Project Punch List: A Pump House
Project Punch List: A Pump House
In Progress,
Buat schedule commissioning
2 A prosedure pompa air
Elect./Mech. eng 24-May-22 50% addi. job install 1 ea new valve 2"
Pasang Label & tag pada pipa air ( Mech. Eng & Cs
3 B untuk gate valve pakai label nomor ) team
Next week 100% Done
D Ramp Check :
5 May 2022
Pasang baricade/guard bagian depan 2
8 B line, material channel 150
Civ. Eng & CS team (Dwg/skets by 0%
Civ. Eng)
Cut bundwall exist. jadi 10 cm & Done,
9 B rapikan (grinding)
Cs team 27-May-2022 100%
actual 12 mm
E Water Tank :
25 May 2022
in Progress,
22 A Fabrikasi & pasang stopper dari CS pipe Civ. Eng & CS team (Dwg/skets by 40%
Fabrikasi only (75%)
Civ. Eng)
H Oil Trap
26 B Fabrikasi & pasang cover grating oil trap Civ. Eng & CS team 27-May-2022 100% Done
In Progress, Pipa hdpe yang
Pasang 6" pipa HDPE untuk
27 B pembuangan air oil trap ke drainage
Tba 40% terpasang tidak sesuai design (perlu
re-work)
*) PRIORITY A. High (must be compeleted for commissioning) B. Medium (must be completed for start-up) C. Normal (must be completed before hand over)
Distribution List: 1). Original: Project Team (CM,PM,PE, Ewr file) 2. Copy : Contractor 3. CAR File ( for capital project only)