Professional Documents
Culture Documents
Chapter 10 New
Chapter 10 New
10-1
SELECTION OF UPS
3 PHASE OR 1 PHASE
Single phase power is used in most homes and small Most consumers of electricity in India have a three
businesses and adequate for running lights, fans, 1 or phase mains connection if the total load is more
2 ACs, some computers and motors up to about 5 than 5-7 KW. Only if expected load is below 5-7KW,
horsepower; a single phase motor draws significantly then the consumer gets a single phase connection.
more current than the equivalent 3-phase motor, Even when the consumer has a three phase
making 3-phase power a more efficient choice for connection, the choice of three phase or single
industrial applications phase UPS depends on several factors like the
loads to be connected to UPS and also electrical
Single-phase distribution within the facility from the building
1
incomer, electrical switchgear and distribution units
0.5 to the room the loads to be protected are within.
This not only builds up a complete picture of the
Voltage
0
electrical circuits on-site. It also helps to determine
-0.5
whether to offer a three phase or single phase UPS
-1 system.
0 90 180 270 360
TIME
UPS Systems – Input and Output Phases
Figure-1 With the waveform of single-phase power, when the wave passes
through zero, the power supplied at that moment is zero. The wave cycles In UPS there are three potential phase
50 times per second configurations available. This is because a 3
phase mains or generator supply actually consists
3-phase power is common in large businesses, data
of three single phase supplies (and a neutral) with
centers, as well as industry and manufacturing around
a 120 degree phase orientation between the them.
the globe. While it is expensive to convert to three
A 3 phase supply can deliver more electrical
phase from an existing single phase
power than a single phase supply.
installation, 3-phase allows for smaller, safer and less
expensive wiring. The laws of physics and Ohms Law also come into
play, meaning that cable sizes also increase in
3-phase
1
diameter as amperages rise. A 10KVA output is
generally the largest single phase UPS system
0.5
available. This is due to the output amperage and
Voltage
10-2
© Copyrights Reserved
SELECTION OF UPS
3 PHASE OR 1 PHASE
3 Phase UPS Systems (3/3 and 3/1) system available (typically 10KVA) the UPS will
Most datacentres, commercial and industrial require a hardwired installation and should also
buildings will have a 3 phase electrical incomer that include an UPS maintenance bypass switch.
connects them via a local distribution transformer to UPS System Load Sizing
the Mains. Three phase circuits may be required When sizing UPS it is important to know the phase
throughout the building to carry the large amounts of configuration required by both the mains supply
electrical power required for large KVA three phase and the loads, in addition to the overall load size.
This is a generalisation as many environments can Electrical consultants and electrical contractors
include both single and three phase loads of course. will often state both load size and phase
configuration. An example would include ‘120KVA
From a UPS systems perspective, if we are to
three phase’. This refers to a 120KVA load run
connect the UPS to a three phase supply we require a
from a three phase 415Vac, 50Hz supply. In terms
UPS with a 3/x configuration. If the loads are three
of load sizing, this means that each phase (of the
phase as well, then we require a 3/3 configuration. If
3 phase electrical supply) will deliver upto 40KVA
the loads are single phase we may need a 3/1
(or 174Amps at 230Vac). If the statement was
configuration.
120KVA per phase then we would be looking at
Using a three phase UPS system can simplify a power 3×120KVA per phase = 360KVA UPS load. The
continuity plan and allows a site to adopt a centralised need for a 120KVA three phase UPS could be met
power protection plan, where one large UPS is used to with three single phase output 40KVA UPS
protect a complete building or critical circuits and provided the connected loads are single phase
operations within it. This is in contrast to a loads. These would be 3/1 configured and
decentralised power continuity plan using a number installed one per phase. However, the overall
of smaller UPS dispersed to protect clusters of loads capital, installation and energy efficiency costs
like computers and lower power equipment (<10KVA) just rose by a factor of 3 compared to a single
within a facility. 120KVA UPS system installation. 3/1 UPS upto
Single Phase UPS Systems (1/1) 60KVA are also used in office environment where
The wall sockets that we typically plug into are single the loads are single phase and this removes the
phase supplies rated at 230Vac 50Hz in India. Typical need to balance the load connections in each of
examples would include ATMs, small lab equipments, the three phases. Larger 3/1 UPS even upto
desktop computers, file servers, switches, routers, 200KVA are typically required for DCS and
hubs and telecoms systems. SCADA loads in heavy industries like Power Plant,
Single phase UPS systems up to 2KVA can be Steel Plant etc.
supplied with a plug or with covered terminals for Typical UPS
Input Output Nomenclature Mains Voltage
Sizes
hardwired installation. At 3KVA, the power
1 Phase 1 Phase 1/1 230/230Vac, 50Hz 400VA-10KVA
required means that the UPS will be supplied as
3 Phase 1 Phase 3/1 415/230Vac, 50Hz 5 - 200KVA
either a hardwired system or with a 16A plug.
3 Phase 3 Phase 3/3 415/415Vac, 50Hz 10KVA – 4.8MVA
Above 5KVA to the largest single phase UPS
10-3
© Copyrights Reserved
UPS SIZING
STEADY STATE LOAD
CONDITIONS
supply and the capacity of the UPS is defined in KVA Non-Critical Load 0% N
(apparent Power) and KW (real power). Critical Loads 66% N+1
Step 1: Need of Load load in KVA and KW derived in step 1 will have to
divided by N as selected in step 2 to arrive the
Tabulate the need of load as shown in the below table UPS capacity.
The sizing of UPS for loads which are dynamic in nature Number of Loads and Sequence of Operation
is a complicated subject, but with the recorded
The UPS selection depends on the no of loads, if
information as shown below, the optimised UPS
there is only one load, then the selection of UPS is
capacity can be derived based on
simple and is based on the maximum peak Current.
• Inrush Current-Nature & Duration
• Peak Process Current–Nature & Duration
UPS Capacity in KVA = √3 X V X Irms-peak
• Number of Loads, sequence of their operation
• Load Power Factor
If there are multiple loads with a combination of
• KVA and KW Demand of the UPS
static and dynamic loading characteristic, then
Inrush Current the UPS capacity is selected based on the
sequence of operation of the loads.
Input surge current or switch-on surge is the
maximum, instantaneous input current drawn by an
Sequential Operation of Load
electrical device when first turned on. The inrush
current can be omitted in the selection calculation if the
When the loads are operated in sequence, the
load is switched on only once and run continuously till
UPS capacity is selected based on the summation
the next shutdown of the plant as we can switch the
of rms currents of all the connected loads and the
loads in manual bypass and once the loads reach the
maximum rms peak current of the load as shown
steady state current, the loads can be transferred to the
in the below formula
UPS.
Peak Process Current When the loads are not operated in a sequence,
the UPS capacity is selected based on the
It is the maximum current drawn momentarily by the
summation of rms currents of all the connected
loads during the process time. This current can be
loads and the rms peak current of all the
repetitive in nature. The peak current has to be part of
connected load as shown in the below formula
the UPS Sizing calculation irrespective of the nature
and duration.
UPS capacity in KVA =√3 X V X ∑1n(Irms+ Irms-peak)
10-5
© Copyrights Reserved
BATTERY SIZING
CALCULATION
A VRLA battery utilizes a one-way, pressure-relief By design, the battery has to be operated in a
valve system to achieve a “recombinant” technology. controlled electrical and environmental conditions
This means that the oxygen normally produced on the and the critical elements affecting battery life are:
positive plate is absorbed by the negative plate. This
suppresses the production of hydrogen at the 1. Under charge Charging of battery with a
negative plate. Water (H2O) is produced instead, lower voltage and current
retaining the moisture within the battery. It never 2. Cycling Cyclic usage of battery
needs watering, and should never be opened as this 3. Overcharge Charging of battery with a
would expose the battery to excess oxygen from the higher voltage or current which is above the
air. recommended conditions of the manufacturer
4. Temperature The ambient temperature
• The nominal cell voltage of a battery cell is 2V, 6
cells are connected in series inside the battery References
container to have a final voltage of 12V.
• The capacity of the battery is defined as • IEEE 1184:2006 IEEE Guide for Batteries for
“Ampere Hour (AH)”. Uninterruptible Power Supply Systems
• The batteries are connected in series to increase • IEEE 485:1997 IEEE Recommended
the voltage of the battery bank and are Practice for Sizing Lead-Acid Batteries for
connected in parallel to increase the capacity of Stationary Applications
the battery bank. • Datasheet’s of major battery manufacturer’s
10-6
© Copyrights Reserved
LIFE EXPECTANCY OF
SMF VRLA BATTERY
100
100
the battery increases.
80
60
Elevated temperature operation will shorten battery 100% DoD 50%DoD 30%DoD
40
life. A general rule of thumb for lead-acid batteries is
that the prolonged use at elevated temperatures will 20
10-7
© Copyrights Reserved
CONSIDERATIONS FOR
BATTERY SIZING
100
90 % RATED CAPACITY
• Design Margin 85
• Ageing Factor 80
• Effects of temperature 10 20 30 40
% Life
50 60 70 80 90 100
10-8
© Copyrights Reserved
TEMPERATURE
CORRECTION
FACTOR FOR
BATTERY SIZING
factor factor
(oF) (oC) (oF) (oC)
77 25.0 1.000
Note --- This table is based on vented lead-acid nominal 1.215 specific gravity. However, it may be used
for vented cells with upto a 1.300 specific gravity. For cells of other designs, refer to the manufacturer.
10-9
© Copyrights Reserved
BATTERY SIZING
CALCULATION FOR
UPS SYSTEMS
Battery Sizing Calculation for UPS System Battery is connected to a DC-DC Converter and the
output of the DC-DC converter is connected as an
The inverter of UPS provides a constant voltage to input to the UPS (refer figure 9)
the loads connected to it. During a battery discharge
the battery supplies constant power to the inverter of In this case, the load on the battery is based on the
the UPS. The DC input voltage to the inverter output load connected to the inverter, the losses of
decreases during the discharge. To maintain a the inverter bridge and also the losses of the
constant power output, the battery discharge current DC-DC Converter,which could increase the
increases accordingly required battery capacity.
VOLTS DC
AMPS DC
Rectifier Inverter
Mains Supply
Output to
15KW
130 130
Critical
125 RES
AMPE 14KW Load
120 120 POWER = V*A
115
110 110 VOLTA 153KW
GE
105
100 100 12KW
95 Battery
90 90 Battery
85
Charger
MINUTES
Figure 9 UPS with DC-DC Charger between the inverter and Battery
Figure 7 Constant Power Discharge Characteristics UPS Efficiency And Power Factor
There are different methods to connect the battery
with the inverter of UPS. Battery can be connected UPS power ratings are quoted in volt-amperes (VA)
directly to input of the inverter (refer Figure 8) and/or watts. The rating in watts is equal to the
rating in volts-amperes multiplied by the power
In this case, the load on the battery is purely based factor.
on the output load connected to the inverter and the
losses of the inverter bridge. UPS output power rating in watts = UPS output in
volts-amperes × power factor
Rectifier Inverter
Mains Supply
10-10
© Copyrights Reserved
BATTERY SIZING
CALCULATION
10-11
© Copyrights Reserved
CONSTANT
BATTERY SIZING POWER
DISCHARGE RATING
CALCULATION
WATTS PER BATTERY
Constant power discharge rating watts per battery @ 27 OC*
DURATION
ECV
10 min 15 min 20 min 30 min 60 min 2 hrs 3 hrs 5 hrs 8 hrs 10 hrs 20 hrs
1.60 3594 2801 2269 1817 1125 680 495 340 225 183 93
1.65 3441 2764 2223 1786 1100 670 483 325 219 181 92
1.70 3288 2727 2177 1755 1075 659 470 318 213 180 92
1.75 3135 2690 2127 1724 1050 649 456 310 210 178 91
1.80 2982 2570 2078 1693 1024 638 442 302 207 177 90
Sample Calculation :
15 mins backup on a 500KVA UPS with an output power factor of 0.9
UPS Rating (KVA) 500KVA Specified by Customer or Consultant
Step 1:
Arrive UPS output power rating in watts = UPS output in volts-amperes × power factor
= 500 X 0.8 KW = 400KW
Step 2:
Arrive the nominal battery load in W
10-12
© Copyrights Reserved
SAMPLE
CALCULATION
Step 3:
Arrive at the adjusted battery power required by taking into consideration design margin,
ageing factor and TCF (Temperature correction factor)
Adjusted nominal battery load in W/Battery = Answer of Step 3 X Design Margin X Ageing Factor X TCF
= 8421.05 X 1 X 1.25 X 1
=10526 W/Battery
As the maximum available AH is 200AH Battery in 12V SMF VRLA battery, we need to parallel multiple
strings of battery to achieve the desired backup time.
Step 5
Watts/Per battery required (Answer of step 4)
No of strings required =
Watts the battery can deliver
(from battery manufacturer datasheet)
A 160AH battery can deliver 3552 W at end cell voltage of 1.75V/Cell for 10 mins
10526 W
= = 2.96 strings = 3 strings
3552W
Hence in this scenario, 3 strings of 160AH battery with 50 battery in each string will provide 10 mins backup
at end cell voltage of 1.75V/Cell.
10-13
© Copyrights Reserved
SELECTION OF
CABLES
Selection Of Cables For this reason, the following rule may be applied:
The cross section of cables depends on: neutral cross section = 2 x phase cross section in
• Permissible temperature rise Sq mm
• Permissible voltage drop
For a given load, each of these parameters results in a Output Cables
minimum permissible cross section. The larger of the
two must be used. To arrive at the cross section of the cable, the
output current needs to be calculated using the
When routing cables, care must be taken to maintain below formula
the required distances between control circuits and
power circuits, to avoid any EMI disturbances caused KVAX1000
by HF currents. Rated Current in A(I) =----------------------
√3 X Vph-ph
Temperature Rise
Permissible temperature rise in cables is limited by using the cable manufacturer’s datasheet and the
the withstanding capacity of cable insulation. conditions linked with routing and bunching of
Temperature rise in cables depends on: cables, the required cable can be selected.
• Type of core (Cu or Al)
• Installation method As thumb rule, we can consider 2A/sq mm to arrive
• Number of touching cables type of cable, the the cross section of the required cables.
maximum permissible current.
Rated Current in A(I)
Voltage Drops Cross Section of Cables in sq mm = --------------------------
The maximum permissible voltage drops are:
• AC circuits (50 or 60 Hz) 2
10-14
© Copyrights Reserved
INPUT, OUTPUT AND
UPS TO BATTERY
CABLES
Input Cables
The cross section of cables required for the input of
Rectifier Input Power in W
the UPS can be derived using the same formula like
Input Power in VA = ---------------------------------------
output cables, but the input power in KVA needs to
Input Power Factor
be derived based on the
VA
• Connected Load
Rated Current in (A) = ----------------------
• Efficiency of the Inverter
3 X Vph-ph
• Battery charging Power
where Vph-ph is the minimum operating Voltage of
• Efficiency of Rectifier
rectifier
• Input power factor of rectifier
• Minimum operating Voltage of Rectifier
10-15
© Copyrights Reserved
CABLE DATASHEET
Derating Factors 1 0.96 0.92 0.88 0.83 0.78 0.75 0.73 0.68 0.62 0.53 0.48 0.3
10-16
© Copyrights Reserved
CABLE DATASHEET
12 3.22 43 30 22 15
10 5.33 61 47 36 25
8 8.76 87 65 49 36
6 13.3 115 87 65 -
10-17
© Copyrights Reserved
SELECTION OF
PROTECTIONS
(CIRCUIT BREAKERS
OR FUSES)
Moulded Case Circuit Breakers are electro mechanical In the first case, the capability strictly
devices, which protect a circuit from Overcurrent and Short depends on the UPS design and in the
Circuit. second case it is based on the i2t
characteristic of the SCR selected in the
Their primary functions are to provide a means either to bypass path or fuse (if present in UPS)
manually open a circuit and automatically open a circuit under
When a short circuit happens on any one
overload or short circuit conditions. The overcurrent, in an
the distribution system on the output of the
electrical circuit, may result from short circuit, overload or faulty
UPS, the current increases significantly. If
design.
the fault is not cleared within milliseconds,
we might risk the uptime of other loads
MCCB is an alternative to a fuse since it does not require
connected to the same UPS as the UPS or
replacement once an overload is detected. Unlike fuse, an
the upstream protection of the UPS will trip
MCCB can be easily reset after a fault and offers improved
resulting in downtime of all the connected
operational safety and convenience without incurring
loads.
operating cost.
10-18
© Copyrights Reserved
SELECTION OF
PROTECTIONS
(CIRCUIT BREAKERS
OR FUSES)
• i2tSCR> i2tMCCB2
MCCB 1 MCCB 2 • i2tMCCB3> i2tMCB6>i2tMCB7
with MCB 7, then we risk to lose all the loads connected to The fault circuit current or the let though
MCB6. energy will purely depend on the impedance
of the transformer.
The let through energy(i t) of MCCB2 is very important. If the
2
let through energy of MCCB 2 is higher than what the SCR The short circuit current of the transformer is
can handle, then the SCR will fail. the ratio of full load current of the transformer
and its impedance. If we have transformer
To protect the loads, SCR and to have the proper with a rated current of 200A and with an
discrimination of short circuit, the following rule has to be impedance of 5%, the short circuit current of
respected transformer will be 4KA.
10-19
© Copyrights Reserved
PROTECTING BATTERY
FROM SHORT CIRCUITS
Short Circuit Protection in Battery Path The following figure shows the curve of the short-
circuit current delivered by a stationary lead-acid
Battery is one of the vital components in an UPS battery; as it can be seen in the figure, after the
system and its main purpose is to provide DC power time, and this is the time necessary to reach the
to the inverter of the UPS when the mains fail and get peak, and the short circuit value decreases to the
charged through the rectifier when the mains return. quasi steady-state short circuit current.
iB
Like any other power source, battery will also
contribute to the fault current when there is fault on the ipB
IK
battery. The main parameters which contribute to
magnitude of the current are battery’s internal
resistance (this depends on plate surface area,
internal plate spacing and electrolyte type) and its tpB t
external circuit resistance. The short circuit current will Figure 12 Curve of Short circuit current in a battery
vary based on the condition and the age of the
battery. The short circuit current of battery can be
calculated by using the Ohms Law(V=IR).
Short Circuit Current of Battery Bank
V
The short circuit current of the battery can be The short circuit of the battery Isc = --------
calculated based on the standard “IEC 61660-1, R
“short circuit currents in DC auxiliary installations in
power plants and substations – part1: Calculation of Where V Open Circuit Voltage of the battery
short circuit currents”. R Internal Resistance of the battery
Protection + - + - + - + - + -
+
isolation
function
10-20
© Copyrights Reserved
CO ORDINATION OF
BATTERY BREAKER
Selection of Battery Breaker Capacity and its Trip Unit As we said earlier, the short circuit current depends
The selection the battery breaker depends on on the voltage and the internal resistance of the
parameters like battery. The internal resistance increases with the
ageing of battery under these conditions and the
Operating Voltage of the Battery Bank: Generally most short circuit current decreases. If this short circuit
of the breakers are designed with an voltage of current is less than the pickup value of the magnetic
250V/Pole and based on the operating voltage of setting of the breaker the principle objective of using
the battery bank, the poles has to be connected in the breaker is defeated as the breaker will not trip.
series to achieve the desired voltage level as shown
in fig.13
R L
10-21
© Copyrights Reserved