ID Task Name Duration Start Finish Predecessors July 2022 August 2022 September 2022

10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20
0 Site ID 305050-Cha Cha- 60m Tower 36 days Fri 6/17/22 Fri 8/5/22
1 1 Surveying and Setting out 1 day Fri 6/17/22 Fri 6/17/22
2 1.1 Kickoff & Overall site setting out 0.5 days Fri 6/17/22 Fri 6/17/22 Carpentary,Labour[200%],Leveling machine[1]
3 2 Tower Raft Foundation 8 days Fri 6/17/22 Tue 6/28/22 1
4 2.1 Excavation work for Raft Foundation 3 days Sat 6/18/22 Fri 6/24/22 Labour For Excavation[2,000%]
5 2.2 Leveling and Compaction 0.5 days Fri 6/24/22 Fri 6/24/22 4 Labour[600%]
6 2.3 QC and Lean Concrete C-10 1 day Sat 6/25/22 Sat 6/25/22 5 Labour[1,000%],Mason[200%],Mixer[1],Vibrator[1],sand[3],aggrigate[4],Cement[10]
7 2.4 Formwork for Pad. 0.5 days Sun 6/26/22 Sun 6/26/22 6 Carpentary[150%],Labour[350%],Formwork[8],Nail[14]
8 2.5 Fabrication and Fixing Reinforcement work. 2 days Mon 6/27/22 Tue 6/28/22 7 Steel Fixer[200%],Labour[200%]
9 2.6 Fixing Anchor bolt & QC 1 day Tue 6/28/22 Tue 6/28/22 8 Carpentary[250%],Labour[200%]
10 2.7 Formwork for column & QC 2 days Wed 6/29/22 Thu 6/30/22 9 Carpentary[200%],Labour[200%]
11 2.8 Casting concrete C-25 1 day Thu 6/30/22 Thu 6/30/22 10 Mason[300%],Labour[1,500%],Mixer[1],Vibrator[1],Cement[126],aggrigate[15],sand[13]
12 3 Concrete Test 0.5 days Wed 7/6/22 Wed 7/6/22 11FS+7 days
13 3.1 Hammer Test and Closing QC 1 day Wed 7/6/22 Wed 7/6/22
14 4 Backfilling and Compaction 2 days Fri 7/8/22 Mon 7/11/22 3,12
15 4.1 Backfilling and Compaction 2 days Fri 7/8/22 Mon 7/11/22 Labour[650%],Comapctor[1]
16 5 Tower Erection 3 days Tue 7/12/22 Thu 7/14/22 14
17 5.1 Assembling and Erection. 2 days Tue 7/12/22 Wed 7/13/22 Rigger[300%],Labour[450%]
18 5.2 Telecom accessories. 1 day Thu 7/14/22 Thu 7/14/22 17 Rigger[400%],Labour[200%]
19 6 Supplamantary Telecom work 4 days Fri 6/24/22 Wed 6/29/22
20 6.1 Foundation for Generator 6 days Fri 6/24/22 Fri 7/1/22 Carpentary[50%],aggrigate[1.5],Cement[6],Labour[150%],sand[1],Mason,Mixer[1],Steel Fixer[50%],Vibrator[1]
21 6.2 Cabinet Foundation 4 days Fri 6/24/22 Wed 6/29/22 20SS Carpentary[50%],aggrigate[1],Cement[7],Labour[150%],Mixer[0.5],Steel Fixer[50%]
22 6.3 ACDB/ ATS Foundation 5 days Fri 6/24/22 Thu 6/30/22 21SS Carpentary[50%],aggrigate[1],Cement[2],Labour,Mason[50%],Mixer[0.5],Steel Fixer[50%],Vibrator[0.5]
23 6.4 Cable tray foundation and Support 1.5 days Sat 6/25/22 Mon 6/27/22 22SS Carpentary[50%],Labour,aggrigate[0.5],Cement[2],Mason,sand[1],Vibrator[1],Steel Fixer
24 6.5 Cable ladder Foundation 1 day Sat 6/25/22 Sat 6/25/22 23SS Labour[200%],aggrigate[0.5],Carpentary[50%],Cement[2],Mason[50%],Mixer[0.25],sand[0.2],Steel Fixer[50%],Vibrator[0.25],Labo
25 6.6 Hand hole. 32 days Sat 6/25/22 Fri 8/5/22 24SS aggrigate[0.5],Carpentary[50%],Cement[2],Formwork[4.5],Labour[150%],Na
26 6.7 Installation of PVC 2 days Sun 6/26/22 Mon 6/27/22
27 7 Building Guard house and latrine 6 days Fri 7/15/22 Fri 7/22/22
28 7.1 Excavation for latrine 2 days Fri 7/15/22 Mon 7/18/22 Labour[350%]
29 7.2 Masonary work for laterin 2 days Tue 7/19/22 Wed 7/20/22 28 Masonary[16.5],Labour[250%],Mason,Cement[6],sand[3]
30 7.3 Formwork and reinforcement for grade beam 1 day Thu 7/21/22 Thu 7/21/22 29 Labour[300%],Carpentary[200%],Nail[6],Steel Fixer[250%],Formwork[2],Re bar[79.5]
31 7.4 Casting grade beam and slab on grade 1 day Fri 7/22/22 Fri 7/22/22 30 Labour[750%],Mason[350%],aggrigate[4.5],Cement[10],Mixer[4],sand[4],Vibrator[3.5]
32 7.5 False column/Concreting 0.5 days Mon 7/25/22 Mon 7/25/22 31 Mason[350%],aggrigate[1.5],Carpentary[150%],Cement[5.5],Formwork[2.5],Mixer[1.5],Nail
33 7.6 Block wall/ Partion work 2 days Mon 7/25/22 Wed 7/27/22 32 Mason[200%],Labour,Cement[4],sand[2.5],Block[350]
34 7.7 Plastering 2 days Wed 7/27/22 Fri 7/29/22 33 Labour[300%],Plasterer[200%],Cement[5.5],sand[3]
35 7.8 Roofing 1 day Fri 7/29/22 Tue 8/2/22 34 EGA Roof Sheet[6],5x7 Zigba Purlin[1],Carpentary[200%],Eucalyptus[1],Labour
36 8 Fence work 6 days Fri 7/15/22 Fri 7/22/22 27
37 8.1 Foundation for fence 2 days Fri 7/15/22 Mon 7/18/22
38 8.1.1 Treanch Excavation and Post Foundation 1 day Fri 7/15/22 Fri 7/15/22 Labour[750%]
39 8.1.2 Masonary work for Fence beam 2 days Mon 7/18/22 Tue 7/19/22 38 Cement[4],Labour[200%],Mason[250%],Masonary[8],sand[7]
40 8.1.3 Reinforcement and Formwork for beam 1 day Wed 7/20/22 Wed 7/20/22 39 Steel Fixer[350%],Carpentary[200%],Formwork[3],Labour[300%],Re bar[21],5x7 Zigba Purlin[1]
41 8.1.4 Vertical Steel Post 1 day Thu 7/21/22 Thu 7/21/22 40 Technician[350%],Labour[300%],Block[1]
42 8.1.5 Casting concrete C-25 1 day Fri 7/22/22 Fri 7/22/22 41 Cement[5],aggrigate[5],Labour[500%],sand[3],Carpentary,Mason[200%],Comapctor[1]
43 8.2 Fence beam (20x30)cm 2 days Tue 7/19/22 Wed 7/20/22 37
44 8.2.1 Formwork and Reinforcement 1 day Tue 7/19/22 Tue 7/19/22 Carpentary[200%],Formwork[2.5],Labour[300%],Nail[5],Eucalyptus[0.5],Steel Fixer[300%],Re bar
45 8.2.2 Concrete Casting C-25 1 day Wed 7/20/22 Wed 7/20/22 44 Labour[600%],aggrigate[3],Cement[7],sand[2.5],Mason[200%]
46 8.3 Mesh Fence 1.5 days Fri 7/22/22 Mon 7/25/22
47 8.3.1 Fixing Mesh 1.5 days Fri 7/22/22 Mon 7/25/22 Technician[550%],Labour[150%]
48 9 Site Gravel 1 day Sun 7/24/22 Sun 7/24/22 36
49 9.1 Leveling Gravel 1 day Sun 7/24/22 Sun 7/24/22 Labour[350%],aggrigate[16]
50 10 Fixing main Gate 1 day Mon 7/25/22 Mon 7/25/22 48
51 10.1 Main Gate 1 day Mon 7/25/22 Mon 7/25/22 Technician[250%],Labour[400%]

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Site ID 305050-Cha Cha
Milestone Inactive Summary Start-only Critical
Date: Mon 6/27/22
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress