Saudi Aramco Typical Inspection Plan: LEAK TESTING (Per SAES-A-004) 15-Nov-17

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 10

SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.

00 30-Jun-16

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

LEAK TESTING (per SAES-A-004) SATIP-A-004-05 15-Nov-17 MECHANICAL


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

PROJECT INSPECTION RESPONSIBILITY


ITEM QUALITY QUALITY ASSIGNMENTS
PHASE & TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
Activity Code CNTRCTR
ARAMCO

DOCUMENT
1.0 SPECIAL PROCESS (PRESSURE TESTING) REQUIRES BEST QUALITY PRACTICE, CPI & EFFICIENT METHODS IN PROCEDURES. PROPOSE BEST METHODS.
REVIEW

In Conjunction with SATIP-A-004-01. Systems


requiring Service Test are identified in Plants *ASME
1.1 Leak Testing Procedure* SAIC-A-2005 SAIC-A-2005 RH RH
V Code Procedure (Bubble Method) @ 5-10 psi per
SAES-A-004

MATERIAL
2.0
RECEIVING
Verify Pneumatic Test Medium & Bubble Data sheets are available on bubble forming solution
2.1 SAIC-A-2004 SAIC-A-2004 RH R
Test Solution used in Leak Tests

3.0 APPLICATION

Test Preparation & Verification of Testing


3.1 SAIC-A-2009 SAIC-A-2009 H W In conjunction with SATIP-A-004-01 as applicable.
equipment (incl safety reqmts)

SAIC-A-2023, SAIC-A-2023,
3.2 Filling & Pressurization W W Ditto
SAIC-A-2020 SAIC-A-2020

Use SATR-A-2010 - In conjunction with SATIP-A-


Leak Test (after Pneumatic Testing) at 5- SAIC-A-2024, SAIC-A-2024,
3.3 H H 004-01 as applicable. *Procedure details
10 psig or BEFORE* Service Test SAIC-A-2021 SAIC-A-2021
sequence/method.

3.4 De-Pressurization SAIC-A-2022 SAIC-A-2022 W S

4.0 POST- TEST

Use SATR-A-2007 & SATR-A-2011, this also In


4.1 Reinstatement Inspection SAIC-A-2006 SAIC-A-2006 H W
conjunction with SATIP-A-004-01 as applicable.

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.00 30-Jun-16

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

LEAK TESTING (per SAES-A-004) SATIP-A-004-05 15-Nov-17 MECHANICAL


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1 levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
4
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H 100% Hold Point for QC Inspection or Test. R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016)

Saudi Aramco: Company General Use


Rev. 2016.06.00

###

Saudi Aramco: Company General Use


30-Jun-16

Saudi Aramco: Company General Use


### ###

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016)

Saudi Aramco: Company General Use


Rev. 2016.06.00

###

Saudi Aramco: Company General Use


30-Jun-16

Saudi Aramco: Company General Use


### ###

Saudi Aramco: Company General Use