Download as pps, pdf, or txt
Download as pps, pdf, or txt
You are on page 1of 9

PTD Energy Management & Information Systems

FERC TC: Information Technology


for Reliability & Markets
ISO-RTO Standards Collaborative July 14, 2004
J. Waight
Security Constrained Unit Commitment

Objectives:
Specify Interfaces to Security Constrained Unit Commitment
(SCUC)
 Continuation of EPRI CME project
1stProject to demonstrate methods of ISO-RTO Standards
Collaborative
Desired Result is that SCUC may be considered as a black box
with standard input and output interfaces
Desired Result is that ISO-RTOs can procure SCUC as a
component, from any vendor, and run multiple SCUC in parallel
ISO-RTOs can integrate SCUC into a Market Operations
System using a standard interface, at reduced cost

Siemens Power Transmission & Distribution, Inc.


Energy Management & Information Systems Division

07-14-2004 2
Process for Creation of Standard Interfaces

Each Vendor contributed its SCUC requirements


 Data Input Requirements and Descriptions
 Data Output Provided by SCUC and Description
 ISO-RTOs review Input/Output requirements
 Create
a profile of data required to support features of Market
 Commonality due to SMD
 Review of existing Common Information Model
 IEC standard 61970 part 301
 Search for existing models that can be reused
 Extension of CIM to add Market Features
 Workshop approach
 Development of a set of tools to automate creation of message
schemas
 Use of tools to create message schemas

Siemens Power Transmission & Distribution, Inc.


Energy Management & Information Systems Division

07-14-2004 3
Tools for Creation of Standard Interfaces

Model Driven Architecture


 Platform Independent Model maintained in UML
 Rational Rose
 Intermediate Model
 RDF/Schema
 Platform Specific Model
 W3C XML Schema
 XPETAL as tool for transformation
 Public Domain

Siemens Power Transmission & Distribution, Inc.


Energy Management & Information Systems Division

07-14-2004 4
Message Framework for SCUC
Input Messages Output Message
Market Input Message (Bids) Schedules
 Generation Bid Prices
 Load Bid
Errors & Warnings
 Transaction Bid
Solution Notes
 Network Model Input
 NERC CPSM profile
 Standing Input Message
 RTO Product Definition
 Market Definition
 Market Participant Registration Control Messages
 System Requirement Schemas
 Load Forecast Fetch
 Generation Initial Conditions
Execute
 Security Analysis Input Message
 Outages
 Contingencies
 Limits
 etc

Siemens Power Transmission & Distribution, Inc.


Energy Management & Information Systems Division

07-14-2004 5
Results to date

First
Project to Demonstrate ISO-RTO Standards Collaborative
Three workshops attended by
 ISO-RTOs, Vendors, and Consultants
Repeatable Process, Methodology, and Tools for Developing
Interface Standards
Model Extensions to the Common Information Model (CIM) to
support SCUC
Development of Message Sequence Diagram
Development of XML schemas to define messages
Planning for pilot project to validate schemas
Achieved in three month schedule

Siemens Power Transmission & Distribution, Inc.


Energy Management & Information Systems Division

07-14-2004 6
Questions ???

Siemens Power Transmission & Distribution, Inc.


Energy Management & Information Systems Division

07-14-2004 7
Backup: Message Sequence Diagram

Market SCUC
User
System (ID#)

EXECUTE
EXECUTE (ID1,ID2,ID3,ID4, ID5)
FETCH (ID1)
Network (ID1)
FETCH (ID2)
Standing (ID2)
FETCH (ID3)
Market (ID3)

FETCH (ID3)
Market (ID3)

FETCH (ID4)
Security Analysis (ID4)
FETCH (ID5)
System Requirements (ID5)
Results (ID1,X,ID3,ID4, ID5)

FETCH (X)
Standing (X)
DISPLAY

Siemens Power Transmission & Distribution, Inc.


Energy Management & Information Systems Division

07-14-2004 8
Backup: Model Driven Architecture Cascaded Pattern

Siemens Power Transmission & Distribution, Inc.


Energy Management & Information Systems Division

07-14-2004 9

You might also like