
Under pressure
Allowable ground bearing pressure is a tricky subject at the Anderson’s book Rigging Engineering Basics
and shows the allowable bearing capacity of
best of times but even more so when it is for a temporary road a number of different soils. The allowable
bearing capacity is derived from the ultimate
to carry a limited number of specialized transport loads over bearing capacity (at which the soil support
fails in shear) with a factor of safety of around
a relatively short time. MARCO VAN DAAL reports 2.5 applied.
There are two methods of ground
I
f there has ever been a controversial the soil for many decades with only a minimal pressure calculation that are well accepted
topic in the heavy transport industry, allowable settlement. It takes into account in our industry. Neither one is a scientific
it must be the determination of the worst case environmental loads such as wind, approach but both methods produce an
ground pressure underneath a transport snow, ice and sometimes earthquakes. This acceptable outcome that is workable in
combination. To arrive at a calculated assumption is invalid for temporary heavy practice and have been used for many years
allowable ground bearing pressure one haul roads, as the name already implies. Such by many companies large and small.
would have to get geophysicists involved to roads often experience a fair amount of traffic The first is the shadow area method.
carry out a full soil analysis followed by a with one (1) or a small number of extreme
recommendation for soil improvement. heavy loads over a period of a few weeks at Shadow area method
Although this is the recommended best to a few years in the worst case. Let’s assume that we have a 6-axle line
method when preparing soil for a permanent Temporary heavy haul roads are often transporter set up in a three point suspension
structure such as a hotel, office building or found on petrochemical plants, both during with four axles per each suspension group
heavy petrochemical and power generation construction and on turn around projects. and four tyres per axle (meaning eight tyres
components (to stay within our industry) it will Also, they are used at power plants, per axle line). The axle distance (DAS) is 1.5
become quickly apparent that this is difficult, temporary storage facilities, wind energy metres (4 ft 11 inches).
if not impossible, to apply this method to the farms and similar projects. Those who are or This combination is carrying a 100 ton
construction of a temporary heavy haul road. have been involved in such projects know that transformer. See Figure 1. The transformer
To start with, the soil analysis carried out these temporary roads are put in place and is placed on the transporter in such a way
for above-mentioned structures assumes that often do not last the duration of the project that each axle carries an equal load. The
these structures pose a permanent load on as the progress of the project claims the real transporter and power pack combined weigh
estate in question and the temporary roads 26 tons. This gives a gross vehicle weight
FIGURE 1 are diverted. This fact alone makes a lengthy (GVW) of 126 tons.
soil analysis an unlikely solution. Each axle line carries 21 tons (126 tons /
There are various types of soil that a road 6 axle lines), each axle carries 10.5 tons and
can be made of. Some are very suitable for each tyre (48 in total) carries 2.6 tons.
medium to heavy loads, some are unsuitable Figure 2 shows the plan view of the
for even light traffic. Table 1 is from Keith transporter in question. The shadow area is