Professional Documents
Culture Documents
Design and Construction of 15 MLD Capacity Main Pumping Station (MPS) at Aerocity, Sas Nagar
Design and Construction of 15 MLD Capacity Main Pumping Station (MPS) at Aerocity, Sas Nagar
Design and Construction of 15 MLD Capacity Main Pumping Station (MPS) at Aerocity, Sas Nagar
CONSTRUCTION OF 15
MLD CAPACITY MAIN
PUMPING STATION (MPS) AT
AEROCITY, SAS NAGAR
Submitted by:
Dipendra Singh
SID : 18102052
DEPARTMENT OF CIVIL
ENGINEERING
PUNJAB ENGINEERING
COLLEGE, CHANDIGARH
1
PRESENTATION CONTENTS
2
INTRODUCTION: THE PROJECT
3
About The Site
6
TECHNOLOGY FOR SEWAGE
TREATMENT
01
SEQUENCING BRANCH REACTOR (SBR) tank using a timed control sequence.
7
Technology Selection Basis
Reasons for selecting SBR
In areas where there is a limited amount of
space is available.
Older wastewater treatment facilities can be
retrofitted to an SBR because the basins are
already present.
10
Field Investigations
Survey of Wards
• Total no of Houses
• Ward wise population projections
• Area and Density of ward
11
Level Change Model With temporary benchmark (TBM)
12
PARTICULAR DESIGN CONDITIONS
Bearing Capacity: Design based on the tested bearing capacity or maximum net safe bearing
capacity of 12 Tonne per sq.m, (1.2 Kg/cm2)
Design characteristics: All the structures designed / built considering
• the worst spring level, no pressure release valves installed for release of uplift
pressure.
• assuming water up to Top of Wall (TOW) with no supporting earth/water pressure on
other side
• Top of outer walls of all RCC structures shall be minimum 0.6 m above
Formation Level of the site.
• All outer walls which are less than 1.2 m above formation level of site shall be provided
with railing
• All water retaining structures designed & constructed in design mix minimum M-30 as
per IS 3370, 2009
• Other non-water retaining structures shall be designed & constructed in design
mix minimum M-25 grade of concrete as per latest IS 456-2000, IS 10262
• Minimum thickness of water retaining structures 200 mm
Plinth Protection: All building and tanks structures provided with min 1200 mm wide
cement concrete (M20) of average thickness 100mm over a layer of CC M-15 (average
thickness 75mm) with toe wall of 230 mm thickness laid over PCC M-15, 75 mm thick
Damp proof course: Damp proof course, 75mm thick, with cement concrete M-2A5 mixed
with approved waterproofing component provided at plinth level in all buildings
13
EXCAVATION WORKS AT SITE
EXCAVATION:
DEWATERING OF EXCAVATION :
FOUNDATION:
The lowermost part of a structure which transmits all loads
and is in direct contact with the ground is called a foundation,
the function of which is to spread or distribute the weight of
the structure over a large area to avoid unequal settlement of
the soil below.
Types of Shallow foundation used at site for various facilities:
Combined Footing
Spread or Isolated Footing
The foundation used in tanks:
TREATED WATER TANK
Raft foundation(mat foundation):
Grade of concrete – M30
Steel Grade – FE 500
16
REINFORCEMENT-BAR BENDING
WORKS AT SITE
17
SITE PLAN
18
STRUCTURE DRAWING AND LAYOUT
19
BAR BENDING SCHEDULE
Sample of Bar Bending Schedule with total steel requirements:
AEROCITY GMADA 10 M.L.D. S.T.P. AEROCITY GMADA 10 M.L.D. S.T.P.
NO. OF NO. OF
S.NO DISCRIPTION OF BAR DIA TOTAL LENGTH TOTAL LENGTH s.no DISCRIPTION OF BAR DIA TOTAL LENGTH TOTAL LENGTH
BARS BARS
20
CONSTRUCTION DRAWINGS
Structural Designer:
21
TESTS PERFORMED AT SITE
22
TESTS PERFORMED AT SITE
Test Details:
Description: Grading Test of Coarse Aggregates (20mm)
Weight of Sample (Kg): 5Kg
Test Details:
Description: Grading Test of Fine Aggregates Weight of
Sample (Kg): 1Kg
23
TESTS PERFORMED AT SITE
24
TESTS PERFORMED AT SITE
1 R.C.C. of Wall of Treated water Tank ( 2 walls upto 2.4m) 25/03/2021 M30 12 22/04/2021 5 8.24 31.35
(6+6) 6 8.28 30.22
2 R.C.C. of wall of Treated water Tank other 2 sides upto 2.4 3/4/2021 M30 12 2/5/2021 5 8.265 33.33
(6+6) 6 8.27 35.56
3 Columns of Treated water Tank 2/4/2021 M30 3 1/.5/2021 5 8.285 29.12
3+ 6 8.29 30.22
4 R.C.C. of Treated water Tank 2nd lift 7/4/2021 M30 6 5/5/2021 5 8.245 37.56
(3+3) 6 8.28 31.34
5 Concrete for columns of Treated water Tank 21/4/2021 M30 3 18/05/2021 3 8.31 33.78
6 Concreteing of foundation of Admin Block 16/4/2021 M25 6 14/05/2021 5 8.285 31.5
6 8.26 30
25
CONCLUSION
26
CONCLUSION
Under the guidance of JE Ravinder Singh and site
engineer Er. Chahatpreet Singh, I got the opportunity to
understand the technical and management aspects of industrial
projects. I got to know about the basic & advanced techniques of
sewage treatment plants as well as faced the challenges which a The benefit & skills gained are:
Civil Engineer must tackle during construction i.e., labor
Insight and practical knowhow of the
problems, cost management, environmental challenges etc.
Civil Engineering field
Overall, it must be said that the construction methods and quality Improvement in teamwork skills
control need very good coordination and adequate manpower, Gained Leadership skills
equipment and funds. During this training all the site staff helped Dealing with other professions
me a lot to provide all the information about any query. Industrial Development of practical skills
training is a very essential part of an engineering course. It helps in Learning of work ethics
elevating and improving the knowledge and skills of the learner. It Interpersonal communication skills
further helps to Students to fulfill their career objectives.
27
Does anyone have any questions?
THANKS
Follow the project updates
addyouremail@freepik.com
+91 620 421 838
yourcompany.com
28