Main Plant Operational Procedure - Heaters, Drains and Vents System
Main Plant Operational Procedure - Heaters, Drains and Vents System
2. Precautions: All site safety and health manuals shall be followed during operation of unit
only.
TRUE FALSE
ANSWER: FALSE
3. Precautions: A through Job Safety Briefing (JSB) shall be completed after beginning of work.
TRUE FALSE
ANSWER: FALSE
4. Pre-Start: VERIFY Plant Drains Flash Tank has ___ to support start-up of the Heaters,
Drains, and Vent System.
8. Start-up: RECORD system operational data per Operator Rounds before system readings have
stabilized.
TRUE FALSE
ANSWER: FALSE
9. Shutdown: VERIFY Heaters, Drains and Vent System can’t be removed from service.
TRUE FALSE
ANSWER: FALSE
10. General Knowledge: During unit start-up Heaters are to be ON-SERVICE during.