ENGINEER’s RESPONSE

Project Construction of Mumbai-Ahmedabad High Speed Rail (MAHSR) Package C7


Ref. No. AMS-0000058 Revision R1
Title METHOD STATEMENT FOR CASTING OF SBS SEGMENTS (R1) Received on 27-05-2022
Review Code Notice of No Objection with Comments (NONOC) Reviewed on 04-06-2022
Other Ref. MAHSR/C7/MS/0034

Sl.no. Drawing / Document No. Observations / Comments


In list of Major Equipment to be used in casting yard quantity of following items shall be mentioned “As per requirement”
in MS.
1) Transit Mixer Trucks
2) Concrete Pump / Boom Placer
3) Pick n Carry Crane
4) Bar Cutting / Shearing machine
5) Bar bending machine
1 Cl. 8
6) Bar spiral bending machine
7) Curing pump
8) Needle Vibrators
9) Survey Instruments
10) Chiller Plant*/RO Plant
• Shall include water tanker with suitable capacity as per requirement.
• Mould / Form Vibrators shall be mentioned per mould with its required numbers.
2 Cl. 14.8 For Installation of seismic stopper and it’s grouting a separate MS shall be submitted.

3 Cl. 13 For curing shall incorporate Section VI-3. Employer’s Requirements (Technical Specifications) Cl. 5.6.1. (b)
4 Cl. 14.18 (E) During placing, the concrete temperature shall not exceed 32ºC as per
5 Cl. 14.10 E (c) Wedge drawing to be enclosed.
Cool water shall be sprinkled at outer most surface of shutter/mould after the concrete has set hard enough and as soon as
6 14.20
the concrete surface reaches touch dry condition.
7 14.24(B) Please correct statement mentioned “50N/mm2 or 7 days, whichever is later” for longitudinal prestressing.
8 14.25(E) Segment stacking arrangement drawing shall be vetted by third party proof checker and same has to be enclosed.
9 Pg. no. 101 Typical sketch for survey inspection checklist to be enclosed.
10 Pg. no. 101 The survey inspection checklist for soffit level checking to be enclosed.
Appendix 1: Inspection The project quality management plan submitted by CJV in Unifier Record No.- COR-0000000056 is not approved yet
11 Test Plan PCC & RCC Pre- so please do incorporate the points i.e. 34,35,36,37,38,39,40,41 & 42 given in R0 – Engineers Response.
stressed Concrete

Note: Notwithstanding Engineer’s comments, responsibility of ensuring conformity to contractual, technical and functional requirements lies with the Contractor.
Any non-compliances on the part of the Contractor in the preparation, submission or resubmission of Contractor’s Documents shall not constitute a Variation.

Jitendra Digitally signed by


Jitendra Prasad

Prasad 12:54:45 +05'30'


Date: 2022.06.06

Samir Sood Jitendra Prasad


_______________________________
____________________________________
[Reviewed by] [Endorsed by]