ANALISA VOLUME PEKERJAAN

Proyek :
Lokasi :
Bagian :

LT No Uraian Pekerjaan (sketsa) Uraian Bag

A PONDASI FOOTPLATE
1 Galian Foot Plate

2 Pemadatan Tanah
3 Pasir Urug t=5cm
4 Lantai Kerja t=5cm

5 Volume Beton:
a Foot Plate
b Pedestal
c T-Beam 20/30
FORM : BT- 001

No. Lbr :

Jml.Lbr :

Variabel Terhitung Pek.


Uraian Bagian
L p l t Un/L Volume

0.90 0.90 0.60 12 5.83

0.90 0.90 12 9.72


0.90 0.90 0.05 12 0.49
0.90 0.90 0.05 12 0.49

0.70 0.70 0.25 12 1.47


0.30 0.30 0.35 12 0.38
13.00 4.00 52.00 0.20 0.30 3.12
: BT- 001

Terhitung Pek.
Sat

m3

m2
m3
m3

m3
m3
m3
ANALISA VOLUME PEKERJAAN

Proyek :
Lokasi :
Bagian :

LT No Uraian Pekerjaan (sketsa) Uraian Ba


1 Kolom Beton
K1

2 Kolom Baja (Alt 2)


K2
FORM : BT- 001

No. Lbr :

Jml.Lbr :

Variabel Terhitung Pek.


Uraian Bagian
L p l t Un/L Volume

0.30 0.30 3.20 12 3.46

3.20 12.00 38.40


: BT- 001

Terhitung Pek.
Sat

m3

m'
ANALISA VOLUME PEKERJAAN

Proyek :
Lokasi :
Bagian :

LT No Uraian Pekerjaan (sketsa)

1 Balok Beton (Alt 1)


B1 25x40
B2 25x40
B3 15x30

2 Balok Baja (Alt 2)


WF 150x75x5x7
WF 200x100x5,5x8
WF 250x125x6x9
Hollow 100x50x4
Variabel
Uraian Bagian
L p l t

40.00 0.25 0.40


20.00 0.25 0.40
52.00 0.15 0.30

92.00
58.50
44.50
19.50
FORM : BT- 001

No. Lbr :

Jml.Lbr :

Terhitung Pek.
Un/L Volume Sat

4.00 m3
2.00 m3
2.34 m3

92.00 m'
58.50 m'
44.50 m'
19.50 m'
ANALISA VOLUME PEKERJAAN

Proyek :
Lokasi :
Bagian :

LT No Uraian Pekerjaan (sketsa) Uraian

Plat Lt
Wm M6-150 t= 13cm
Rabat Beton t=20cm
Plastik Membran / Plastik Layer t=0,2mm
Joint Sealent
FORM : BT- 001

No. Lbr :

Jml.Lbr :

Variabel Terhitung Pek.


Uraian Bagian
L p l t Un/L Volume

0.09 12.00 1.08 167.92 0.13 21.83


0.09 12.00 1.08 167.92 0.20 33.58
0.09 12.00 1.08 167.92 167.92
0.13 24 3.12
: BT- 001

Terhitung Pek.
Sat

m3
m3
m2
m'
ANALISA VOLUME PEKERJAAN

Proyek :
Lokasi :
Bagian :

LT No Uraian Pekerjaan (sketsa) Urai


LT1 1 PEKERJAAN LANTAI
Screading Lt
Rolag Bata area Trap Tangga 13.00
Anti Rayap
FORM : BT- 001

No. Lbr :

Jml.Lbr :

Variabel
Uraian Bagian
L p l t Un/L

0.09 12.00 1.08 167.92


1.50 1.80 2.00 85.80
169.00
FORM : BT- 001

No. Lbr :

Jml.Lbr :

Terhitung Pek.
Volume Sat

167.92 m2
85.80 m2
169.00 m2
ANALISA VOLUME PEKERJAAN

Proyek :
Lokasi :
Bagian :

LT No Uraian Pekerjaan (sketsa) Uraia


LT1 1 PEKERJAAN PLAFON
Plafon 68.88
Rangka Plafon 68.88
Cat Plafon 68.88
FORM : BT- 001

No. Lbr :

Jml.Lbr :

Variabel Terhitung Pek.


Uraian Bagian
L p l t Un/L Volume

47.60 116.48 116.48


47.60 116.48 116.48
47.60 116.48 116.48
: BT- 001

Terhitung Pek.
Sat

m2
m2
m2
ANALISA VOLUME PEKERJAAN

Proyek :
Lokasi :
Bagian :

LT No Uraian Pekerjaan (sketsa) Uraia

PLESTERAN + ACIAN

1 1 Plesteran + Acian Kolom

Total Pekerjaan Plesteran + Acian

2 Sponengan Kolom
FORM : BT- 001

No. Lbr :

Jml.Lbr :

Variabel Terhitung Pek.


Uraian Bagian
L p l t Un/L Volume

2.00 1.20 0.30 0.30 3.20 12 46.08

46.08

3.20 48 153.60
: BT- 001

Terhitung Pek.
Sat

m2

m2

m'
ANALISA VOLUME PEKERJAAN

Proyek :
Lokasi :
Bagian :

LT No Uraian Pekerjaan (sketsa) Uraia


R 1 PEKERJAAN ATAP GENTENG
Penutup Atap 68.88
Rangka Atap
Brunjung
Molo
List Plank
FORM : BT- 001

No. Lbr :

Jml.Lbr :

Variabel
Uraian Bagian
L p l t Un/L

47.60 116.48

15.20
1.70
52.00
FORM : BT- 001

No. Lbr :

Jml.Lbr :

Terhitung Pek.
Volume Sat

116.48 m2
116.48 m2
15.20 m'
1.70 m'
52.00 m'
Sloof
Vol Sat Uraian Tenaga Bahan Harga Teaga+Bhn+Alt
1.00 m3 K175 Rp 150,000.00 Rp 960,000.00 Rp 1,110,000.00
kg Besi Ulir Rp 7,000.00 Rp 25,000.00 Rp 32,000.00
m2 Bekisting Sloof Rp 150,000.00

Balok
Vol Sat Uraian Tenaga Bahan Harga Teaga+Bhn
1.00 m3 K175 Rp 150,000.00 Rp 960,000.00 Rp 1,110,000.00
kg Besi Ulir Rp 7,000.00 Rp 25,000.00 Rp 32,000.00
m2 Bekisting Rp 150,000.00

Kolom STUKUR
Vol Sat Uraian Tenaga Bahan Harga Teaga+Bhn
1.00 m3 K175 Rp 150,000.00 Rp 960,000.00 Rp 1,110,000.00
kg Besi Ulir Rp 7,000.00 Rp 25,000.00 Rp 32,000.00
m2 Bekisting Rp 150,000.00

Plat
Vol Sat Uraian Tenaga Bahan Harga Teaga+Bhn
1.00 m3 K175 Rp 150,000.00 Rp 960,000.00 Rp 1,110,000.00
kg Besi Ulir Rp 2,000.00 Rp 9,000.00 Rp 11,000.00
m2 Bekisting Rp 150,000.00

FOOTPLAT
Vol Sat Uraian Tenaga Bahan Harga Teaga+Bhn
1.00 m3 K175 Rp 150,000.00 Rp 960,000.00 Rp 1,110,000.00
kg Besi Ulir Rp 2,000.00 Rp 9,000.00 Rp 11,000.00
m2 Bekisting Rp 150,000.00
Harga Beton
Harga Terhitung
Rp 1,110,000.00 Beton Tenaga Bahan
Rp - K175 Rp 900,000.00
Rp - K225
Rp 1,110,000.00 K250 Rp 975,000.00
K275 Rp 1,000,000.00
K300 Rp 150,000.00 Rp 1,025,000.00
K325 Rp 1,050,000.00
Harga Terhitung K350 Rp 1,075,000.00
Rp 1,110,000.00
Rp - By Extra untuk Penjagaan Polisi,dll
Rp - 150000
Rp 1,110,000.00

Harga Terhitung
Rp 1,110,000.00
Rp -
Rp -
Rp 1,110,000.00

Harga Terhitung
Rp 1,110,000.00
Rp -
Rp -
Rp 1,110,000.00

Harga Terhitung
Rp 1,110,000.00
Rp -
Rp -
Rp 1,110,000.00
Total
Rp 900,000.00
Rp -
Rp 975,000.00
Rp 1,000,000.00
Rp 1,175,000.00
Rp 1,050,000.00
Rp 1,075,000.00
Analisa Netto Harga Satuan Beton

LANTAI 1
A FootPlat
Vol Sat Uraian Tenaga Bahan Harga Teaga+Bhn+Alt Harga Terhitung
1.00 m3 K175 Rp 150,000.00 Rp 960,000.00 Rp 1,110,000.00 Rp 1,110,000.00
43.37 kg Besi Ulir Rp 7,000.00 Rp 25,000.00 Rp 32,000.00 Rp 1,387,903.41
0.46 m2 Bekisting Rp 200,000.00 Rp 92,165.90 Bekisting dpt dr hrga penawaran vendor bekisting jogja
Rp 2,590,069.31

B Balok T_Beam
Vol Sat Uraian Tenaga Bahan Harga Teaga+Bhn+Alt Harga Terhitung
1.00 m3 K175 Rp 150,000.00 Rp 960,000.00 Rp 1,110,000.00 Rp 1,110,000.00
152.39 kg Besi Ulir Rp 7,000.00 Rp 25,000.00 Rp 32,000.00 Rp 4,876,543.79
10.00 m2 Bekisting Rp - Rp - Rp 200,000.00 Rp 2,000,000.00
Rp 7,986,543.79

C Kolom Pedestal
Vol Sat Uraian Tenaga Bahan Harga Teaga+Bhn+Alt Harga Terhitung
1.00 m3 K175 Rp 150,000.00 Rp 960,000.00 Rp 1,110,000.00 Rp 1,110,000.00
737.21 kg Besi Ulir Rp 7,000.00 Rp 25,000.00 Rp 32,000.00 Rp 23,590,637.04
15.56 m2 Bekisting Rp - Rp - Rp 200,000.00 Rp 3,111,111.11
Rp 27,811,748.15

D Kolom Str K1
Vol Sat Uraian Tenaga Bahan Harga Teaga+Bhn+Alt Harga Terhitung
1.00 m3 K175 Rp 150,000.00 Rp 960,000.00 Rp 1,110,000.00 Rp 1,110,000.00
173.50 kg Besi Ulir Rp 7,000.00 Rp 25,000.00 Rp 32,000.00 Rp 5,551,869.63
11.11 m2 Bekisting Rp - Rp - Rp 200,000.00 Rp 2,222,222.22
Rp 8,884,091.85

E Balok B1
Vol Sat Uraian Tenaga Bahan Harga Teaga+Bhn+Alt Harga Terhitung
1.00 m3 K175 Rp 150,000.00 Rp 960,000.00 Rp 1,110,000.00 Rp 1,110,000.00
144.51 kg Besi Ulir Rp 7,000.00 Rp 25,000.00 Rp 32,000.00 Rp 4,624,213.33
8.50 m2 Bekisting Rp - Rp - Rp 200,000.00 Rp 1,700,000.00
Rp 7,434,213.33

F Balok B2
Vol Sat Uraian Tenaga Bahan Harga Teaga+Bhn+Alt Harga Terhitung
1.00 m3 K175 Rp 150,000.00 Rp 960,000.00 Rp 1,110,000.00 Rp 1,110,000.00
311.15 kg Besi Ulir Rp 7,000.00 Rp 25,000.00 Rp 32,000.00 Rp 9,956,821.33
10.00 m2 Bekisting Rp - Rp - Rp 200,000.00 Rp 2,000,000.00
Rp 13,066,821.33

G Balok B3
Vol Sat Uraian Tenaga Bahan Harga Teaga+Bhn+Alt Harga Terhitung
1.00 m3 K175 Rp 150,000.00 Rp 960,000.00 Rp 1,110,000.00 Rp 1,110,000.00
176.27 kg Besi Ulir Rp 7,000.00 Rp 25,000.00 Rp 32,000.00 Rp 5,640,659.75
12.22 m2 Bekisting Rp - Rp - Rp 200,000.00 Rp 2,444,444.44
Rp 9,195,104.20

H Wm M6
Vol Sat Uraian Tenaga Bahan Harga Teaga+Bhn Harga Terhitung
1.00 m3 K175 Rp 150,000.00 Rp 920,000.00 Rp 1,070,000.00 Rp 1,070,000.00
7.69 m2 wiremesh m6 Rp 15,000.00 Rp 30,000.00 Rp 45,000.00 Rp 346,153.85
6.76 m2 Bekisting Rp 45,000.00 Rp 304,200.00
Rp 1,720,353.85
H Rbt Betontebal 8cm
Vol Sat Uraian Tenaga Bahan Harga Teaga+Bhn Harga Terhitung
1.00 m3 K175 Rp 150,000.00 Rp 700,000.00 Rp 850,000.00 Rp 850,000.00
6.76 m2 Bekisting Rp 45,000.00 Rp 304,200.00
Rp 1,154,200.00
ANALISA VOLUME PEKERJAAN FORM : BT- 001

Proyek : No. Lbr :


Lokasi :
Bagian : Jml.Lbr :

Variabel Terhitung Pek.


LT No Uraian Pekerjaan (sketsa) Uraian Bagian
kg/m P L T Un/L Volume Sat

FOOTPLAT IGD

1 FP-1 700 700 25 10 7.000 7.000 0.250 12.250 15.190 m³


Sample : 1 unit 0.100 2.940 0.066 X
BETON 1.000 m3 1.000 m3
Pendek Panjang
BESI D10 200 200
D10 200 200
Besi Tul Pokok Atas - Pendek 200 D-10 0.624 7.180 36.000 161.335 kg/spl
Tul Pokok Atas - Panjang 200 D-10 0.624 7.180 36.000 161.335 kg/spl
Tul Pokok Bawah - Pendek 200 D-10 0.624 7.480 36.000 168.076 kg/spl
Tul Pokok Bawah - Panjang 200 D-10 0.624 7.480 36.000 168.076 kg/spl
TOTAL BERAT BESI TULANGAN 43.372 KG

BEKISTING 7.000 7.000 0.250 2.000 7.000 m2/spl


0.461 M2
2 Balok T_Beam 20/30 0.200 0.300 16.667 16.667 m'/m3
Sample : 3.4 m' 4.902 X
BETON 1.000 m3 1.000 m3

BESI 2 2 2
2 2 2
Besi Tul Pokok Atas 2 D-13 8.200 1.042 8.200 1.000 8.542 kg/spl
Tul Ekstra Atas Kiri 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Ekstra Atas Kanan 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Pokok Bawah 2 D-13 7.000 1.042 7.000 1.000 7.292 kg/spl
Tul Ekstra Tengah 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Ekstra Atas Kiri 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Ekstra Atas Kanan 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Sengkang Tumpuan 150 D-10 0.160 0.260 0.160 0.260 0.100 0.624 0.940 0.150 13.000 7.627 kg/spl
Tul Sengkang Lapangan 150 D-10 0.160 0.260 0.160 0.260 0.100 0.624 0.940 0.150 13.000 7.627 kg/spl
TOTAL BERAT BESI TULANGAN ULIR 152.392 KG
BEKISTING 0.200 0.200 0.200 0.600 3.400 1.000 2.040 m2/spl
10.000 M2

3 Kolom Pedestal 30/30 0.300 0.300 11.111 11.111 m'/m³


Sample : 0.3 m' 37.037 x
BETON 1.000 m3 1.000 m3

BESI Tul Pokok 8 D-13 17.040 1.040 17.040 1.000 17.722 kg/spl
Tul Sengkang Tumpuan 200 D-10 0.270 0.270 0.270 0.270 0.100 0.617 1.180 0.200 2.000 1.455 kg/spl
Tul Sengkang Lapangan 200 D10 0.270 0.270 0.270 0.270 0.100 0.617 1.180 0.200 1.000 0.728 kg/spl
TOTAL BERAT BESI K1-A 20X40 Besi Ulir 884.649 737.207 kg

BEKISTING 0.400 0.300 0.700 0.300 2.000 0.420 m2/spl


TOTAL BEKISTING 18.667 15.556 m2

4 Kolom Str K1 30/30 0.300 0.600 5.556 5.556 m'/m³


Sample : 1 m' 5.556 x
BETON 1.000 m3 1.000 m3

BESI Tul Pokok 8 D-13 22.640 1.040 22.640 1.000 23.546 kg/spl
Tul Sengkang Tumpuan 200 D-10 0.270 0.570 0.270 0.570 0.100 0.617 1.780 0.200 4.000 4.391 kg/spl
Tul Sengkang Lapangan 200 D10 0.270 0.570 0.270 0.570 0.100 0.617 1.780 0.200 3.000 3.293 kg/spl
TOTAL BERAT BESI K1-A 20X40 Besi Ulir 208.195 173.496 kg

BEKISTING 0.400 0.600 1.000 1.000 2.000 2.000 m2/spl


TOTAL BEKISTING 13.333 11.111 m2

5 Balok B1 25/40 0.250 0.400 10.000 10.000 m'/m3


Sample : 1.5 m' 6.667 X
BETON 1.000 m3 1.000 m3

BESI 3 3 3
3 3 3
Besi Tul Pokok Atas 3 D-13 7.200 1.042 7.200 1.000 7.500 kg/spl
Tul Ekstra Atas Kiri 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Ekstra Atas Kanan 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Pokok Bawah 3 D-13 4.800 1.042 4.800 1.000 5.000 kg/spl
Tul Ekstra Tengah 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Ekstra Atas Kiri 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Ekstra Atas Kanan 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Sengkang Tumpuan 150 D-10 0.210 0.360 0.210 0.360 0.100 0.617 1.240 0.150 6.000 4.588 kg/spl
Tul Sengkang Lapangan 150 D-10 0.210 0.360 0.210 0.360 0.100 0.617 1.240 0.150 6.000 4.588 kg/spl
TOTAL BERAT BESI TULANGAN ULIR 144.507 KG

BEKISTING 0.250 0.300 0.300 0.850 1.500 1.000 1.275 m2/spl


8.500 M2

6 Balok B2 25/40 0.200 0.300 16.667 16.667 m'/m3


Sample : 3.75 m' 4.444 X
BETON 1.000 m3 1.000 m3

BESI 5 5 5
4 4 4
Besi Tul Pokok Atas 5 D-16 22.250 1.583 22.250 1.000 35.229 kg/spl
Tul Ekstra Atas Kiri 0 D-16 0.000 1.583 0.000 1.000 0.000 kg/spl
Tul Ekstra Atas Kanan 0 D-16 0.000 1.583 0.000 1.000 0.000 kg/spl
Tul Pokok Bawah 4 D-16 15.400 1.583 15.400 1.000 24.383 kg/spl
Tul Ekstra Tengah 0 D-16 0.000 1.583 0.000 1.000 0.000 kg/spl
Tul Ekstra Atas Kiri 0 D-16 0.000 1.583 0.000 1.000 0.000 kg/spl
Tul Ekstra Atas Kanan 0 D-16 0.000 1.583 0.000 1.000 0.000 kg/spl
Tul Sengkang Tumpuan 150 D-10 0.160 0.260 0.160 0.260 0.100 0.395 0.940 0.150 14.000 5.198 kg/spl
Tul Sengkang Lapangan 150 D-10 0.160 0.260 0.160 0.260 0.100 0.395 0.940 0.150 14.000 5.198 kg/spl
TOTAL BERAT BESI TULANGAN ULIR 311.151 KG

BEKISTING 0.200 0.200 0.200 0.600 3.750 1.000 2.250 m2/spl


10.000 M2

7 Balok B3 15/30 0.150 0.300 22.222 22.222 m'/m3


Sample : 1.5 m' 14.815 X
BETON 1.000 m3 1.000 m3

BESI 2 2 2
2 2 2
Besi Tul Pokok Atas 2 D-13 4.400 1.042 4.400 1.000 4.583 kg/spl
Tul Ekstra Atas Kiri 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Ekstra Atas Kanan 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Pokok Bawah 2 D-13 3.200 1.042 3.200 1.000 3.333 kg/spl
Tul Ekstra Tengah 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Ekstra Atas Kiri 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Ekstra Atas Kanan 0 D-13 0.000 1.042 0.000 1.000 0.000 kg/spl
Tul Sengkang Tumpuan 150 D-10 0.110 0.260 0.110 0.260 0.100 0.395 0.840 0.150 6.000 1.991 kg/spl
Tul Sengkang Lapangan 150 D-10 0.110 0.260 0.110 0.260 0.100 0.395 0.840 0.150 6.000 1.991 kg/spl
TOTAL BERAT BESI TULANGAN ULIR 176.271 KG
BEKISTING 0.150 0.200 0.200 0.550 1.500 1.000 0.825 m2/spl
12.222 M2

8 PLAT LANTAI 13 cm 1.500 1.500 0.130 0.293 m3


Sample : 2.25 m2 3.419 x/m2
BETON 1.000 m3 1.000 m3

WIRE MESH M6 3.070 1.500 1.500 1.000 6.908 kg/spl


2.250 m2/spl

1 rol 2.100 5.400 11.340


TOTAL BERAT WIREMESH 31.308 KG
TOTAL LUAS WIREMESH 7.692 m2
24.5 27.44
2.94
0
ESTIMASI RENCANA ANGGARAN BIAYA
JOGLO GEREJA CILACAP
Pekerjaan : Pembangunan Joglo - Gereja Tanggal : Juni 2022
Kota : Cilacap Luas : 100 m2

JUMLAH HARGA SUBTOTAL HARGA Proc


NO URAIAN PEKERJAAN
(Rp) (Rp) Pek

A PRELIMINARY #NAME? #NAME?

#NAME? #NAME?

B PEKERJAAN STRUKTUR

1 PEKERJAAN PONDASI Rp. 62,807,747.55 #NAME?

2 PEKERJAAN BAJA DAN BETON Rp. 125,363,410.74 #NAME?

Rp. 188,171,158.29 #NAME?

C. PEKERJAAN ARSITEKTUR

1 PEKERJAAN PASANGAN Rp. 20,576,916.94 #NAME?

2 PEKERJAAN ATAP GENTENG Rp. 58,642,970.88 #NAME?

Rp. 79,219,887.82 #NAME?

D. PEKERJAAN ELEKTRIKAL DAN PLUMBING

1 PEKERJAAN INSTALASI LISTRIK Rp. 6,450,000.00 #NAME?

2 PEKERJAAN INSTALASI PLUMBING Rp. 9,130,000.00 #NAME?

Rp. 15,580,000.00 #NAME?

TOTAL #NAME?
#NAME? #NAME?
PEMBULATAN #NAME?
JUMLAH HARGA SUBTOTAL HARGA Proc
NO URAIAN PEKERJAAN
(Rp) (Rp) Pek

Tiga Ratus Empat Juta Tujuh Ratus Tiga Puluh Ribu


TERBILANG
Rupiah
ESTIMASI RENCANA ANGGARAN BIAYA
JOGLO GEREJA CILACAP

Pekerjaan : Persiapan
Kota : Cilacap
Sat. Agustus September Oktober
No. Uraian Pekerjaan VOL Bobot
Pek. M1 M2 M3 M4 M5 M1 M2 M3 M4 M5 M1 M2
Chart Title
A PRELIMINARY
1 Uitzet ( Pengukuran ) 1.00 ls 0.20% 0.20%
2 Bowplank 60.00 m' 1.79% 1.79%
3 Pek. Pagar Pengaman - m'
4 Gudang Bahan & Material 20.00 m2 5.34% 2.67% 2.67%
5 Pek. Papan Nama Proyek 120 x 90 cm 1.00 bh 0.12% 0.12%
6 Pembersihan Lapangan Awal 169.00 m2 0.34% 0.34%
7 Pembersihan Lapangan Akhir 169.00 m2 0.34% 0.17% 0.17%
8 Listrik Kerja (Penerangan, Mesin, Pompa air) 2.00 bln 0.28% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
9 Keamanan Proyek 2.00 bln 0.41% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%

B STRUKTUR
B.1. PEKERJAAN PONDASI
Pekerjaan Foot Plate
25.47% 5.09% 5.09% 5.09% 5.09% 5.09%
ok
B.2. PEKERJAAN BAJA DAN BETON
Kolom Struktur
1 K2 (HB200x200x8X12) 38.40 m'
15.75% 3.15% 3.15% 3.15% 3.15% 3.15%
Ring Balok
1 WF 150x75x5x7 92.00 m' 6.96% 6.96%
2 WF 200x100x5,5x8 58.50 m' 7.45% 3.72% 3.72%
3 WF 250x125x6x9 44.50 m' 11.77% 5.89% 5.89%

C ARSITEKTURAL
C.2. PEKERJAAN ATAP GENTENG
23.78% 5.94% 5.94% 5.94% 5.94%
REKAP TOTAL 100%
Bobot Total 5.18% 7.82% 8.30% 8.30% 8.30% 8.30% 13.89% 15.61% 11.89% 6.00% 6.17% 0.23%
Bobot Akumulatif 5.18% 13.00% 21.30% 29.60% 37.90% 46.20% 60.09% 75.71% 87.60% 93.60% 99.77% 100.00%
ESTIMASI RENCANA ANGGARAN BIAYA
JOGLO GEREJA CILACAP

Pekerjaan : Struktur
Kota : Cilacap

Sat. Harga Sat Harga Terhitung Jumlah Proc


No. Uraian Pekerjaan VOL
Pek. Pekerjaan Upah&Bahan Terhitung Pek

B STRUKTUR

B.1. PEKERJAAN PONDASI

Pekerjaan Foot Plate

1 Galian Foot Plate 34.58 m3 Rp. 100,980.00 Rp. 3,491,888.40 1.86%

2 Pemadatan Tanah 9.72 m2 Rp. 121,176.00 Rp. 1,177,830.72 0.63%

3 Pasir Urug t=5cm 0.49 m3 Rp. 309,100.00 Rp. 150,222.60 0.08%

4 Lantai Kerja t=5cm 0.49 m3 Rp. 418,820.00 Rp. 203,546.52 0.11%

5 Pekerjaan Beton Foot Plate: 0.00%

a Foot Plate 1.47 m3 Rp. 2,590,069.31 Rp. 3,807,401.88 2.02%

b Pedestal 0.38 m3 Rp. 27,811,748.15 Rp. 10,512,840.80 5.59%

c T-Beam 20/30 3.12 m3 Rp. 7,986,543.79 Rp. 24,918,016.63 13.24%

6 Pasir Urug t=60cm (untuk menaikkan level lantai utama) 60.00 m³ Rp. 309,100.00 Rp. 18,546,000.00 9.86%

Rp. 62,807,747.55 33.38%

ok

B.2. PEKERJAAN BAJA DAN BETON

Kolom Struktur

1 K2 (HB200x200x8X12) 38.40 m' Rp. 1,011,349.69 Rp. 38,835,828.13 20.64%

Rp. 38,835,828.13 20.64%

ok
Sat. Harga Sat Harga Terhitung Jumlah Proc
No. Uraian Pekerjaan VOL
Pek. Pekerjaan Upah&Bahan Terhitung Pek

Ring Balok

1 WF 150x75x5x7 92.00 m' Rp. 186,670.41 Rp. 17,173,677.72 9.13%

2 WF 200x100x5,5x8 58.50 m' Rp. 313,926.11 Rp. 18,364,677.44 9.76%

3 WF 250x125x6x9 44.50 m' Rp. 652,388.70 Rp. 29,031,297.15 15.43%

Rp. 64,569,652.31 34.31%

ok

Plat Lantai

1 Wm M6-150 t= 13cm 21.83 m3 Rp. 535,567.96 Rp. 11,691,234.34 6.21%

2 Rabat Beton t=20cm 33.58 m3 Rp. 305,702.00 Rp. 10,266,695.97 5.46%

Rp. 21,957,930.31 11.67%

ok

TOTAL Rp. 188,171,158.29 100.00% 100.00%


ESTIMASI RENCANA ANGGARAN BIAYA
JOGLO GEREJA CILACAP

Pekerjaan : Arsitektural
Kota : Cilacap
:
Sat. Harga Sat Harga Terhitung Jumlah Proc
No. Uraian Pekerjaan VOL
Pek. Pekerjaan Upah&Bahan Terhitung Pek

C ARSITEKTURAL

C.1. PEKERJAAN PASANGAN

1 Plesteran + Acian Kolom 46.08 m² Rp. 103,021.05 Rp. 4,747,209.98 5.99%

2 Sponengan Kolom 153.60 m' Rp. 15,115.10 Rp. 2,321,679.36 2.93%

3 Screading Lt 100.00 m² Rp. 40,356.80 Rp. 4,035,680.00 5.09%

4 Tumpukan Bata untuk teras dan trap tangga 69.00 m² Rp. 137,280.40 Rp. 9,472,347.60 11.96%

Rp. 20,576,916.94 25.97%

ok

C.2. PEKERJAAN ATAP GENTENG

1 Penutup atap spandek pasir tebal 0.03mm 116.48 m² Rp. 95,000.00 Rp. 11,065,600.00 13.97%

2 Rangka Atap (WF) 116.48 m² Rp. 258,906.00 Rp. 30,157,370.88 38.07%

3 Usuk Reng (Baja Ringan) 116.48 m² Rp. 125,000.00 Rp. 14,560,000.00 18.38%

4 Listplank Kayu (uk. 200x18 mm), inc. Cat 52.00 m' Rp. 55,000.00 Rp. 2,860,000.00 3.61%

Rp. 58,642,970.88 74.03%

ok

TOTAL Rp. 79,219,887.82 100.00% 100.00%


ESTIMASI RENCANA ANGGARAN BIAYA
JOGLO GEREJA CILACAP

Pekerjaan : Elektrikal
Kota : Cilacap

Sat. Harga Sat Harga Terhitung Jumlah Proc


No. Uraian Pekerjaan VOL
Pek. Pekerjaan Upah&Bahan Terhitung Pek

D ELEKTRIKAL

D.1 PEKERJAAN INSTALASI LISTRIK

1 Lampu LED downlight 9 watt (daylight) 9.00 unit Rp. 150,000.00 Rp. 1,350,000.00 8.66%

2 Outdoor Wall Lamp, LED 9 watt (warm white) 8.00 unit Rp. 350,000.00 Rp. 2,800,000.00 17.97%

3 Instalasi Stop kontak single 13A 1PH (200W) 5.00 unit Rp. 150,000.00 Rp. 750,000.00 4.81%

4 Instalasi lampu NYM 3 x 2,5 mm2 9.00 unit Rp. 150,000.00 Rp. 1,350,000.00 8.66%

5 Saklar Single 4.00 unit Rp. 20,000.00 Rp. 80,000.00 0.51%

6 Saklar Double 1.00 unit Rp. 20,000.00 Rp. 20,000.00 0.13%

7 Stop Kontak Single 5.00 unit Rp. 20,000.00 Rp. 100,000.00 0.64%

Rp. 6,450,000.00 41.40%

ok

D.2 PEKERJAAN INSTALASI PLUMBING

1 Instalasi Pipa Air Bersih (asumsi sumber air PDAM) 1.00 ls Rp. 250,000.00 Rp. 250,000.00 1.60%

2 Instalasi Pipa Air Bekas 1.00 ls Rp. 500,000.00 Rp. 500,000.00 3.21%

3 Pembuatan Gutter dan Tutup beton (di sekitar Joglo) 58.00 m' Rp. 135,000.00 Rp. 7,830,000.00 50.26%

4 Bak Kontrol 1.00 unit Rp. 550,000.00 Rp. 550,000.00 3.53%

Rp. 9,130,000.00 58.60%

ok

TOTAL Rp. 15,580,000.00 100.00% 100.00%