This document contains budgeted and actual quantities for key construction items and equipment for an airport security force project. It lists 16 items with budgeted and actual quantities, including concrete, excavation, fencing, lighting, and cables. It also lists 9 pieces of construction equipment, such as manlifts, cranes, and dump trucks, with budgeted quantities and actual units on site. The progress is at 0% for the concrete line item. MAFCO is listed as the expected contractor to mobilize in mid-August.
This document contains budgeted and actual quantities for key construction items and equipment for an airport security force project. It lists 16 items with budgeted and actual quantities, including concrete, excavation, fencing, lighting, and cables. It also lists 9 pieces of construction equipment, such as manlifts, cranes, and dump trucks, with budgeted quantities and actual units on site. The progress is at 0% for the concrete line item. MAFCO is listed as the expected contractor to mobilize in mid-August.
This document contains budgeted and actual quantities for key construction items and equipment for an airport security force project. It lists 16 items with budgeted and actual quantities, including concrete, excavation, fencing, lighting, and cables. It also lists 9 pieces of construction equipment, such as manlifts, cranes, and dump trucks, with budgeted quantities and actual units on site. The progress is at 0% for the concrete line item. MAFCO is listed as the expected contractor to mobilize in mid-August.
SN DESCRIPTION UNIT BUDGETED QTY ACTUAL QTY % Progress
1 Concrete CUM 2800 0% 2 Excavation CUM 16000 3 Backfilling CUM 30000 4 Asphalt LM 3300 5 Fixed Camera EA 8 6 PTZ EA 11 7 MIDS EA 8 LRC EA 4 9 FOFFS EA 10 FEC EA 19 11 FENCE CAT.2 LM 3250 12 FENCE CAT.4 LM 2100 13 Lighting fixtures EA 167 14 Turnstile EA 8 15 Card reader EA 8 16 MV/LV cables AASF-Construction Equipment
SN DESCRIPTION UNIT BUDGETED QTY ACTUAL QTY % Progress
1 Manlift EA 1 #DIV/0! 2 Crane EA 1 3 Grader EA 0 4 Roller EA 0 5 Backhoe EA 1 6 Dump Truck EA 0 7 Water tanker EA 0 8 Boom truck EA 1 9 10 11 12 13 14 15 16 MAFCO MAFCO Expected to mobilize by mid August Expected to mobilize by mid August MAFCO Expected to mobilize by mid August Expected to mobilize by mid August NGMSA