Draft - General Terms and Conditions
Draft - General Terms and Conditions
1. SCOPE OF WORK
The Sub- Contractor’s scope of work under this contract shall include all as detailed in the Bill of
Quantities enclosed along with this order agreement.
3. CONTRACT VALUE
The Contract value as mutually agreed is INR /- (Indian only).
The above mentioned contract value is excluding of taxes, duties, levies as applicable. (The agreed rates
shall be firm and binding on you for the entire duration of contract including any extensions of time as
granted by the Main Contractor, and no subsequent claim for extra or escalation whatsoever will be
allowed.
Note: The item wise rate break-up has been attached here with. The Quantities given in the BOQ are
tentative & the scope of work may increase or reduce as per the sub- Contractor’s performance. The
authority to allot work to sub- Contractor lies with the project manager.
4. TYPE OF CONTRACT
This is purely an Item Rate Contract, and the payments shall be made for the works actually executed,
measured and certified by the SPCPL authorised Engineer. The contract price is inclusive of all Labour,
tools & tackles, consumables, chemicals, equipment to complete the work within the agreed time frame
under this contract with instruction.
5. SPECIFICATIONS
All work shall be executed in conformity with the specifications mentioned in the BOQ and Design
Drawings issued, which form part of the contract.
6. MOBILISATION ADVANCE:
NA
7. SCHEDULE OF DATE
P a ge |1
a. Date of Commencement of Work :
b. Date of Completion :
Time is the essence of this contract. The scope of the works covered under this contract shall be
completed within the specified timelines and handed over.
So the total duration of this work order is 2 months from Commencement of works.
8. TERMS OF PAYMENT
20% with GST within seven days from the date of shell plan approval
70% with GST within 15 days after receipt of material at site.
Balance 10% with GST after two pour or 45 days whichever is earlier.
1) Contract Agreement / WO
2) Priced Bill of quantities/ Schedule of quantities.
3) Approved Drawings.
1. No idling charges whatsoever will be entertained. Sub- Contractor shall ensure that the work
proceeds with prior planning and without any hurdles.
2. No Escalation shall be entertained on any items of contract till the date of the completion of
the project. (Limited to quantum of this work order.)
16. TERMINATION
The Main Sub- Contractor reserves the right to terminate/alter the contract with a prior intimation to
you. In which case the Main Sub- Contractor shall not be liable pay any sort of damages including
foreclosure damages which may be incurred by you. Such termination and/or alteration will be
indicated to you at the outset of 30days in writing and if no improvements/changes indicating
progress are noted, the same will result in termination.
P a ge |3
All disputes and difference of any kind whatsoever arising out of or in connection with this Contract
whether during the progress of the work or after their completion shall be settled mutually.
For any of the disputes courts of Mumbai shall have the exclusive Jurisdiction.
P a ge |4