Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 5

Ing.

Ricardo Liñan Blas

CONCRETO F'C KG/CM2 1 bulto = 18.90 lts


Resistencia 1 m3 # bultos 1 bolsa cemento
f'c=kg/cm2 Cemento Arena Piedra H2O Arena Piedra H2O Cemento Arena Piedra H2O
100 5.98 0.51 0.85 186.90 26.89 44.78 9.89 1.00 4.50 7.49 31.26
140 7.36 0.54 0.67 193.20 28.33 35.56 10.22 1.00 3.85 4.83 26.25
175 8.85 0.57 0.58 194.25 30.00 30.56 10.28 1.00 3.39 3.45 21.95
175 8.15 0.82 0.58 194.25 43.12 30.56 10.28 1.00 5.00 5.00 22.10
210 10.22 0.55 0.56 197.40 28.89 29.44 10.44 1.00 2.83 2.88 19.32
245 12.08 0.53 0.54 196.35 27.78 28.33 10.39 1.00 2.30 2.35 16.26
280 14.01 0.47 0.54 198.45 25.00 28.33 10.50 1.00 1.78 2.02 14.17

CONCRETO EN VOLUMENES
Tipo 1 m3 # bultos 1 bolsa cemento
Dosificación Cemento Arena Piedra H2O Arena Piedra H2O Cemento Arena Piedra H2O
1:2:2 10.38 0.70 0.70 210.00 37.22 37.22 11.11 1.00 3.59 3.59 20.24
1:2:2,5 9.51 0.64 0.80 194.25 33.89 42.22 10.28 1.00 3.56 4.44 20.42
1:2:3 8.65 0.59 0.88 183.75 31.11 46.67 9.72 1.00 3.60 5.40 21.25
1:2:3,5 8.03 0.55 0.96 178.50 28.89 50.56 9.44 1.00 3.60 6.30 22.23
1:2:4 7.41 0.50 1.01 173.25 26.67 53.33 9.17 1.00 3.60 7.20 23.38
1:2,5:2,5 8.65 0.74 0.74 183.75 38.89 38.89 9.72 1.00 4.50 4.50 21.25
1:2,5:3 8.03 0.68 0.82 178.50 36.11 43.33 9.44 1.00 4.50 5.40 22.23
1:2,5:3,5 7.41 0.63 0.88 173.25 33.33 46.67 9.17 1.00 4.50 6.30 23.38
1:2,5:4 6.92 0.59 0.95 168.00 31.11 50.00 8.89 1.00 4.50 7.23 24.29
1:2,5:4,5 6.55 0.56 1.00 162.75 29.44 52.78 8.61 1.00 4.50 8.06 24.86
1:3:3 7.41 0.76 0.76 173.25 40.00 40.00 9.17 1.00 5.40 5.40 23.38
1:3:4 6.55 0.66 0.88 162.75 35.00 46.67 8.61 1.00 5.35 7.13 24.86
1:3:5 5.81 0.59 0.98 157.50 31.11 51.67 8.33 1.00 5.36 8.90 27.13
1:3:6 5.31 0.53 1.05 147.00 27.78 55.56 7.78 1.00 5.23 10.46 27.67
1:4:7 4.32 0.59 1.03 131.25 31.11 54.44 6.94 1.00 7.20 12.59 30.36
1:4:8 4.08 0.55 1.08 126.00 28.89 57.22 6.67 1.00 7.09 14.04 30.91

HORMIGON
Tipo 1 m3 # bultos 1 bolsa cemento
Resistencia Cemento Hormigon H2O Hormigon H2O Cemento Hormigon H2O
110 5.97 1.19 186.90 62.72 9.89 1.00 10.50 31.28
140 6.99 1.19 210.00 62.83 11.11 1.00 8.99 30.03
1:6 6.51 1.10 220.50 58.33 11.67 1.00 8.96 33.87
1:7 5.78 1.14 199.50 60.56 10.56 1.00 10.49 34.55
1:8 5.25 1.19 178.50 62.78 9.44 1.00 11.96 34.00
1:9 4.83 1.22 168.00 64.44 8.89 1.00 13.34 34.78
1:10 4.41 1.25 147.00 66.11 7.78 1.00 14.99 33.33
1:12 3.78 1.29 126.00 68.33 6.67 1.00 18.08 33.33

MORTEROS
Tipo 1 m3 # bultos 1 bolsa cemento
Dosificación Cemento Arena H2O Arena H2O Cemento Arena H2O
1:1 22.24 0.76 425.25 40.00 22.50 1.00 1.80 19.12
1:2 14.82 1.01 315.00 53.33 16.67 1.00 3.60 21.25
1:3 11.12 1.13 60.00 60.00 3.17 1.00 5.40 5.40
1:4 8.89 1.21 252.00 63.89 13.33 1.00 7.18 28.33
1:5 7.41 1.26 236.25 66.67 12.50 1.00 8.99 31.88
1:6 6.42 1.29 220.50 68.33 11.67 1.00 10.64 34.33
1:7 5.56 1.32 204.75 70.00 10.83 1.00 12.59 36.83
Ing. Ricardo Liñan Blas

1:8 4.94 1.34 194.25 71.11 10.28 1.00 14.39 39.31


1:9 4.45 1.37 183.75 72.22 9.72 1.00 16.24 41.32
1:10 4.08 1.19 173.25 62.83 9.17 1.00 15.41 42.50
CANT ANCHO LARGO ALTO AREA VOLUMEN PARCIAL
Cimiento corrido m3 5.28
LADO 01 1.00 0.40 10.00 0.40 1.60
LADO 02 1.00 0.40 10.00 0.40 1.60
LADO 03 1.00 0.40 7.00 0.40 1.12
LADO 04 1.00 0.40 6.00 0.40 0.96
Sobre cimiento m3 1.49
LADO 01 1.00 0.15 10.00 0.30 0.45
LADO 02 1.00 0.15 10.00 0.30 0.45
LADO 03 1.00 0.15 7.00 0.30 0.32
LADO 04 1.00 0.15 6.00 0.30 0.27
Columnas 1.13
Col. 15x25 10.00 0.15 0.25 3.00 1.13
Muro de ladrillo 99.00
LADO 01 1.00 10.00 3.00 30.00
LADO 02 1.00 10.00 3.00 30.00
LADO 03 1.00 7.00 3.00 21.00
LADO 04 1.00 6.00 3.00 18.00
Piso 70.00
AREA 1.00 7.00 10.00 70.00
MATERIALES CANT P.U.
CONCRETO 14.89
03 CEMENTO 104.23 22.50
HORMIGON 17.68 22.00
LADRILLO 3663.00 0.36
FIERRO 3/8 13.00 16.00
FIERRO 1/4 10.00 6.50

10.00 m
01 02

04

7.00 m
PARCIAL

2345.18
389.02
1318.68
208.00
65.00
4325.87