Professional Documents
Culture Documents
EOL-Engg-M-001 - R1 - Tank Product Pipeline Hydro Testing Doping and Installation
EOL-Engg-M-001 - R1 - Tank Product Pipeline Hydro Testing Doping and Installation
TABLE OF CONTENTS
Page 2 of 7
Nayara Energy Limited CEP - Hydro Testing , Doping & Installation of Tank & Pipeline
Marketing Department EOL-Engg-M-001_R1
Retail Division
Rev. 1 – 9th June, 2020
A portion in tank without paint is like cancerous part of the human body. It will spread exponentially when
it will be earthen without doing Doping. Rusting and hence damage in larger part of tank will take place the tank
within 2-3 years and will make way to leakage.
1.2 REFERENCES
1.2.1 GENERAL REQUIREMENT
All the service work will comply with project manual for construction of a retail outlet.
1.2.2 STANDARD REQUIREMENT
Tank fabrication shall conform IS 10987.1992: Practice for Design, Fabrication, Testing & Installation of
under-ground / above-ground horizontal Cylindrical Steel Storage Tanks for Petroleum Products.
1.2.3 PROJECT REFERENCE DRAWINGS
Reference Project Doc Number Description Rev
EOL-M/STD/M/CCOE/002 MS Tank Design (15 KL Capacity) 0
EOL-M/STD/M/CCOE/003 MS Tank Design (20 KL Capacity) 0
EOL-M/STD/M/CCOE/007 MS Tank Design (25 KL Capacity) 1
EOL-M/STD/M/CCOE/004 MS Tank Design (30 KL Capacity) 0
EOL-M/STD/M/CCOE/005 MS Tank Design (40 KL Capacity) 0
With this knowledge, the following work method will be the basic steps taken to complete installation of MS Tank
with interconnecting infrastructure post hydro testing and water proofing process.
Page 3 of 7
Nayara Energy Limited CEP - Hydro Testing , Doping & Installation of Tank & Pipeline
Marketing Department EOL-Engg-M-001_R1
Retail Division
Rev. 1 – 9th June, 2020
5. Hydro test to be carried out preferably in the early morning or afternoon hours. Constant pressure of 0.5
kg/cm2 has to be kept and observed for one hour.
6. Pressure gauges used for testing must have valid calibration certificate with traceability. PG should be of the
range 0-1 Kg/cm2 with least count of 0.1 kg/cm2. Once desired pressure attained then please mark the position
of the pointer with marker pen on the glass of the PG.
7. If any pressure drop found during this process, leakage points has to identified and rectified as per procedure
with the help of tank vendor immediately. For leakages observed through weld joints, tank has to be returned
back to vendor with REJECTED stamp.
8. Hydro testing process has to be repeated again after attending the leakages through flange/threaded joints.
9. If there is no any pressure drops during an observation period of one hour, release the water pressure
and empty the tank.
10. MS Tank has to be cleaned thoroughly with the help of dry cloth from inside after hydro testing process.
2.3.1 Surface Preparation: - The surface should be thoroughly cleaned to remove loose dust, foreign particles, rust,
laitance, oil and other contaminants.
2.3.2 Application: - Apply primer (min. thickness of 60 micron) using Brush or Spray Gun in two coats. Never apply
primer on Wet Surface or when it is raining. Allow the primer to dry completely and then proceed for application
of anti-corrosive bituminous paint.
Each container should be agitated for at least 3 minutes with a mechanical mixer in order to produce a
homogenous solution before application of anti-corrosive bituminous paint. Anti -corrosive bituminous paint is
cold, applied by using steel plate in two - three layers with thickness in each layer between 1-1.5mm max., to
achieve 3 mm thickness. Each new layer is applied in a criss-cross pattern with respect to the previous one, when
the latter is dry, in order to avoid solvent vapour inclusion between the layers. For the same reason one thick layer
should be avoided.
Page 4 of 7
Nayara Energy Limited CEP - Hydro Testing , Doping & Installation of Tank & Pipeline
Marketing Department EOL-Engg-M-001_R1
Retail Division
Rev. 1 – 9th June, 2020
Coating needs to be started from the base of the Tank so after emptying the tank, it can be rolled such that
manhole touches the ground. Put gunny bags as wedges for support to tank.
Please apply first Coat of Shalimar Tar Plastic Paint to 1/3rd of the Tank bottom area and allow it to dry for
sufficient time. Once the Paint is dried then apply second coat of the Paint and allow it to dry.
Application of the Paint to be done uniformly using Steel Plate from top to bottom so that the thickness of 3
mm Paint is available on the entire Tank body. Once the bottom coating is done please ensure gunny bag cushion
is provided while rolling back for other side coating and then back to straight upright position to avoid damage to
the coating. Take photographs of this painted area from all sides.
Once the Painting is done please check the thickness of the Paint by either removing 50mmx50mm area or
measuring the same with tape or with Elcometer without removing any Painted part. If the thickness is found
sufficient then Paint the area from where the sample was extracted. . If found sufficient, allow the Paint to dry.
Please ensure that the Tank pit area is cleaned and ladder is available for the skilled Manpower to go inside
the Pit. In case the Earth Pit wall needs to be made, please ensure it is of max. 1.2 mtr height only. Tank should be
lifted with Crane having Proper sling and hook and to be kept inside the Tank Pit. Use gunny bags to avoid scratches
to painted portion while tank is being lifted from current position with crane. Tank should be properly levelled,
aligned with the help of water level so that the Tank is straight and upright inside the Pit and Manhole cover is in
the Centre of the Tank.
Tank should be anchored properly from both the sides. Now fill the sand in alternate layers (of height not
more than 300mm) along the length of the tank. Sand back filling can be done upto the height of the earlier painted
bottom portion, leaving 50mm painted portion. Now paint the other balance and top portion of the tank as
explained above.
In case of rainy season please fill the Tank with water once it is placed properly inside the Pit so that the Tank
should not float if the Painting work is taking long time during the rains. Painting of the balance area of the Tank to
be done as per the process followed earlier. Once all the Painting work is completed please check the thickness of
the Paint again. If found sufficient, allow the Paint to dry. The ideal setting time for drying 3mm thick tar plastic is
72 hours (minimum).
Once the Painting is completely done as per process and verified that required thickness is available the start
filling the sand next to the Tanks in alternate layers to avoid differential Pressure on the wall from both the sides
simultaneously till the top of the Tank.
Take photographs of the painted portion of the tank inside the pit from all sides of the tank. Also take the count
and photographs of the emptied cans/drums of primer and paint to ensure the consumption of entire estimated
quantity of STP as per trailing table.
Requirement of STP
Sr. Tank Surface
No. Tank Capacity Approximate Qty of paint required (Kg) Area (Sq.M.)
1. 15 KL 130 41.01
2. 20 KL 160 50.57
3. 25 KL 180 56.97
4. 30 KL 195 63.34
5. 40 KL 235 72.39
Add 1-2 boxes in above quantity for suction, fill and vent pipeline coating.
1. Ensure brick wall thickness 600 mm wherever future plan of adjacent tank installation, to avoid existing wall
collapse after excavation in future (Existing Tank May Tilt)
2. Ensure the burry depth is minimum 900 mm, but calculate this depth based on the pipe length, slope, fittings,
and manhole height and observe whichever is more.
3. Ensure that the front and back ends of MS Tank are at the same level and the central dip hatch is vertically up
100%, after lowering the tank.
4. After straightening the tank, the tank should be fastened/ tightened with turn buckle.
5. Remaining portion doping to be done by Tiki tar plastic or Shalimastic Anti Corrosive doping in the pit.
Page 5 of 7
Nayara Energy Limited CEP - Hydro Testing , Doping & Installation of Tank & Pipeline
Marketing Department EOL-Engg-M-001_R1
Retail Division
Rev. 1 – 9th June, 2020
6. Again tank inside should be cleaned with the help of dry clothes.
7. Use the new gaskets (CAF) for manhole and all flanges. Old gaskets will be wasted, once in contact with water.
CAF gasket should be fire fly or Champion make or approved brand.
8. The tank pit shall be back filled from inside and outside simultaneously to avoid differential pressure on the
wall.
2.5 PERMITS
Prepare work permit to carry out lifting work and confined space working as and when required. These permits
will be reviewed as conditions change and work type progresses from initial construction to cleaning, painting,
testing and commissioning.
DIVISIONAL ENGINEER
1. Shall be responsible for supervising in coordination with Tank Vendor to ensure that all project design
specifications and standards are met.
2. Shall inspect all incoming materials for installation at site to ensure that all materials are in good condition.
3. Shall be responsible for arranging required materials for installation of MS Tanks.
4. Shall be responsible for monitoring all safety aspect during execution.
5. Shall be responsible for organizing necessary inspection and prepare documentation.
4.3 MATERIAL
1. Primer
2. Bituminous anti corrosive paint
Page 6 of 7
Nayara Energy Limited CEP - Hydro Testing , Doping & Installation of Tank & Pipeline
Marketing Department EOL-Engg-M-001_R1
Retail Division
Rev. 1 – 9th June, 2020
7.0 ATTACHMENT
Appendix A : Construction Manual
Appendix B : Drawing & BOM – MS Tank (15 KL Capacity)
Appendix C : Drawing & BOM – MS Tank (20 KL Capacity)
Appendix D : Drawing & BOM – MS Tank (25 KL Capacity)
Appendix E : Drawing & BOM – MS Tank (30 KL Capacity)
Appendix F : Drawing & BOM – MS Tank (40 KL Capacity)
Appendix G : Hydro Testing Report format to be filled at Retail Outlet.
Page 7 of 7
Annexure G
Date of Inspection
LR No.
Factory Hydro test report and photograph with TPI Report with photographs
witness
Packing list of fittings Packing List
Thickness
Neck Length
Suction Pipes (50 NB) 4 no's - 100 mm above the bottom of tank.
Dip pipe & dip pipe nozzle (50 NB) 1 No- with perforatations
Remark: