Scheduling/Leveling Report - 2022-08-07 10:32:41 - PM.

EXE
=========================================================

Default Project..................................................MBS
Use scheduling options from......................................MBS

Projects:

MBS............................................................Construction
of Grain Storage Facilites

Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retained
Logic
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish Float
Calculate float based on finish date of .........................Each project
Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar

Advanced
--------
Calculate multiple float paths...................................No

Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................174
# Not Started....................................................174
# In Progress....................................................0
# Completed......................................................0
# Relationships..................................................144
# Activities with Constraint.....................................0

Errors:
-------
Warnings:
---------
Activities without predecessors..................................30
Project: MBS Activity: SL1000 Project Start
Project: MBS Activity: SL2580 Driven piles layout &
excavation
Project: MBS Activity: SL2920 Driven piles layout &
excavation
Project: MBS Activity: SL3260 Driven piles layout &
excavation
Project: MBS Activity: SL3600 Pit layout & excavation
Project: MBS Activity: SL3610 Pit pile hacking
Project: MBS Activity: SL3620 Concrete topping of 100mm
thick C15 concrete cushion @ pit bottom
Project: MBS Activity: SL3630 Concrete topping of 20mm
thick 1:2:5 cement mortar leveling layer @ pit bottom
Project: MBS Activity: SL3640 Application of 2mm thick
polyurethane waterproofing coating @ pit bottom
Project: MBS Activity: SL3650 Concrete topping of 50mm
thick C20 fine stone concrete protective layer @ pit bottom
Project: MBS Activity: SL3660 Pit installation of rebars
Project: MBS Activity: SL3670 Pit installation of formworks
Project: MBS Activity: SL3680 Installation of steel channel
@ pit bottom
Project: MBS Activity: SL3690 Pit concrete pouring (self
waterproof concrete)
Project: MBS Activity: SL3700 Pit concrete topping of 20mm
thick 1:2 cement mortar ( mixed with 10% water repellent mortar )
Project: MBS Activity: SL3710 Pit installation of rebars
Project: MBS Activity: SL3720 Pit installation of formworks
Project: MBS Activity: SL3730 Pit installation of iron
ladder
Project: MBS Activity: SL3740 Pit concrete pouring (self
waterproof concrete)
Project: MBS Activity: SL3750 Concrete topping of 20mm
thick 1:2:5 cement mortar leveling layer @ side wall
Project: MBS Activity: SL3760 Application of 2mm thick
polyurethane waterproofing coating @ side wall
Project: MBS Activity: SL3770 Concrete topping of 20mm
thick 1:2:5 cement protective leveling layer @ side wall
Project: MBS Activity: SL3780 Pit backfilling & compaction
Project: MBS Activity: SL3790 Suspended girders/beams
scaffolding installation
Project: MBS Activity: SL3800 Suspended girders/beams
bottom formworks installation
Project: MBS Activity: SL3810 Suspended girders/beam rebars
installation
Project: MBS Activity: SL3820 Top slab scaffolding support
installation
Project: MBS Activity: SL3830 Top slab formworks
installation
Project: MBS Activity: SL3840 Top slab rebars installation
Project: MBS Activity: SL3850 Top slab concrete pouring

Activities without successors....................................36


Project: MBS Activity: SL1010 Finish of Silo 1
Project: MBS Activity: SL1020 Finish of Silo 2
Project: MBS Activity: SL1030 Finish of Silo 3
Project: MBS Activity: SL1040 Finish of Silo 4
Project: MBS Activity: SL1050 Project Finish
Project: MBS Activity: SL1090 Material Procurement
Project: MBS Activity: SL1100 Temporary Facilities
Project: MBS Activity: SL1420 CIP wall installation of
guard rail
Project: MBS Activity: SL2910 CIP wall installation of
guard rail
Project: MBS Activity: SL3250 CIP wall installation of
guard rail
Project: MBS Activity: SL3590 CIP wall installation of
guard rail
Project: MBS Activity: SL3600 Pit layout & excavation
Project: MBS Activity: SL3610 Pit pile hacking
Project: MBS Activity: SL3620 Concrete topping of 100mm
thick C15 concrete cushion @ pit bottom
Project: MBS Activity: SL3630 Concrete topping of 20mm
thick 1:2:5 cement mortar leveling layer @ pit bottom
Project: MBS Activity: SL3640 Application of 2mm thick
polyurethane waterproofing coating @ pit bottom
Project: MBS Activity: SL3650 Concrete topping of 50mm
thick C20 fine stone concrete protective layer @ pit bottom
Project: MBS Activity: SL3660 Pit installation of rebars
Project: MBS Activity: SL3670 Pit installation of formworks
Project: MBS Activity: SL3680 Installation of steel channel
@ pit bottom
Project: MBS Activity: SL3690 Pit concrete pouring (self
waterproof concrete)
Project: MBS Activity: SL3700 Pit concrete topping of 20mm
thick 1:2 cement mortar ( mixed with 10% water repellent mortar )
Project: MBS Activity: SL3710 Pit installation of rebars
Project: MBS Activity: SL3720 Pit installation of formworks
Project: MBS Activity: SL3730 Pit installation of iron
ladder
Project: MBS Activity: SL3740 Pit concrete pouring (self
waterproof concrete)
Project: MBS Activity: SL3750 Concrete topping of 20mm
thick 1:2:5 cement mortar leveling layer @ side wall
Project: MBS Activity: SL3760 Application of 2mm thick
polyurethane waterproofing coating @ side wall
Project: MBS Activity: SL3770 Concrete topping of 20mm
thick 1:2:5 cement protective leveling layer @ side wall
Project: MBS Activity: SL3780 Pit backfilling & compaction
Project: MBS Activity: SL3790 Suspended girders/beams
scaffolding installation
Project: MBS Activity: SL3800 Suspended girders/beams
bottom formworks installation
Project: MBS Activity: SL3810 Suspended girders/beam rebars
installation
Project: MBS Activity: SL3820 Top slab scaffolding support
installation
Project: MBS Activity: SL3830 Top slab formworks
installation
Project: MBS Activity: SL3840 Top slab rebars installation

Out-of-sequence activities.......................................0

Activities with Actual Dates > Data Date.........................0

Milestone Activities with invalid relationships..................1


Project: MBS Activity: SL1000 Project Start

Finish milestone and predecessors have different calendars.......0

Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................174
# Relationships with other projects..............................0
Data Date........................................................01-Aug-22
Earliest Early Start Date........................................01-Aug-22
Latest Early Finish Date.........................................18-Jul-26
Exceptions:
-----------
Critical Activities..............................................102
Project: MBS Activity: SL1020 Finish of Silo 2
Project: MBS Activity: SL1030 Finish of Silo 3
Project: MBS Activity: SL1040 Finish of Silo 4
Project: MBS Activity: SL2580 Driven piles layout &
excavation
Project: MBS Activity: SL2590 Driven piles pile hacking
Project: MBS Activity: SL2600 Driven piles lean concrete
pouring
Project: MBS Activity: SL2610 Pile cap bottom bars
installation
Project: MBS Activity: SL2620 Pile cap column starter bars
installation
Project: MBS Activity: SL2630 Pile cap top bars
installation
Project: MBS Activity: SL2640 Pile cap formworks
installation
Project: MBS Activity: SL2650 Pile cap concrete pouring
Project: MBS Activity: SL2660 Footing tie beam rebars
installation
Project: MBS Activity: SL2670 Footing tie beam formworks
installation
Project: MBS Activity: SL2680 Footing tie beam concrete
pouring
Project: MBS Activity: SL2690 Column rebars installation
Project: MBS Activity: SL2700 Column formworks installation
Project: MBS Activity: SL2710 Column concrete pouring
Project: MBS Activity: SL2720 Slab-on grade backfilling &
compaction
Project: MBS Activity: SL2730 Slab-on grade gravel bedding
Project: MBS Activity: SL2740 Slab-on grade installation of
rebars
Project: MBS Activity: SL2750 Slab-on grade installation of
formworks
Project: MBS Activity: SL2760 Slab-on grade concrete
pouring
Project: MBS Activity: SL2770 Suspended girders/beams
scaffolding installation
Project: MBS Activity: SL2780 Suspended girders/beams
bottom formworks installation
Project: MBS Activity: SL2790 Suspended girders/beam rebars
installation
Project: MBS Activity: SL2800 Suspended girders/beam
formworks installation
Project: MBS Activity: SL2810 Suspended slab scaffolding
support installation
Project: MBS Activity: SL2820 Suspended slab formworks
installation
Project: MBS Activity: SL2830 Suspended slab rebars
installation
Project: MBS Activity: SL2840 Suspended slab concrete
pouring
Project: MBS Activity: SL2850 CIP wall rebars installation
Project: MBS Activity: SL2860 CIP wall formworks
installation
Project: MBS Activity: SL2870 CIP wall concrete pouring
Project: MBS Activity: SL2880 Installation of bricks
Project: MBS Activity: SL2890 Installation of MU slag
hollow block, M7.5 cement mortar
Project: MBS Activity: SL2900 Concrete pouring with 10@200
rebar wire mesh
Project: MBS Activity: SL2920 Driven piles layout &
excavation
Project: MBS Activity: SL2930 Driven piles pile hacking
Project: MBS Activity: SL2940 Driven piles lean concrete
pouring
Project: MBS Activity: SL2950 Pile cap bottom bars
installation
Project: MBS Activity: SL2960 Pile cap column starter bars
installation
Project: MBS Activity: SL2970 Pile cap top bars
installation
Project: MBS Activity: SL2980 Pile cap formworks
installation
Project: MBS Activity: SL2990 Pile cap concrete pouring
Project: MBS Activity: SL3000 Footing tie beam rebars
installation
Project: MBS Activity: SL3010 Footing tie beam formworks
installation
Project: MBS Activity: SL3020 Footing tie beam concrete
pouring
Project: MBS Activity: SL3030 Column rebars installation
Project: MBS Activity: SL3040 Column formworks installation
Project: MBS Activity: SL3050 Column concrete pouring
Project: MBS Activity: SL3060 Slab-on grade backfilling &
compaction
Project: MBS Activity: SL3070 Slab-on grade gravel bedding
Project: MBS Activity: SL3080 Slab-on grade installation of
rebars
Project: MBS Activity: SL3090 Slab-on grade installation of
formworks
Project: MBS Activity: SL3100 Slab-on grade concrete
pouring
Project: MBS Activity: SL3110 Suspended girders/beams
scaffolding installation
Project: MBS Activity: SL3120 Suspended girders/beams
bottom formworks installation
Project: MBS Activity: SL3130 Suspended girders/beam rebars
installation
Project: MBS Activity: SL3140 Suspended girders/beam
formworks installation
Project: MBS Activity: SL3150 Suspended slab scaffolding
support installation
Project: MBS Activity: SL3160 Suspended slab formworks
installation
Project: MBS Activity: SL3170 Suspended slab rebars
installation
Project: MBS Activity: SL3180 Suspended slab concrete
pouring
Project: MBS Activity: SL3190 CIP wall rebars installation
Project: MBS Activity: SL3200 CIP wall formworks
installation
Project: MBS Activity: SL3210 CIP wall concrete pouring
Project: MBS Activity: SL3220 Installation of bricks
Project: MBS Activity: SL3230 Installation of MU slag
hollow block, M7.5 cement mortar
Project: MBS Activity: SL3240 Concrete pouring with 10@200
rebar wire mesh
Project: MBS Activity: SL3260 Driven piles layout &
excavation
Project: MBS Activity: SL3270 Driven piles pile hacking
Project: MBS Activity: SL3280 Driven piles lean concrete
pouring
Project: MBS Activity: SL3290 Pile cap bottom bars
installation
Project: MBS Activity: SL3300 Pile cap column starter bars
installation
Project: MBS Activity: SL3310 Pile cap top bars
installation
Project: MBS Activity: SL3320 Pile cap formworks
installation
Project: MBS Activity: SL3330 Pile cap concrete pouring
Project: MBS Activity: SL3340 Footing tie beam rebars
installation
Project: MBS Activity: SL3350 Footing tie beam formworks
installation
Project: MBS Activity: SL3360 Footing tie beam concrete
pouring
Project: MBS Activity: SL3370 Column rebars installation
Project: MBS Activity: SL3380 Column formworks installation
Project: MBS Activity: SL3390 Column concrete pouring
Project: MBS Activity: SL3400 Slab-on grade backfilling &
compaction
Project: MBS Activity: SL3410 Slab-on grade gravel bedding
Project: MBS Activity: SL3420 Slab-on grade installation of
rebars
Project: MBS Activity: SL3430 Slab-on grade installation of
formworks
Project: MBS Activity: SL3440 Slab-on grade concrete
pouring
Project: MBS Activity: SL3450 Suspended girders/beams
scaffolding installation
Project: MBS Activity: SL3460 Suspended girders/beams
bottom formworks installation
Project: MBS Activity: SL3470 Suspended girders/beam rebars
installation
Project: MBS Activity: SL3480 Suspended girders/beam
formworks installation
Project: MBS Activity: SL3490 Suspended slab scaffolding
support installation
Project: MBS Activity: SL3500 Suspended slab formworks
installation
Project: MBS Activity: SL3510 Suspended slab rebars
installation
Project: MBS Activity: SL3520 Suspended slab concrete
pouring
Project: MBS Activity: SL3530 CIP wall rebars installation
Project: MBS Activity: SL3540 CIP wall formworks
installation
Project: MBS Activity: SL3550 CIP wall concrete pouring
Project: MBS Activity: SL3560 Installation of bricks
Project: MBS Activity: SL3570 Installation of MU slag
hollow block, M7.5 cement mortar
Project: MBS Activity: SL3580 Concrete pouring with 10@200
rebar wire mesh

Activities with unsatisfied constraints..........................0

Activities with unsatisfied relationships........................0

Activities with external dates...................................0