Professional Documents
Culture Documents
Project Management Homework N°12
Project Management Homework N°12
Management of project
Prepared by
Group 02
2019/2020
Introduction :
Project management is defined as the process of utilizing resources to get the
job done properly confirming specified time and cost, completing the definite
project with limited resource and cost is very difficult.
So as part of this work we will see how we can manage the project in terms of
time in both cases (uncertainty and certainty).
K (4)
L (5)
I(7)
1
2/ The total time of the project is determine by the longest critical path which
is consiste of a sum of critical activities (that it has slack = 0)
16 D 22 22 G 29 29 H 38 38 M 40
4 4 4 4
20 6 26 26 7 33 33 9 42 42 2 44
33 K 37
1
34 4 38
0 A 2 2 B 6 6 C 16 16 E 20 20 F 25 25 J 33 38 N 44
0 0 0 0 0 0 0
0 2 2 2 4 6 6 10 16 16 4 20 20 5 25 25 8 33 38 6 44
33 L 38
ES ID EF 16 I 23 0
SL 2 33 5 38
LS DU LF 18 7 25
SL : slack = LF – EF
Method of calculation :
2
Activity Early Early Late Late 3/ Activity with one predecessor
start finish start finish
the ES=EF of predecessor activity
A 0 2 0 2
ex : ES(B)=EF(A)=2
B 2 6 2 6
C 6 16 6 16 4/ Activity with more predecessor
D 16 22 20 26
The ES=Max (EF of all predecessor
E 16 20 16 20 activities)
F 20 25 20 25
G 22 29 26 33 ex : ES(N)=Max (37 ; 38)=38
H 29 38 33 42 5/ Activity without successor the
I 16 23 18 25 LF=time of completion ex : LF of
J 25 33 25 33 activity M and N = 44
K 33 37 34 38
6/LS=LF-duration
L 33 38 33 38
M 38 40 42 44 ex: LS(D)=26-6=20
N 38 44 38 44
8/ Activity with more than one successor the LF=Min (LS of all successor
activity) ex : LF(J)=Min (33 ; 34)=33
4/ Critical activities are those if they are delayed will delay completion of the
project. (Slack=0)
So from the second figure we can see that the critical activities
Are : A-B-C-E-F-J-L-N
3
5/ the delays tolerated for other activities :
We can calculate the delays like that : the late start for each activity minus the
early start.
For the other activities : D=4 ; G=4 ; H=4 ; K=1 ; M=4 ; I=2
Comment : we notice that each time the duration increases ; the probability of
completing the project will increase also.
Here the opposite when the duration decrease ; the probability decrease also.
4
The diagram above shows the probability that the project has been completed
at different times.
Now we will see how to accelerate the project by crashing activities in the
critical paths
We have 2 activities in the critical path more than 7 weeks C and J and each
activity can be reduced by 2 weeks as written in the question :
5
Time 43 weeks D G H M
additional cost 30000$ 6 7 9 2
critical path A-B-C-E-F-J-L-N
K
4
A B C E F J N
2 4 9 4 5 8 6
L
activities changed I 5
C 30000$ 7
Time 42 weeks D G H M
additional cost 60000$ 6 7 9 2
critical path A-B-C-E-F-J-L-N
K
4
A B C E F J N
2 4 8X 4 5 8 6
L
activities changed I 5
C 30000$ 7
Time 41 weeks D G H M
additional cost 90000$ 6 7 9 2
critical path A-B-C-E-F-J-L-N
K
4
A B C E F J N
2 4 8X 4 5 7 6
L
activities changed I 5
J 30000$ 7
Time 40 weeks D G H M
add cost 120000$ 6 7 9 2
critical path A-B-C-E-F-J-L-N
K
4
A B C E F J N
2 4 8X 4 5 6X 6
L
activities changed I 5
J 30000$ 7
6
Conclusion :
It can be seen that the expected completion time is 44 weeks and we can
expedite the project by reducing the expected project duration from 44 weeks
to 40 weeks, by crashing activities C and J.
The additional cost for crashing activities C and J and to complete the project
by 40 weeks is 120000$.
This makes us get a reward of 150000$ and the net profit of reducing the
project to 40 weeks becomes as follows : 150000$-120000$=30000$.