Emergency Evacuation Drill

Location: Project:
CONTRACT
Construction of 16 P S/S PIC-P-7717
NO:
16 P S/S RC YANBU YANBU
DRILL No. 4

Type of Drill Evacuation Drill Oil / Chemical spill Heat Stress


Shade the box as (Fire)
applicable
Other (specify):
Proposed Date 18-04-2022 Proposed Start Time :07:00 AM Proposed Evacuation Time: 4 mins.
Scenario prepared by: Mr. Mudassar (Siemens HSE Manager)
Emergency Evacuation Drill (Fire) Drill Plan Scenario Description:
At around 07:00 am on April 4, 2022, @ Siemens site a worker found a smoke and fire near to the 380kv GIS
Building suddenly approach/informed to the Site Manager and safety officer at Siemens site in which they are
checking the site work.
Note : Planning and review all drills should eliminate all risk of actual injury or incident all communication written
and verbal, should start and end with “this is a drill”
Emergency Evacuation Drill (Fire) Drill Plan will start at 08:00 am and will complete at 08:15 am the time
line event are
the following.
Planned Description of Plan Drill
Time Activity

07:00 AM Safety officer are making his Safety Inspection Reports.


07:00 AM Everything runs smoothly at the Site.
07:05 AM Site Manager, and engineers are visiting the site.
7:05 AM visits runs smoothly discussing their routine works
07:14 AM One Technician observed the smoke and fire besides the manhole 1 while arranging plywood

07:15 AM Safety representative informed to Site manager about the fire.


07:16 AM Manual Alarms are used by the Safety officer and inform the Emergency response Team.
07:16 AM Site Manager suspended the site visit and instructs Safety Supervisor to proceed to Assembly
point areatogether with workers.
07:16 AM Site Manager informed the SIEMENS Project Manager
07:20 AM All Occupants (Worker and Staff) were evacuated
07:25 AM Safety Officer Muhammad Atif assist the evacuee to the assemble assembly point and start to
conductHeadcount.

07:28 AM Upon the arrival of emergency team at location, Fire Fighting team starts extinguished fire on the
affected area
07:50 AM Emergency is declared ALL Clear through Fire Warden advised
08:00 AM Site manager inform the workforce to report at the Site to resume work.