AASF-Key Quantities

SN DESCRIPTION UNIT BUDGETED QTY ACTUAL QTY % Progress


1 Concrete CUM 2800 0%
2 Excavation CUM 16000
3 Backfilling CUM 30000
4 Asphalt LM 3300
5 Fixed Camera EA 8
6 PTZ EA 11
7 MIDS EA
8 LRC EA 4
9 FOFFS EA
10 FEC EA 19
11 FENCE CAT.2 LM 3250
12 FENCE CAT.4 LM 2100
13 Lighting fixtures EA 167
14 Turnstile EA 8
15 Card reader EA 8
16 MV/LV cables
AASF-Construction Equipment

SN DESCRIPTION UNIT BUDGETED QTY ACTUAL QTY % Progress


1 Manlift EA 1 #DIV/0!
2 Crane EA 1
3 Grader EA 0
4 Roller EA 0
5 Backhoe EA 1
6 Dump Truck EA 0
7 Water tanker EA 0
8 Boom truck EA 1
9
10
11
12
13
14
15
16
MAFCO
MAFCO
Expected to mobilize by mid August
Expected to mobilize by mid August
MAFCO
Expected to mobilize by mid August
Expected to mobilize by mid August
NGMSA