DC Migration Non Sap Servers - Priority 01 Servers Hi Level WBS Finalization

Server Name Server use Priority on migration Service Owner


Common Jump JUMP Priority 01 Radika
JKG-PRD-RODC01 AD INFRA Priority 01 Mafais
JKG-PRD-DNS DNS Priority 01 Mafais
NTP1 NTP Priority 01 Chandu
JKG-PRD-ROOTCA Certificate Servers Priority 01 Mafais
JKG-PRD-SUBCA Certificate Servers Priority 01 Mafais
JKG-PRD-ADDC01 AD INFRA Priority 01 Mafais

_x000D_ John Keells Group - Confidential


#
JKG-PRD-RODC01 WBS Plan
what is the migration priority
Application or Database installed?
Migration approche ( commvault / rehost)
In rehost, Who is going to install Application or Database
In replication, Who is going to do database restoration
How many days need to install/ restore DB
How many days need to install/ restore App
What are the BU connect
Who is responsible for test failover
How many days need for test failover
How many days need for cutover
When can we do the cutover

_x000D_ John Keells Group - Confidential


#
Common Jump WBS Plan
what is the migration priority
Application or Database installed?
Migration approche ( commvault / rehost)
In rehost, Who is going to install Application or Database
In replication, Who is going to do database restoration
How many days need to install/ restore DB
How many days need to install/ restore App
What are the BU connect
Who is responsible for test failover
How many days need for test failover
How many days need for cutover
When can we do the cutover

_x000D_ John Keells Group - Confidential


#
JKG-PRD-DNS WBS Plan
what is the migration priority
Application or Database installed?
Migration approche ( commvault / rehost)
In rehost, Who is going to install Application or Database
In replication, Who is going to do database restoration
How many days need to install/ restore DB
How many days need to install/ restore App
What are the BU connect
Who is responsible for test failover
How many days need for test failover
How many days need for cutover
When can we do the cutover

_x000D_ John Keells Group - Confidential


#
NTP1 WBS Plan
what is the migration priority
Application or Database installed?
Migration approche ( commvault / rehost)
In rehost, Who is going to install Application or Database
In replication, Who is going to do database restoration
How many days need to install/ restore DB
How many days need to install/ restore App
What are the BU connect
Who is responsible for test failover
How many days need for test failover
How many days need for cutover
When can we do the cutover

_x000D_ John Keells Group - Confidential


#
JKG-PRD-ADDC01 WBS Plan
what is the migration priority
Application or Database installed?
Migration approche ( commvault / rehost)
In rehost, Who is going to install Application or Database
In replication, Who is going to do database restoration
How many days need to install/ restore DB
How many days need to install/ restore App
What are the BU connect
Who is responsible for test failover
How many days need for test failover
How many days need for cutover
When can we do the cutover

_x000D_ John Keells Group - Confidential


#
JKG-PRD-ROOTCA WBS Plan
what is the migration priority
Application or Database installed?
Migration approche ( commvault / rehost)
In rehost, Who is going to install Application or Database
In replication, Who is going to do database restoration
How many days need to install/ restore DB
How many days need to install/ restore App
What are the BU connect
Who is responsible for test failover
How many days need for test failover
How many days need for cutover
When can we do the cutover

_x000D_ John Keells Group - Confidential


#
JKG-PRD-SUBCA WBS Plan
what is the migration priority
Application or Database installed?
Migration approche ( commvault / rehost)
In rehost, Who is going to install Application or Database
In replication, Who is going to do database restoration
How many days need to install/ restore DB
How many days need to install/ restore App
What are the BU connect
Who is responsible for test failover
How many days need for test failover
How many days need for cutover
When can we do the cutover