NO. URAIAN PEKERJAAN SAT.

HARGA KETERANGAN
1 2 3 4 5

A HARGA SATUAN UPAH


1 Pekerja HR 27,500.00
2 Mandor HR 50,000.00
3 Kepala Tukang HR 47,500.00
4 Tukang Batu HR 42,500.00
5 Tukang Kayu HR 45,000.00
7 Tukang Cat HR 40,000.00
9 Tukang Besi HR 42,500.00

B HARGA SATUAN BAHAN


1 Tanah Urug M3 27,500.00
2 Pasir Urug M3 47,500.00
3 Pasir Pasang M3 52,500.00
4 Kerikil M3 110,000.00
5 Sirtu M3 35,000.00
7 Batu Kali Pecah M3 50,000.00
8 Batu Alam M3 70,000.00
9 Kerikil Pecah 2/3 M3 87,500.00
10 Kerikil Pecah 1cm M3 92,500.00
11 Batu Bata BJ 250.00
14 Keramik 30/30 M2 48,000.00
15 Keramik 20/20 M2 35,000.00
16 Keramik 20/25 M2 45,000.00
17 Semen Portland KG 750.00
18 Semen Warna KG 7,500.00
19 Kayu Kamper M3 2,400,000.00
20 Kayu Meranti M3 1,500,000.00
21 Papan Kamper M3 2,500,000.00
22 Papan Meranti M3 1,600,000.00
23 Papan Randu M3 1,000,000.00
24 Kayu Dolken BTG 2,500.00
25 Triplek 4 mm uk. 120 x 240 cm LBR 52,000.00
26 Triplek 9 mm uk. 120 x 240 cm LBR 74,000.00
27 Teakwood 4 mm LBR 77,000.00
28 Gypsum Board 9 mm M2 25,000.00
29 List Plafond M1 13,000.00
31 Minyak Cat LTR 5,000.00
32 Plamir Kayu KG 27,500.00
33 Plamir Tembok KG 8,000.00
35 Meni kayu KG 14,000.00
36 Meni Besi KG 11,000.00
37 Cat Kayu KG 27,500.00
39 Cat Tembok KG 10,000.00
40 Cat Zincromate KG 35,000.00
41 Plamir Tembok KG 8,000.00
42 Dempul Kayu KG 18,000.00
46 Teer Arang KG 2,500.00
47 Paku Usuk KG 7,500.00
48 Paku Triplek KG 7,500.00
49 Paku Seng KG 10,000.00
50 Kunci Tanam BH 300,000.00
51 Kunci Aluminium BH 500,000.00
52 Kaca Bening 5 mm M2 60,000.00
53 Kaca Es 3 mm M2 100,000.00
55 Engsel Pintu BH 64,000.00
56 Engsel Jendela BH 18,000.00
57 Grendel Jendela BH 15,000.00
58 Grendel Pintu BH 12,000.00
59 Hak Angin BH 24,000.00
60 Door Stop BH 24,000.00
63 Saklar Tunggal BH 84,000.00
64 Saklar Double BH 16,000.00
65 Kabel NYA 500V2x1,5 BH 18,000.00
66 Stop Kontak BH 2,000.00
72 Pipa PVC ø 3" M1 10,500.00
73 Pipa PVC ø 4" M1 25,000.00
74 Pipa PVC 6" M1 32,500.00
75 Pipa PVC ø 3/4" M1 62,000.00
76 Pipa PVC ø 5/8" M1 6,000.00
77 Kloset Jongkok BH 300,000.00
82 Tempat Sabun BH 75,000.00
83 Kran Bak Mandi BH 50,000.00
84 Kran Taman BH 150,000.00
86 Rol TBA BH 300,000.00
87 Avour BH 5,000.00
97 Kanal C NP KG 10,000.00
108 Besi Beton KG 5,500.00
110 Kawat Ikat Beton KG 7,500.00
138 Asbes Gelombang Kecil M2 32,000.00
ANALISA HARGA PEKERJAAN

VOL. SAT. URAIAN PEKERJAAN HARGA SATUAN JLH. HARGA


1 2 3 4 5

PEKERJAAN PERSIAPAN

1 M2 Pembersihan Lokasi dan Perataan


0.1000 hr Pekerja Rp 27,500.00 Rp 2,750.00
0.0500 hr Mandor Rp 50,000.00 Rp 2,500.00
Rp 5,250.00

1 M1 Pengukuran dan Pemasangan Bouwplank


0.0070 m3 Papan Randu Rp 1,000,000.00 Rp 7,000.00
0.0120 m3 Usuk Rp 1,500,000.00 Rp 18,000.00
0.0200 kg Paku Rp 5,500.00 Rp 110.00
0.0100 hr Kepala Tukang Rp 47,500.00 Rp 475.00
0.1000 hr Tukang Kayu Rp 45,000.00 Rp 4,500.00
0.1000 hr Pekerja Rp 27,500.00 Rp 2,750.00
0.0050 hr Mandor Rp 50,000.00 Rp 250.00
Rp 33,085.00

PEKERJAAN TANAH

1 M3 Galian Tanah Keras dalam 1,5 - 2


0.6250 hr Pekerja Rp 27,500.00 Rp 17,187.50
0.0620 hr Mandor Rp 50,000.00 Rp 3,100.00
Rp 20,287.50
1M3 Urugan Tanah Sirtu
1.2000 m3 Tanah Urug Rp 27,500.00 Rp 33,000.00
0.2500 hr Pekerja Rp 27,500.00 Rp 6,875.00
0.0250 hr Mandor Rp 50,000.00 Rp 1,250.00
Rp 41,125.00
1M3 Pengurugan Pasir Urug
1.2000 m3 Pasir Urug Rp 47,500.00 Rp 57,000.00
0.3000 hr Pekerja Rp 27,500.00 Rp 8,250.00
0.0100 hr Mandor Rp 50,000.00 Rp 500.00
Rp 65,750.00
1 M3 Urugan kembali Galian
0.1920 hr Pekerja Rp 27,500.00 Rp 5,280.00
0.0190 hr Mandor Rp 50,000.00 Rp 950.00
Rp 6,230.00

1 M3 Urugan Pasir Termasuk Pemadatan / Penyiraman


1.2000 m3 Pasir Urug Rp 47,500.00 Rp 57,000.00
0.3000 hr Pekerja Rp 27,500.00 Rp 8,250.00
0.0100 hr Mandor Rp 50,000.00 Rp 500.00
Rp 65,750.00

PEKERJAAN PONDASI

1 M3 Pasangan Batu Kosong (Anstampeng)


1.2000 m3 Batu Kali Rp 50,000.00 Rp 60,000.00
0.3000 m3 Pasir Urug Rp 47,500.00 Rp 14,250.00
0.3930 hr Tukang Batu Rp 42,500.00 Rp 16,702.50
0.0390 hr Kepala Tukang Rp 47,500.00 Rp 1,852.50
0.7800 hr Pekerja Rp 27,500.00 Rp 21,450.00
0.0390 hr Mandor Rp 50,000.00 Rp 1,950.00
Rp 116,205.00

1 M3 Pasangan Batu Kali 1Pc : 3Ps


1.1000 m3 Batu Kali Rp 50,000.00 Rp 55,000.00
202.0000 kg Semen Rp 750.00 Rp 151,500.00
0.1850 m3 Pasir Pasang Rp 52,500.00 Rp 9,712.50
0.6000 hr Tukang Batu Rp 42,500.00 Rp 25,500.00
0.0600 hr Kepala Tukang Rp 47,500.00 Rp 2,850.00
1.5000 hr Pekerja Rp 27,500.00 Rp 41,250.00
0.0750 hr Mandor Rp 50,000.00 Rp 3,750.00
Rp 289,562.50

PEKERJAAN DINDING

1 M2 Pasangan Bata Merah 1/2 bata Adukan 1Pc : 3Ps


70.0000 bj Bata Merah Rp 250.00 Rp 17,500.00
14.3700 kg Semen Rp 750.00 Rp 10,777.50
0.0400 m3 Pasir Pasang Rp 52,500.00 Rp 2,100.00
0.1000 hr Tukang Batu Rp 42,500.00 Rp 4,250.00
0.0100 hr Kepala Tukang Rp 47,500.00 Rp 475.00
0.3200 hr Pekerja Rp 27,500.00 Rp 8,800.00
0.0150 hr mandor Rp 50,000.00 Rp 750.00
Rp 44,652.50

1 M2 Pasangan Bata Merah 1/2 bata Adukan 1Pc : 5Ps


70.0000 biji Bata Merah Rp 250.00 Rp 17,500.00
9.6800 kg Semen Rp 750.00 Rp 7,260.00
0.0450 m3 Pasir Pasang Rp 52,500.00 Rp 2,362.50
0.1000 hr Tukang Batu Rp 42,500.00 Rp 4,250.00
0.0100 hr Kepala Tukang Rp 47,500.00 Rp 475.00
0.3200 hr Pekerja Rp 27,500.00 Rp 8,800.00
0.0150 hr mandor Rp 50,000.00 Rp 750.00
Rp 41,397.50

PEKERJAAN PLESTERAN
1M2 Plesteran dan Acian 1 : 3 tebal 15 mm
6.4800 kg Semen Rp 750.00 Rp 4,860.00
0.0190 m3 Pasir Pasang Rp 52,500.00 Rp 997.50
0.1500 hr Tukang Batu Rp 42,500.00 Rp 6,375.00
0.0150 hr Kepala Tukang Rp 47,500.00 Rp 712.50
0.2000 hr Pekerja Rp 27,500.00 Rp 5,500.00
0.0100 hr mandor Rp 50,000.00 Rp 500.00
Rp 18,945.00

1M2 Plesteran dan Acian 1 : 5 tebal 15 mm


3.6800 kg Semen Rp 750.00 Rp 2,760.00
0.0230 m3 Pasir Pasang Rp 52,500.00 Rp 1,207.50
0.1500 hr Tukang Batu Rp 42,500.00 Rp 6,375.00
0.0150 hr Kepala Tukang Rp 47,500.00 Rp 712.50
0.2000 hr Pekerja Rp 27,500.00 Rp 5,500.00
0.0100 hr mandor Rp 50,000.00 Rp 500.00
Rp 17,055.00

1M2 Plesteran dan Acian Beton 1 : 5 tebal 15 mm


7.0700 kg Semen Rp 750.00 Rp 5,302.50
0.0210 m3 Pasir Pasang Rp 52,500.00 Rp 1,102.50
0.2000 hr Tukang Batu Rp 42,500.00 Rp 8,500.00
0.0200 hr Kepala Tukang Rp 47,500.00 Rp 950.00
0.2600 hr Pekerja Rp 27,500.00 Rp 7,150.00
0.0130 hr mandor Rp 50,000.00 Rp 650.00
Rp 23,655.00
1M1 Benangan
0.0845 kg Semen Rp 750.00 Rp 63.36
0.0090 m3 Pasir Rp 52,500.00 Rp 472.50
0.1200 hr Tukang batu Rp 42,500.00 Rp 5,100.00
Rp 5,635.86

1M1 Kolplint
0.0845 kg Semen Rp 750.00 Rp 63.36
0.0090 m3 Pasir Rp 52,500.00 Rp 472.50
0.1200 hr Tukang batu Rp 42,500.00 Rp 5,100.00
Rp 5,635.86

PEKERJAAN BETON

1M3 Rabatan Beton 1 : 3 : 5


0.0440 m3 Kerikil Rp 92,500.00 Rp 4,070.00
10.0000 kg Semen Rp 750.00 Rp 7,500.00
0.0260 m3 Pasir Rp 52,500.00 Rp 1,365.00
0.0020 hr Kepala Tukang Rp 47,500.00 Rp 95.00
0.0200 hr Tukang batu Rp 42,500.00 Rp 850.00
1.1500 hr Pekerja Rp 27,500.00 Rp 31,625.00
0.0060 hr Mandor Rp 50,000.00 Rp 300.00
Rp 45,805.00
1 M3 Beton Berstruktur K-275
0.8200 m3 Kerikil Rp 92,500.00 Rp 75,850.00
400.0000 kg Semen Rp 750.00 Rp 300,000.00
0.4000 m3 Pasir Rp 52,500.00 Rp 21,000.00
1.0000 hr Tukang Batu Rp 42,500.00 Rp 42,500.00
0.1000 hr Kepala Tukang Rp 47,500.00 Rp 4,750.00
6.0000 hr Pekerja Rp 27,500.00 Rp 165,000.00
0.3000 hr Mandor Rp 50,000.00 Rp 15,000.00
Rp 624,100.00

1 KG Pekerjaan Pembesian pemakaian besi


1.0500 kg Besi Beton Rp 5,500.00 Rp 5,775.00
0.0150 kg Kawat Beton Rp 7,500.00 Rp 112.50
0.0070 hr Tukang Besi Rp 42,500.00 Rp 297.50
0.0070 hr Kepala Tukang Rp 47,500.00 Rp 332.50
0.0070 hr Pekerja Rp 27,500.00 Rp 192.50
0.0003 hr Mandor Rp 50,000.00 Rp 15.00
Rp 6,710.00
1 M3 Pekerjaan Bekisting Lantai
0.0400 m3 Kayu Terentang Rp 1,500,000.00 Rp 60,000.00
0.4000 kg Paku Rp 39,000.00 Rp 15,600.00
0.2000 ltr Minyak Bekisting Rp 17,360.00 Rp 3,472.00
0.0150 m3 Kayu Meranti Rp 1,600,000.00 Rp 24,000.00
0.3500 lbr Tripleks 9 Rp 74,000.00 Rp 25,900.00
6.0000 btg Dolken Rp 2,500.00 Rp 15,000.00
0.2600 hr Tukang Kayu Rp 45,000.00 Rp 11,700.00
0.0260 hr Kepala Tukang Rp 47,500.00 Rp 1,235.00
0.3000 hr Pekerja Rp 27,500.00 Rp 8,250.00
0.0050 hr Mandor Rp 50,000.00 Rp 250.00
Rp 165,407.00

1 M3 Pekerjaan Bekisting Sloof


0.0450 m3 Kayu Terentang Rp 1,500,000.00 Rp 67,500.00
0.3000 kg Paku Rp 5,500.00 Rp 1,650.00
0.1000 ltr Minyak Bekisting Rp 17,360.00 Rp 1,736.00
0.2600 hr Tukang Kayu Rp 45,000.00 Rp 11,700.00
0.0260 hr Kepala Tukang Rp 47,500.00 Rp 1,235.00
0.3000 hr Pekerja Rp 27,500.00 Rp 8,250.00
0.0050 hr Mandor Rp 50,000.00 Rp 250.00
Rp 92,321.00

1 M3 Pekerjaan Bekisting Kolom


0.0400 m3 Kayu Terentang Rp 1,500,000.00 Rp 60,000.00
0.4000 kg Paku Rp 5,500.00 Rp 2,200.00
0.2000 ltr Minyak Bekisting Rp 17,360.00 Rp 3,472.00
0.0150 m3 Kayu Meranti Rp 1,600,000.00 Rp 24,000.00
0.3500 lbr Tripleks 9 mm Rp 74,000.00 Rp 25,900.00
2.0000 btg Dolken Rp 2,500.00 Rp 5,000.00
0.3300 hr Tukang Kayu Rp 45,000.00 Rp 14,850.00
0.0330 hr Kepala Tukang Rp 47,500.00 Rp 1,567.50
0.3000 hr Pekerja Rp 27,500.00 Rp 8,250.00
0.0060 hr Mandor Rp 50,000.00 Rp 300.00
Rp 145,539.50

1 M3 Pekerjaan Bekisting Balok


0.0400 m3 Kayu Terentang Rp 1,500,000.00 Rp 60,000.00
0.4000 kg Paku Rp 5,500.00 Rp 2,200.00
0.2000 ltr Minyak Bekisting Rp 17,360.00 Rp 3,472.00
0.0180 m3 Kayu Meranti Rp 1,600,000.00 Rp 28,800.00
0.3500 lbr Tripleks 9 mm Rp 74,000.00 Rp 25,900.00
2.0000 btg Dolken Rp 2,500.00 Rp 5,000.00
0.3300 hr Tukang Kayu Rp 45,000.00 Rp 14,850.00
0.0330 hr Kepala Tukang Rp 47,500.00 Rp 1,567.50
0.3200 hr Pekerja Rp 27,500.00 Rp 8,800.00
0.0006 hr Mandor Rp 50,000.00 Rp 30.00
Rp 150,619.50

Pembongkaran Cetakan dan Penyiraman Beton


4.0000 m3 Pekerja Rp 27,500.00 Rp 110,000.00
Rp 110,000.00
1M3 Sloof Beton Bertulang 1PC : 2PS :3KR (K275) dengan Pemakaian Besi 240kg
1.0000 m3 Pekerjaan Beton Berstruktur K 225 Rp 624,100.00 Rp 624,100.00
240.0000 Kg Pekerjaan pembesian Rp 6,710.00 Rp 1,610,400.00
1.0000 m3 Acuan untuk Beton Struktur(Bekisting) Rp 92,321.00 Rp 92,321.00
1.0000 m3 Pembongkaran Cetakan dan Penyiraman Rp 110,000.00 Rp 110,000.00
Rp 2,436,821.00

1M3 Kolom Beton Bertulang 1PC : 2PS :3KR (K275) dengan Pemakaian Besi 240kg
1.0000 m3 Pekerjaan Beton Berstruktur K 225 Rp 624,100.00 Rp 624,100.00
240.0000 Kg Pekerjaan pembesian Rp 6,710.00 Rp 1,610,400.00
1.0000 m3 Acuan untuk Beton Struktur(Bekisting) Rp 145,539.50 Rp 145,539.50
1.0000 m3 Pembongkaran Cetakan dan Penyiraman Rp 110,000.00 Rp 110,000.00
Rp 2,490,039.50

1M3 Ring Balk Beton/Beton Praktis Bertulang 1PC : 2PS :3KR (K275) dengan Pemakaian Besi 150kg
1.0000 m3 Pekerjaan Beton Berstruktur K 225 Rp 624,100.00 Rp 624,100.00
150.0000 Kg Pekerjaan pembesian Rp 6,710.00 Rp 1,006,500.00
1.0000 m3 Acuan untuk Beton Struktur(Bekisting) Rp 3,472.00 Rp 3,472.00
1.0000 m3 Pembongkaran Cetakan dan Penyiraman Rp 14,850.00 Rp 14,850.00
Rp 1,648,922.00

1M3 Balok Beton Bertulang 1PC : 2PS :3KR (K275) dengan Pemakaian Besi 240kg
1.0000 m3 Pekerjaan Beton Berstruktur K 225 Rp 624,100.00 Rp 624,100.00
240.0000 Kg Pekerjaan pembesian Rp 6,710.00 Rp 1,610,400.00
1.0000 m3 Acuan untuk Beton Struktur(Bekisting) Rp 150,619.50 Rp 150,619.50
1.0000 m3 Pembongkaran Cetakan dan Penyiraman Rp 110,000.00 Rp 110,000.00
Rp 2,495,119.50

1M3 Lantai Beton Bertulang 1PC : 2PS :3KR (K275) dengan Pemakaian Besi 240kg
1.0000 m3 Pekerjaan Beton Berstruktur K 225 Rp 624,100.00 Rp 624,100.00
240.0000 Kg Pekerjaan pembesian Rp 6,710.00 Rp 1,610,400.00
1.0000 m3 Acuan untuk Beton Struktur(Bekisting) Rp 165,407.00 Rp 165,407.00
1.0000 m3 Pembongkaran Cetakan dan Penyiraman Rp 110,000.00 Rp 110,000.00
Rp 2,509,907.00

PEKERJAAN KAYU

1 M3 Kusen Pintu & Jendela kayu kamper


1.2000 m3 Kayu Kamper Rp 2,400,000.00 Rp 2,880,000.00
1.0500 hr Tukang Kayu Rp 45,000.00 Rp 47,250.00
0.1050 hr Kepala Tukang Rp 47,500.00 Rp 4,987.50
0.3500 hr Pekerja Rp 27,500.00 Rp 9,625.00
0.0180 hr mandor Rp 50,000.00 Rp 900.00
Rp 2,942,762.50
1 M2 Daun Pintu Panil kayu kamper
0.0400 m3 Kayu Kamper Rp 2,400,000.00 Rp 96,000.00
2.5000 hr Tukang Kayu Rp 45,000.00 Rp 112,500.00
0.2500 hr Kepala Tukang Rp 47,500.00 Rp 11,875.00
1.0000 hr Pekerja Rp 27,500.00 Rp 27,500.00
0.0500 hr mandor Rp 50,000.00 Rp 2,500.00
Rp 250,375.00
1 M2 Daun Jendela kayu kamper
0.0350 m3 Kayu Kamper Rp 2,400,000.00 Rp 84,000.00
2.0000 hr Tukang Kayu Rp 45,000.00 Rp 90,000.00
0.2000 hr Kepala Tukang Rp 47,500.00 Rp 9,500.00
0.8000 hr Pekerja Rp 27,500.00 Rp 22,000.00
0.0400 hr mandor Rp 50,000.00 Rp 2,000.00
Rp 207,500.00

1 M2 Pasangan Rangka Plafond 30X60


0.0120 m3 Kayu Meranti Rp 2,400,000.00 Rp 28,800.00
0.1000 kg Paku Rp 5,500.00 Rp 550.00
0.2500 hr Tukang Kayu Rp 45,000.00 Rp 11,250.00
0.0250 hr Kepala Tukang Rp 47,500.00 Rp 1,187.50
0.1500 hr Pekerja Rp 27,500.00 Rp 4,125.00
0.0750 hr Mandor Rp 50,000.00 Rp 3,750.00
Rp 49,662.50

1 M2 Pasangan Plafond Gypsum Board 9 mm


0.3640 lbr Gypsum Rp 25,000.00 Rp 9,100.00
0.1100 kg Paku Rp 5,500.00 Rp 605.00
0.0500 hr Tukang Kayu Rp 45,000.00 Rp 2,250.00
0.0050 hr Kepala Tukang Rp 47,500.00 Rp 237.50
0.1000 hr Pekerja Rp 27,500.00 Rp 2,750.00
0.0050 hr Mandor Rp 50,000.00 Rp 250.00
Rp 15,192.50

1 M1 List Plafond
1.1000 m1 List Gypsum Rp 13,000.00 Rp 14,300.00
0.0100 kg Paku Rp 5,500.00 Rp 55.00
0.0500 hr Tukang Kayu Rp 45,000.00 Rp 2,250.00
0.0050 hr Kepala Tukang Rp 47,500.00 Rp 237.50
0.0500 hr Pekerja Rp 27,500.00 Rp 1,375.00
0.0030 hr Mandor Rp 50,000.00 Rp 150.00
Rp 18,367.50

PEKERJAAN PENGUNCI

1 Bh Pasang Slot Pintu


1.0000 bh Slot Rp 24,000.00 Rp 24,000.00
0.1500 hr Tukang Kayu Rp 42,500.00 Rp 6,375.00
0.0150 hr Kepala Tukang Rp 47,500.00 Rp 712.50
0.0150 hr Pekerja Rp 27,500.00 Rp 412.50
0.0008 hr mandor Rp 50,000.00 Rp 37.50
Rp 31,537.50

1 Bh Pasang Slot Jendela/Boven


1.0000 bh Slot Rp 12,000.00 Rp 12,000.00
0.1500 hr Tukang Kayu Rp 42,500.00 Rp 6,375.00
0.0150 hr Kepala Tukang Rp 47,500.00 Rp 712.50
0.0150 hr Pekerja Rp 27,500.00 Rp 412.50
0.0008 hr mandor Rp 50,000.00 Rp 37.50
Rp 19,537.50

1 Bh Pasang Engsel Jendela/Boven


1.0000 bh Engsel Rp 15,000.00 Rp 15,000.00
0.1000 hr Tukang Kayu Rp 42,500.00 Rp 4,250.00
0.0100 hr Kepala Tukang Rp 47,500.00 Rp 475.00
0.0100 hr Pekerja Rp 27,500.00 Rp 275.00
0.0005 hr mandor Rp 50,000.00 Rp 25.00
Rp 20,025.00
1 Bh Pasang Engsel Pintu
1.0000 bh Engsel Rp 18,000.00 Rp 18,000.00
0.1500 hr Tukang Kayu Rp 42,500.00 Rp 6,375.00
0.0150 hr Kepala Tukang Rp 47,500.00 Rp 712.50
0.0150 hr Pekerja Rp 27,500.00 Rp 412.50
0.0008 hr mandor Rp 50,000.00 Rp 37.50
Rp 25,537.50

1 Bh Pasang Hak Angin Sikutan


1.0000 bh Hak Sikutan Rp 24,000.00 Rp 24,000.00
0.1500 hr Tukang Kayu Rp 42,500.00 Rp 6,375.00
0.0150 hr Kepala Tukang Rp 47,500.00 Rp 712.50
0.0150 hr Pekerja Rp 27,500.00 Rp 412.50
0.0008 hr mandor Rp 50,000.00 Rp 37.50
Rp 31,537.50

1 Unit Pasang Kunci Tanam Pintu Teakwood


1.0000 set Kunci Pintu Rp 300,000.00 Rp 300,000.00
0.5000 hr Tukang Kayu Rp 42,500.00 Rp 21,250.00
0.0100 hr Kepala Tukang Rp 47,500.00 Rp 475.00
0.0100 hr Pekerja Rp 27,500.00 Rp 275.00
0.0050 hr mandor Rp 50,000.00 Rp 250.00
Rp 322,250.00

1 M2 Pasang Kaca Bening 5mm


1.1000 m3 Kaca Bening Rp 60,000.00 Rp 66,000.00
0.1500 hr Tukang Kayu Rp 42,500.00 Rp 6,375.00
0.0150 hr Kepala Tukang Rp 47,500.00 Rp 712.50
0.0150 hr Pekerja Rp 27,500.00 Rp 412.50
0.0008 hr mandor Rp 50,000.00 Rp 37.50
Rp 73,537.50

PEKERJAAN ATAP

1 Kg Pasang Kuda-kuda Kanal C


1.1000 kg Canal Rp 10,000.00 Rp 11,000.00
0.0800 ltr Meni Besi Rp 11,000.00 Rp 880.00
0.0200 kg Tukang Besi Rp 42,500.00 Rp 850.00
0.0060 hr Kepala Tukang Rp 47,500.00 Rp 285.00
0.0060 hr Pekerja Rp 27,500.00 Rp 165.00
0.0600 hr Mandor Rp 50,000.00 Rp 3,000.00
Rp 16,180.00

1m3 Pasang Gording Kayu Kamper


1.1000 m3 Kayu Kamper Rp 2,400,000.00 Rp 2,640,000.00
0.8000 kg Paku Rp 7,500.00 Rp 6,000.00
12.0000 hr Tukang Kayu Rp 42,500.00 Rp 510,000.00
1.2000 hr Kepala Tukang Rp 47,500.00 Rp 57,000.00
4.0000 hr Pekerja Rp 27,500.00 Rp 110,000.00
0.2000 hr Mandor Rp 50,000.00 Rp 10,000.00
Rp 3,323,000.00

1 M2 Pasang Atap Asbes Gelombang Kecil


1.0500 m2 Asbes Gelombang Kecil Rp 57,000.00 Rp 59,850.00
0.0200 bh Sekerup Rp 400.00 Rp 8.00
0.0750 hr Tukang Kayu Rp 50,000.00 Rp 3,750.00
0.0080 hr Kepala Tukang Rp 60,000.00 Rp 480.00
0.1500 hr Pekerja Rp 40,000.00 Rp 6,000.00
0.0060 hr Mandor Rp 100,000.00 Rp 600.00
Rp 70,688.00

PEKERJAAN PENGECATAN

1 M2 Mengecat Dengan 1 kali Cat Dasar dan 2 kali Cat Tembok


0.1000 kg Cat Dasar Rp 15,000.00 Rp 1,500.00
0.2600 kg Cat Tembok Rp 15,000.00 Rp 3,900.00
0.1000 kg Plamir Rp 8,000.00 Rp 800.00
0.0630 hr Tukang Cat Rp 40,000.00 Rp 2,520.00
0.0063 hr Kepala Tukang Rp 47,500.00 Rp 299.25
0.0200 hr Pekerja Rp 40,000.00 Rp 800.00
0.0025 hr Mandor Rp 50,000.00 Rp 125.00
Rp 9,944.25

1 M2 Mengecat Kayu 1 Kali Cat Dasar dan 3 Kali Cat Halus


0.2000 kg Cat Meni Rp 22,500.00 Rp 4,500.00
0.3500 kg Cat Kayu Rp 39,000.00 Rp 13,650.00
0.1700 ltr Cat Dasar Rp 39,000.00 Rp 6,630.00
0.1500 kg Plamir Cat Rp 27,500.00 Rp 4,125.00
0.1050 hr Tukang Cat Rp 40,000.00 Rp 4,200.00
0.0040 hr Kepala Tukang Rp 47,500.00 Rp 190.00
0.0700 hr Pekerja Rp 40,000.00 Rp 2,800.00
0.0025 hr Mandor Rp 50,000.00 Rp 125.00
Rp 36,220.00

1 M2 Mengecat Plafond
0.1000 kg Cat Dasar Rp 15,000.00 Rp 1,500.00
0.2600 kg Cat Tembok Rp 15,000.00 Rp 3,900.00
0.1000 kg plamir Rp 8,000.00 Rp 800.00
0.0630 hr tukang cat Rp 40,000.00 Rp 2,520.00
0.0063 hr kepala tukang Rp 47,500.00 Rp 299.25
0.0200 hr Pekerja Rp 40,000.00 Rp 800.00
0.0025 hr mandor Rp 50,000.00 Rp 125.00
Rp 9,944.25

PEKERJAAN SANITASI

1 unit Daun Pintu Kusen dan Daun Pintu PVC


1.0000 m3 Kusen dan Daun Pintu PVC Rp 385,000.00 Rp 385,000.00
2.5000 hr Tukang Batu Rp 42,500.00 Rp 106,250.00
0.2500 hr Kepala Tukang Rp 47,500.00 Rp 11,875.00
0.8800 hr Pekerja Rp 27,500.00 Rp 24,200.00
0.0440 hr mandor Rp 50,000.00 Rp 2,200.00
Rp 529,525.00

1 Unit Pemasanga Floor Drain


1.0000 bh Floor drain Rp 100,000.00 Rp 100,000.00
0.0100 Kepala Tukang Rp 47,500.00 Rp 475.00
0.1000 Tukang Batu Rp 42,500.00 Rp 4,250.00
0.0100 Pekerja Rp 27,500.00 Rp 275.00
0.0050 hr Mandor Rp 50,000.00 Rp 250.00
Rp 105,250.00

1 Unit Pembuatan Bak Kontrol Bata (45X45) cm


40.0000 bh Bata Rp 250.00 Rp 10,000.00
77.0000 kg Semen Rp 750.00 Rp 57,750.00
0.1300 m3 Pasir Rp 52,500.00 Rp 6,825.00
0.0200 kg Kerikil Rp 110,000.00 Rp 2,200.00
2.6000 m3 Besi Beton Rp 9,000.00 Rp 23,400.00
0.0900 kg Pasir Beton Rp 52,500.00 Rp 4,725.00
0.0470 hr Kepala Tukang Rp 47,500.00 Rp 2,232.50
0.4730 hr Tukang Batu Rp 42,500.00 Rp 20,102.50
1.4200 hr Pekerja Rp 27,500.00 Rp 39,050.00
0.0710 hr Mandor Rp 50,000.00 Rp 3,550.00
Rp 169,835.00

1 Unit Pembuatan Bak Mandi


194.4000 bh Bata Rp 250.00 Rp 48,600.00
120.0000 kg Semen Rp 750.00 Rp 90,000.00
0.3000 m3 Pasir Rp 52,500.00 Rp 15,750.00
6.0000 kg Semen nat Rp 7,500.00 Rp 45,000.00
0.3000 hr Kepala Tukang Rp 47,500.00 Rp 14,250.00
3.0000 hr Tukang Batu Rp 42,500.00 Rp 127,500.00
6.0000 hr Pekerja Rp 27,500.00 Rp 165,000.00
0.3000 hr Mandor Rp 50,000.00 Rp 15,000.00
Rp 521,100.00

1 Unit Pemasangan Kloset Jongkok


1.0000 unit Kloset Rp 300,000.00 Rp 300,000.00
6.0000 kg Semen Rp 750.00 Rp 4,500.00
0.0100 m3 Pasir Rp 52,500.00 Rp 525.00
0.1500 hr Kepala Tukang Rp 47,500.00 Rp 7,125.00
0.5000 hr Tukang Batu Rp 42,500.00 Rp 21,250.00
0.2500 hr Pekerja Rp 27,500.00 Rp 6,875.00
0.1600 hr Mandor Rp 50,000.00 Rp 8,000.00
Rp 348,275.00

1 Unit Pemasangan Tempat Sabun


1.0000 unit Tempat Sabun Rp 75,000.00 Rp 75,000.00
6.0000 kg Semen Rp 750.00 Rp 4,500.00
0.0100 m3 Pasir Pasang Rp 52,500.00 Rp 525.00
0.1000 hr Kepala Tukang Rp 47,500.00 Rp 4,750.00
0.0050 hr Mandor Rp 50,000.00 Rp 250.00
0.0100 hr Pekerja Rp 27,500.00 Rp 275.00
0.1000 hr Tukang Batu Rp 42,500.00 Rp 4,250.00
Rp 89,550.00

1 Unit Kran air


1.0000 unit Kran Rp 150,000.00 Rp 150,000.00
0.0250 Rol Rol TBA Rp 5,000.00 Rp 125.00
0.0100 hr Kepala Tukang Rp 47,500.00 Rp 475.00
0.1000 hr Tukang Batu Rp 42,500.00 Rp 4,250.00
0.0100 hr Pekerja Rp 27,500.00 Rp 275.00
0.0050 hr Mandor Rp 50,000.00 Rp 250.00
Rp 155,375.00

1 Unit Kran Taman


1.0000 unit Kran Rp 200,000.00 Rp 200,000.00
0.0250 Rol Rol TBA Rp 5,000.00 Rp 125.00
0.0100 hr Kepala Tukang Rp 47,500.00 Rp 475.00
0.1000 hr Tukang Batu Rp 42,500.00 Rp 4,250.00
0.0100 hr Pekerja Rp 27,500.00 Rp 275.00
0.0050 hr Mandor Rp 50,000.00 Rp 250.00
Rp 205,375.00

1 Unit Resapan
2700.0000 ltr Bata Rp 250.00 Rp 675,000.00
2.7500 lbr Semen Rp 750.00 Rp 2,062.50
0.5000 kg Pasir Rp 52,500.00 Rp 26,250.00
0.1000 m3 Kerikil Rp 110,000.00 Rp 11,000.00
15.0000 kg Besi Beton Rp 9,000.00 Rp 135,000.00
0.0250 m3 Papan Rp 1,000,000.00 Rp 25,000.00
0.1200 m3 Plat Beton Rp 2,495,119.50 Rp 299,414.34
0.150 hr Kepala Tukang Rp 47,500.00 Rp 7,612.50
1.500 hr Tukang Batu Rp 42,500.00 Rp 75,750.00
1.000 hr Pekerja Rp 27,500.00 Rp 30,000.00
0.160 hr Mandor Rp 50,000.00 Rp 8,800.00
Rp 1,295,889.34

1 Unit Septictank
3200.0000 ltr Bata Rp 250.00 Rp 800,000.00
20.0000 lbr Semen Rp 750.00 Rp 15,000.00
2.4000 kg Pasir Rp 52,500.00 Rp 126,000.00
0.0900 m3 Kerikil Rp 110,000.00 Rp 9,900.00
30.0000 kg Besi Beton Rp 9,000.00 Rp 270,000.00
0.0300 m3 Papan Rp 1,000,000.00 Rp 30,000.00
0.6100 m3 Plat Beton Rp 2,495,119.50 Rp 1,522,022.90
1.0000 m1 Pipa PVC Rp 25,000.00 Rp 25,000.00
0.150 hr Kepala Tukang Rp 47,500.00 Rp 7,612.50
1.500 hr Tukang Batu Rp 42,500.00 Rp 63,750.00
1.000 hr Pekerja Rp 27,500.00 Rp 27,500.00
0.160 hr Mandor Rp 50,000.00 Rp 8,000.00
Rp 2,904,785.40

1 M1 Pemasangan Instalasi Pipa PVC AW d. 3/4 "


1.2000 m1 Pipa Rp 6,000.00 Rp 7,200.00
0.3500 Perlengkapan Rp 7,200.00 Rp 2,520.00
0.0060 hr Kepala Tukang Rp 47,500.00 Rp 285.00
0.0600 hr Tukang Batu Rp 42,500.00 Rp 2,550.00
0.0360 hr Pekerja Rp 27,500.00 Rp 990.00
0.0050 hr Mandor Rp 50,000.00 Rp 250.00
Rp 13,795.00

1 M1 Pemasangan Instalasi Pipa PVC AW d. 3" Kotor


1.2000 m1 Pipa PC 3' Rp 25,000.00 Rp 30,000.00
0.3500 Perlengkapan Rp 30,000.00 Rp 10,500.00
0.0135 hr Kepala Tukang Rp 47,500.00 Rp 641.25
0.1350 hr Tukang Batu Rp 42,500.00 Rp 5,737.50
0.0810 hr Pekerja Rp 27,500.00 Rp 2,227.50
0.0041 hr Mandor Rp 50,000.00 Rp 205.00
Rp 49,311.25

1 M1 Pemasangan Instalasi Pipa PVC AW d. 4 ''


1.2000 m1 Pipa PC 4' Rp 32,500.00 Rp 39,000.00
0.3500 Perlengkapan Rp 39,000.00 Rp 13,650.00
0.0135 hr Kepala Tukang Rp 47,500.00 Rp 641.25
0.1350 hr Tukang Batu Rp 42,500.00 Rp 5,737.50
0.0810 hr Pekerja Rp 27,500.00 Rp 2,227.50
0.0041 hr Mandor Rp 50,000.00 Rp 205.00
Rp 61,461.25

1 M1 Pemasangan Instalasi Pipa PVC AW d. 6''


1.2000 m1 Pipa PC 6' Rp 62,000.00 Rp 74,400.00
0.3500 Perlengkapan Rp 74,400.00 Rp 26,040.00
0.0135 hr Kepala Tukang Rp 47,500.00 Rp 641.25
0.1350 hr Tukang Batu Rp 42,500.00 Rp 5,737.50
0.0810 hr Pekerja Rp 27,500.00 Rp 2,227.50
0.0041 hr Maandor Rp 50,000.00 Rp 205.00
Rp 109,251.25

PEKERJAAN PENUTUP LANTAI DAN DINDING

1 m2 Pasang Keramik Lantai 30/30


1.000 m2 Keramik Rp 50,000.00 Rp 50,000.00
11.380 kg Semen Rp 750.00 Rp 8,535.00
1.500 kg semen Warna Rp 7,500.00 Rp 11,250.00
0.042 m3 Pasir Rp 52,500.00 Rp 2,205.00
0.050 hr Kepala Tukang Rp 47,500.00 Rp 2,375.00
0.500 hr Tukang Batu Rp 42,500.00 Rp 21,250.00
1.000 hr Pekerja Rp 27,500.00 Rp 27,500.00
0.050 hr mandor Rp 50,000.00 Rp 2,500.00
Rp 125,615.00

1 m2 Pasang Keramik Lantai 20/20


1.000 m2 Keramik Rp 45,000.00 Rp 45,000.00
11.380 kg Semen Rp 750.00 Rp 8,535.00
1.500 kg semen Warna Rp 7,500.00 Rp 11,250.00
0.042 m3 Pasir Rp 52,500.00 Rp 2,205.00
0.035 hr Kepala Tukang Rp 47,500.00 Rp 1,662.50
0.350 hr Tukang Batu Rp 42,500.00 Rp 14,875.00
0.620 hr Pekerja Rp 27,500.00 Rp 17,050.00
0.030 hr mandor Rp 50,000.00 Rp 1,500.00
Rp 102,077.50

1 m2 Pasang Keramik dinding 20/25


1.000 m2 Keramik Rp 47,500.00 Rp 47,500.00
9.340 kg Semen Rp 750.00 Rp 7,005.00
1.500 kg semen Warna Rp 7,500.00 Rp 11,250.00
0.018 m3 Pasir Rp 52,500.00 Rp 945.00
0.045 hr Kepala Tukang Rp 47,500.00 Rp 2,137.50
0.100 hr Tukang Batu Rp 42,500.00 Rp 4,250.00
0.600 hr Pekerja Rp 27,500.00 Rp 16,500.00
0.030 hr mandor Rp 50,000.00 Rp 1,500.00
Rp 91,087.50

PEKERJAAN LISTRIK

1 unit Pemasangan Titik Lampu


1.000 ljr Pipa PVC 5/8 Rp 3,000.00 Rp 3,000.00
1.000 bh Fiting Rp 10,000.00 Rp 10,000.00
15.000 rol Isolator Rp 750.00 Rp 11,250.00
30.000 m1 Kabel NYA V 2x1,5 Mm2 Rp 2,000.00 Rp 60,000.00
6.000 bh las doof Rp 250.00 Rp 1,500.00
2.000 bh T Doofs PVC Rp 1,875.00 Rp 3,750.00
0.050 hr Kepala Tukang Rp 47,500.00 Rp 2,375.00
1.000 hr Tukang Listrik Rp 42,500.00 Rp 42,500.00
1.000 hr Pekerja Rp 27,500.00 Rp 27,500.00
Rp 161,875.00

1 unit Pemasangan Stop Kontak


0.020 ljr Pipa PVC 5/8 Rp 3,000.00 Rp 60.00
15.000 m1 Kabel NYA V 2x1,5 Mm2 Rp 2,000.00 Rp 30,000.00
1.000 bh Stop Kontak Rp 21,000.00 Rp 21,000.00
1.000 bh T Doofs PVC Rp 100,000.00 Rp 100,000.00
0.050 hr Kepala Tukang Rp 47,500.00 Rp 2,375.00
0.500 hr Tukang Listrik Rp 42,500.00 Rp 21,250.00
0.050 hr Pekerja Rp 27,500.00 Rp 1,375.00
Rp 176,060.00
REKAPITULASI KUANTITAS DAN HARGA

Proyek : Juanda Business Centre


Pekerjaan : Taman
Lokasi : Jalan Juanda
Surabaya

NO URAIAN PEKERJAAN JUMLAH HARGA

I Pekerjaan Persiapan Rp 500,000.00


II Pekerjaan Penanaman Pohon Peneduh Rp 25,564,000.00
III Pekerjaan Penanaman Semak dan Perdu Rp 10,668,000.00
IV Pekerjaan Penanaman Rumput Rp 11,730,000.00

Jumlah Total Rp 48,462,000.00


Jumlah Dibulatkan Rp 48,462,000.00

TERBILANG ; ENAM PULUH SEMBILAN JUTA TUJUH RATUS RIBU RUPIAH

Surabaya, 9 Januari 2006

( Ir. ANDY SANTOSO )


DAFTAR KUANTITAS DAN HARGA

Proyek : Renovasi Masjid Al-Muhajirin


pekerjaan : Taman dan Teras
Lokasi : Rewwin
Sidoarjo

NO URAIAN PEKERJAAN SAT VOL HARGA SATUAN JUMLAH HARGA

I Pekerjaan Persiapan
1 Pembersihan Lokasi Ls 1.00 Rp 200,000.00 Rp 200,000.00
2 Uiset & Bouwplank Ls 1.00 Rp 300,000.00 Rp 300,000.00
Rp 500,000.00

II Pek. Lantai Teras


1 Rolag Bata M3 4.26 Rp 450,000.00 Rp 1,917,000.00
2 Plesteran M2 109.20 Rp 20,000.00 Rp 2,184,000.00
3 Pasang Keramik M2 124.30 Rp 110,000.00 Rp 13,673,000.00
4 Pasang Bak Kontrol Unit 21.00 Rp 150,000.00 Rp 3,150,000.00
5 Saluran Air Hujan PVC 4" Ml 82.00 Rp 20,000.00 Rp 1,640,000.00
6 Saluran Tertutup Ml 12.00 Rp 250,000.00 Rp 3,000,000.00
Rp 25,564,000.00

III Pekerjaan Paving


1 Bongkar Paving yang ada M2 420.00 Rp 4,000.00 Rp 1,680,000.00
2 Galian Tanah M2 32.40 Rp 20,000.00 Rp 648,000.00
3 Urug Sirtu dan Pemadatan M3 51.75 Rp 80,000.00 Rp 4,140,000.00
4 Pasang Pavig Stone M2 420.00 Rp 10,000.00 Rp 4,200,000.00
Rp 10,668,000.00

IV Pekerjaan Taman
1 Renovasi Pagar yang ada Ml 111.00 Rp 50,000.00 Rp 5,550,000.00
2 Pembuatan Taman M2 206.00 Rp 30,000.00 Rp 6,180,000.00
Rp 11,730,000.00

Jumlah Total Rp 48,462,000.00


Jumlah dibulatkan Rp 48,462,000.00

Terbilang : Empat Puluh Delapan Juta Empat Ratus Enam Puluh Dua Ribu Rupiah

Mengetahui ketua takmir Al-Muhajirin Sidoarjo 17 Maret 2007

(Ir. H. Husni Tamrin) (Ir . Eko Harianto)