Estimate For Repairing Bath Room Xen Office Building Pasrur Link Divisional Office of MR Link Canal Sialkot
Estimate For Repairing Bath Room Xen Office Building Pasrur Link Divisional Office of MR Link Canal Sialkot
ABSTRACT OF COST
Sr.
Quantity Description Unit Rate Amount
No.
Dismantling cement concrete 1:2:4 plan Ch # 4
1 21 item # 19 c 100cft 6,888.30 1446.54
Chement Concrete plain including placing
Compacting , Finishing and Curing Completed
2 21 including Screening and Washing of Stone Aggregate 100cft 22497.8 4725
ratio 1:2:4 Ch # 5 item # 5f
Total 80574
Add PST 16% 12892
Certified that the items, Rates & Quantities Certified that the data
provided in the estimate has been checked forming the basis of this
by me and found correct as per my entire estimate has been checked
satisfaction by me and found correct as
per my visual inspection
Sub Engineer,
DETAIL OF QUANTITY
Sr.
No. Description Quantity Unit
Cement concrete plain including placing, compacting, finishing and curing complete
2 (including screening and washing of stone aggregate): Ratio 1:2:4 21cft 100 Cft
Bathroom Floor = 9.25 x 6.83 x 0.33 = 21cft
Dismantling of tiles.
Bathroom floor = 9.25 x 6.83 = 63.17 Sft
Wall(A,B) of Bathroom = 1 (7.66+8.5) x3.16 = 51 Sft
Wall (C,D) = 1 ( 7.16+5.83 ) x 3.083 = 40 Sft
3 Jambs of Door (2) = 2 (3.083 +3.083 ) x .75 = 9.25Sft 179.27 100 Sft
Window Jambs = 3 x 0.75 = 2.25Sft
W.seat = 3.16 x 3 = 9.48 Sft
Door down side = 1 (2.5+3) x0 .75 = 4.12 Sft
Total =179.27 Sft
Laying floor of approved coloured glazed tiles ¼ "(6 mm) thick, laid in white cement
and pigment on a bed of ¾" (20 mm) thick cement mortar 1:2.
Bathroom floor = 9.25 x6.83 =63.17 Sft
Wall of Bathroom = 2(6.83+9.25) x 7 = 225.12 Sft
Jambs of door (1) = 2 (3+7)0.75 = 15 Sft
Jambs of Door (2) = 2 (2.5+7 )0.75 = 14.25 Sft
Window Jambs = 2(3+3.75) 0.75 = 10.125 Sft
3 277.66 100 Sft
Total =327.67 Sft
Deduction
Window = 3x 3.75 = 11 Sft
Door (1) = 3 x 7 = 21 Sft
door (2) = 2.5 x 7 = 18 Sft
Total Deduction = 50 Sft
Net Quantity = 327.66 -50 = 277.66 Sft
Providing, laying, cutting, jointing, testing and disinfecting G.I. pipeline in trenches,
with socket joints, using G.I.pipes of B.S.S. 1387-1967 complete in all respects, with
plugs, etc. is included in the rates. specials and valves. Medium Quality.
Main Supply outer = 5+ 2 = 7
4 Internal main supply = 3+3+2+2 = 10 45 Per Rft
For Wall shower = 3+3+3+3 = 12
For wash Hand basin = 2+2+2+2 = 8
for Comode = 2+3+3 = 8
Total = 45'
Providing and fitting glazed earthen ware water closet European type, excluding seat
5 and cover:- white 1 No.
Providing and fitting glazed earthen ware wash hand basin56x40 cm (22"x16")
6 1 No.
including bracket set, waste pipe and waste coupling, etc. (white with pedestal)
Providing and fitting plastic made low down flushing cistern13.63 litre (3 gallons)
7 capacity, including bracket set, copper connection, etc. complete. Coloured. 1 No.
Bath = Set No.2
Providing and fixing looking glass 55x40 cm (22"x16") size, and 5 mm thick, first
8 1 No.
quality.
Providing and fixing chromium plated stop cock, heavy:- 1.5 cm (½").
With wash hand basin = 2
10 With Comode 3 No.
=1
Total 3 No.
Providing and fixing, chromium plated mixing valve, for wash hand basin, sink or
11 shower. 2 No.
Wash hand basin + shower = 1+1 = 2 No.
Providing and fitting, chromium plated or brass oxidised, swan neck cock 15 mm (½")
12 dia. two way. 1 No.
14 Providing and fitting, cast iron soil pipe with:- cement caulked joint:- 4'' dia. 7 Per ft
15 Providing and fixing, angle iron brackets for:- wash hand basin and cistern = 2 No. 2 Each
16 Providing and fixing chromium plated shower rose:- 1.5x10 cm (½"x4"). 1 Each
17 Providing and fixing chromium plated pillar-cock, heavy:- (for muslim shower). 1 Each
Sub Divisional Officer,
Rawal Link Sub Division,
Sialkot.