Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

THE FHI CLINICAL/PREVAIL RENOVATION

OF THE C.H. RENNIE PROJECT LOCATED IN


KAKATA CITY MARGIBI COUNTY, LIBERIA

WEEKLY REPORT 11

Reporting period: May 16-21, 2022

Prepared for : FHI CLINICAL/PREVAIL

Prepared by: Patrick T. USAR

Bezaleel + Turkey Contractor Inc.

1.0 WEEKLY HIGHLIGHTS


1.1 Key Events
During the reporting period under review, which began from May 16-21 2022. Zenith Construction
workers were engaged in an enthusiastic construction activity on the site. Bezaleel Turnkey Contractors
Inc. is providing inspection services for the project. The project is the FHI Clinical/PREVAIL OPD and
office Renovation located at the C.H. Rennie compound. The plan project consists of the OPD Building
and Lab facility for Prevail. This progress report is to provide to the client a weekly development
indication of the construction process of the project.

The followings are works completed and those that are in progress during the reporting period

1. General painting
2. Application of wall putty (smoothing of wall)
3. Installation of aluminum sliding windows, and frame and Doors

Table 1: The table included a summary of the project highlights for the reporting period

Date May 16-21 2022


ONGOING WORK DURING THE REPORTING PERIOD
1. Renovation of OPD and Porch Extension
Scope of work Activities Percentage (%)
General painting Application of 10%
primer(first coat) on
ceiling and plywood
partition, and application
of white paint on ceiling.
Application of wall putty Application of wall putty 98%
and smoothing of wall
ongoing
Fabrication of Aluminum Fabrication and 50%
sliding window frame installation of aluminum
and door frame. window frames and
doors frames,
installation of sliding
window glasses.

SAFETY MEASURE DURING THE REPORTING PERIOD.


May 21,2022 All safety measures relating to the project
is in place and ongoing 100%. Relative to
the following:
Safety Measures
a. Wearing of reflective jackets, and
helmet.
b. Working in safe environment
c. Using the appropriate working
materials per department of work.

Table 2: Summary of overall works progress up to May, 2022

Item Description Progress as of last Accumulative Remarks


reporting period progress to
(%) date (%)
1.0 OPD and Porch Extension The project
project C.H. Rennie performance factors
compound, Kakata, Margibi show that the level of
county. work is satisfactory
but with little
progress during the
week under review.

1.2 Project Deliverable and Documentation


The main content of the report included:

 Status of mobilization
 Outline of applicable project control measures
 The Quality Assurance Plan
 Comments of the review of drawings

2.0 Environmental monitoring and compliance


During the reporting period, the following were observed as shown below:

a. The debris stockpile is being removed from the site gradually.


b. Site workers were in full PPEs during work hours

4.0 Materials
The materials on site include:

a. Steel
b. Galvanize pipe
c. Welding rod
d. Cutting disc for concrete
e. PVC pipes (4’’, 2’’, ½ “)
f. PVC reducer, PCV Glue, PVC TEE
g. Plywood
h. Ceiling strip
i. PVC ceiling
j. Putty
k. Floor board
l. Chain link wire
m. Tiles
n. Aluminum accessories
o. Primer
p. Paints (Briton)
5.0 Photo Gallery

Figure 1. installation of aluminium sliding window Figure 2. installation of aluminium partition

Figure 3. application of primer on ceiling and partition Figure 4. applicarion of primer and paint on ceiling

You might also like