Professional Documents
Culture Documents
Theoretical and Practical Considerations in Implementing and Using A Reliability Unit Commitment (RUC) in Restructured Electricity Markets - 2006
Theoretical and Practical Considerations in Implementing and Using A Reliability Unit Commitment (RUC) in Restructured Electricity Markets - 2006
Theoretical and Practical Considerations in Implementing and Using A Reliability Unit Commitment (RUC) in Restructured Electricity Markets - 2006
Panel:
Reliability Unit Commitment
Sponsored by: IEEE PES Power System Analysis, Computing and Economics Committee
It has been widely accepted that in restructured electricity However, there are also differences between the DAM and
markets a Reliability Unit Commitment (RUC) function is the RUC processes. The proposed IFM process is based on
needed to ensure reliability. Specifically, the purpose of RUC bid-in and self scheduled demand, while the proposed RUC
is to ensure that sufficient capacity is available at proper process uses the ISO’s load forecast. The objective function
locations to meet real-time energy and associated ancillary in the DAM is to minimize the overall costs as reflected by
services requirements. Since the scheduled load that clears the start-up, no-load and incremental offer prices, and where
Day-Ahead Market (DAM) and Hour-Head Market (HAM)
relevant, Ancillary Services (A/S) capacity bids. The
may be less than the actual load for a variety of reasons, the
resource committed in the DAM and HAM may not be objective function of the RUC function, in many but not all
sufficient to meet the energy and capacity requirements in cases, is the same as the objective function of the DAM
real-time. Therefore, a RUC function is needed to reserve optimization (with availability payment in lieu of capacity
enough on-line capacity to meet the load forecast obtained in adder). The three-part bids submitted in the DAM will be
DA and the associated operating reserve requirements; while also used in the RUC process. Resources committed in the
the objective of DAM is to procure energy and capacity to DAM will be modeled as “must-run” in RUC, i.e., these
meet the DA scheduled load and the DA ancillary service resources will not be de-committed.
requirements. The objective of the HA RUC is to reserve
enough on-line capacity to meet the load forecast obtained in In some other markets the RUC process minimizes only the
HA; while the objective of HAM is to procure energy and start-up and no-load components for additional commitments.
capacity to meet the HA scheduled load and the HA ancillary This is motivated by the goal of minimizing uplift costs
service. Both the DA RUC and the HA RUC will include resulting from start-up and no-load prices, as well as creating
system-wide as well as locational needs. incentives for market participants to make bids and offers as
accurately as possible in the DAM. However in some
The fundamental methodology for solving the RUC problem regions, this may give an advantage to dispatch of imports
is based on the Security Constrained Unit Commitment (without any start-up and no-load bid component) before
(SCUC) that is also used in clearing the forward markets. dispatch of generators in the ISO region (that do have start-
Both the DAM and the RUC processes are based on a up and no-load bids). If imports selected as reliability
centralized unit commitment optimization that allows multi- reserves are assured payments, regardless of whether the
part offers (with capacity bids, start-up, no-load and energy is truly needed in real time, this bias could result in
incremental energy bids). The RUC optimization considers inefficient market outcomes. Additionally, generators
inter-temporal operational constraints for generators (ramp- selected in the RUC process that are dispatched at their
rates, minimum output, minimum run times, etc.), and minimum block can also contribute to uplift costs because of
incorporates transmission constraints in developing a least- their minimum load cost may exceed the LMP. Ignoring
cost commitment and dispatch for a twenty-four hour period. energy prices completely in the RUC process may not result
(The time horizon may be extended to 5 days or a week.) Both in the lowest possible uplift.
utilize a Full Network Model (FNM) that includes all
The RUC process will procure a combination of energy and
transmission constraints, branch group and nomogram
unloaded capacity. It will procure 100 percent of the capacity
constraints.
needed to meet the ISO’s requirements taking into account