Call for TENDER No. MMC20-5039 COMPANY’s preliminary SSHE Risk assessment Exhibit L Annex-3
PRELIMINARY WELLHEAD PLATFORM EPCI
PROJECT RISK ASSESSMENT
1. Contract Title: EPCI of Wellhead Platforms, Associated Pipelines and Brownfield Modifications for
Zawtika Development Project Phase 1D
Note:
TENDERER shall review and populate the Project SSHE Risk Assessment ITT SSHE Section Attachment 2
The Pre-populated SSHE Hazards shall be assessed considering Project scope, and TENDERERS onshore and the
offshore activities. The qualification risk assessment shall be based on the COMPANY SSHE Risk Ranking Matrix as
provided and Standard ISO 17776 LISTING OF HAZARDS
TENDERER should consider the hazards without any risk mitigations, (initial risk) thereafter TENDERER shall detail the
proposed risk mitigations and safety controls which TENDERER considers would if implemented reduce the risk and
reassess the risk ranking which demonstrate risk values may be reduced to as low as possible.
Guidance:
TENDERER is expected to update the Risk Ranking table Mitigations and contingencies accordingly
Purpose of the activity is to assess TENDERER concept and acknowledgement of Project related SSHE risks and the anticipated
risk mitigation options it would consider during execution.
Risk Matrix shall be COMPANY Procedures 11038-STD-SSHE-401-R06 SSHE Risk Management Standard
In the event of award the document shall be utilized as applicable in preparation of specific Work Instructions, Job Safety
Analysis and any relevant top hazards included within monthly Project Risk Management reviews.
TENDERER if successful will utilize and continually revise this document under the Project Monthly Risk Assessment
TENDERER at its own discretion may additional activity activities and assess accordingly; utilizing COMPANY Risk Standard
and ISO 17776 LISTING OF HAZARDS as necessary
Note: the Initial Risk Rankings are subjective assessment and will be revised with Project Team during execution
Part 1: Project Management
Page 1 of 6
EPCI of Wellhead Platforms, Associated Pipelines and Brownfield Modifications for Zawtika Development Project Phase 1D PTTEPI/ ……………
Call for TENDER No. MMC20-5039 COMPANY’s preliminary SSHE Risk assessment Exhibit L Annex-3
Part 1: Project Management
Note: Risk Ranking is made without consideration of Safety Precautions and Contingencies have no bearing on the risk ranking and are related to “response” arrangement in the event the risk is realized and a loss occurs)
Project Step / Activity ISO Hazard Element: Initial Risk Evaluation Risk SSHE Precautions Contingencies Post Risk
Reference SA - Safety Ranking (Risk mitigations to prevent hazard occurring) (Emergency & Crisis Ranking
SE - Security Hazards Arising Hazard Initiated by Consequences Impact Likelihood Impact x What will be implemented to reduce the Risk arrangements, spare (Residual
H - Health (Consequence) (Frequency) Likelihood to ALARP equipment, back up plans if Risk Impact x
E- Environment applicable) Likelihood)
Site to Site / Facility 21.15 SA, SE Collision Poor driver Injury, Fatality - Defensive driver training - ERP
Travelling/ Transportation 21.16 Break down competency / Reputation - Vehicle minim standards and inspections - First Aid kits
Speeding inability related to Delay - Driver license - Fire Extinguisher
Detention / Fines by defensive driving - Driver SSHE Rules - Break down equipment
authorities Poor vehicle - UDAT Program - Means of communication
fatigue condition - Fit To Work program / eye tests
4 3 12 (medium) - Journey Management Control / Planning
Unfit No journey
management - Fatigue Management
assessment
Drugs & Alcohol
No MCU/ UDAT
Long driving hours
Work Permit Arrangement SA,SE Detention of Lack of Detained by
(Services to Company/ personnel by assessment in authorities
Contractor and Sub- authorities relation to visa / Reputation 3 3 9 (medium) -
Contractor personnel) WP process Project Delay
Company and
Contractor
Accommodation 27.02 SA,SE, H, E Health Impacts Ineffective Injury -
Arrangements (Services to 24.04 Fire / Explosion assessment of Ill-health
Company/ Contractor and 24.05 Security facilities Project damage 4 3 12 (medium) -
Sub-Contractor personnel) 24.06 Delay
Thefts/ assaults
Employment of Sub- SA,SE, H, E Disputes/ Strike Delayed payment Reputation -
Contractors 27.02 to subcontractor Project Delay
4 4 16 (high)
27.04 salaries
Poor Cash Flow
Country - Socio Political 27.04 SE, SA Dispute with local Ineffective CSR Reputation -
Events 27.02 community plan Project Delay
Employment of local Poor CSR Injury
workforce (avoid dispute) consultation 3 3 9 (medium) -
/ Elections & Religious process and plan
Events, Labour days
(protests)
Natural Disasters/ 9.01 SA, E, SE, H Earthquake Natural event Project Delay
Weather 9.02 Storm / Lightening Injury/ fatality
9.03 Flooding Ill-health
25.09 Security Impacts: Damage
24.04 4 3 12 (medium) - -
Civil Unrest Fire/ Explosion
24.05 Water & Food Borne
Bacteria
Page 2 of 6
EPCI of Wellhead Platforms, Associated Pipelines and Brownfield Modifications for Zawtika Development Project Phase 1D PTTEPI/ ……………
Call for TENDER No. MMC20-5039 COMPANY’s preliminary SSHE Risk assessment Exhibit L Annex-3
Part 2: Onshore Fabrication Project Risk Ranking
Note: Risk Ranking is made without consideration of Safety Precautions and Contingencies have no bearing on the risk ranking and are related to “response” arrangement in the event the risk is realized and a loss occurs)
Project Step / Activity ISO Hazard Element: Initial Impact Initial Likelihood Risk SSHE Precautions Contingencies Post Risk
Reference SA - Safety Evaluation Evaluation Ranking (Risk mitigations to prevent hazard occurring) (Emergency & Crisis Ranking
SE - Security (Consequence) (Frequency) Impact x ( What will be implemented to reduce the Risk arrangements, spare (Residual
Hazards Arising Hazard Initiated by Consequences
H - Health Likelihood to ALARP equipment, back up plans if Risk Impact
E- Environment applicable) x Likelihood)
Award / appointment of 25.12 SA, SE, H, E Unware of Hazards/ Lack of effective Increased - Effective Pre-Selection and - Approved ERP
Fabrication Sub- 25.13 Lack of Awareness Pre-Selection and frequency and Qualification Process - Approved ERT
Contractors 25.14 - Contract Exhibits include details of - Tested ERT Systems
Unaware of SSHE Qualification severity of
- Alternate Sub-
25.15 systems process Incidents/ HSE and cascade requirements of
Contractors pre-
25.16 Incompetent accidents Project including and $ Weighted selection
personnel Ineffective Project Delay requirements
Poor SSHE culture cascading of Downgrade - Clear HSE Deliverables established
Contactor Contract SSHE SSHE incentive for Sub-Contractor
Leadership requirements Injury, damage, - Effective Induction & Training
4 4 16 (high)
“standoff” – Sub- delay Program and certification
Contractor Reputation verification
responsibility Incentive $ - Competent Supervision
Downgrade - Audit and Inspection corrective
action plans
- Sub-Contractor HSE Performance
reports and reviews
- Developed Project SSHE rules with
Company Life Saving Icons
Award / appointment of As above SA, SE, H, E Focused on No SSHE As above -
Fabrication & Offshore Productivity deliverables
Sub-Contractors Poor SSHE culture/ within Contract
attitude terms
Sub-Contractor Contracts
dispute department 4 4 16 (high) -
failure to review
Project Terms
and Conditions
for Sub-
Contractor T&CS
Work / Task Supervision 26.06 SA,H, E Poor SSHE Project Delay Injury -
25.13 Competency of Injury Damage
25.14 Supervisor Damage Delay
25.15 Stop Work conflicts Reputation
25.16 4 4 16 (high) -
with Company Incentive $
during execution Downgrade
phase
Productivity Focus
Onsite Transportation 29.01 SA, H, Pedestrians/ other Poor driver Injury -
21.15 vehicles competency / Damage
21.16 Speeding inability related to Delay
Unfit defensive driving Reputation
Drugs and Alcohol Poor vehicle Incentive $ 4 3 12 (medium) -
condition Downgrade
Lack of speed
limitations / Site
Rules
No MCU / UDAT
Work at Nights/ Overtime 25.14 SA Fatigue Ineffective work Injury -
25.15 Darkness / shadow planning Damage
25.16 Unfit No Policy for Delay
26.04 Overtime / Out Of Incentive $
26.05 3 3 9 (medium) -
hour working Downgrade
25.09 Lack of lighting
Lack of
supervision
Page 3 of 6
EPCI of Wellhead Platforms, Associated Pipelines and Brownfield Modifications for Zawtika Development Project Phase 1D PTTEPI/ ……………
Call for TENDER No. MMC20-5039 COMPANY’s preliminary SSHE Risk assessment Exhibit L Annex-3
Mobilization of personnel 25.13 SA, H Mismatch of work to Infective personnel Injury -
25.12 physical abilities assessment Damage
29.01 Unfit Lack of Supervision Delay
Lack of effective Incentive $
MCU Downgrade 3 3 9 (medium) -
Ineffective
Induction
No Green Hat
Policy
Work at Heights 6.01 SA Personnel at height Inadequate access Injury -
6.02 >2m arrangement Fatality
6.03 Personnel at height No WAH policy Damage
25.12 <2m Lack of Fall Reputation
Overhead equipment protection system Delay 4 3 12 (medium) -
Mismatch of work to Lack tool lanyard Incentive $
physical abilities Poor housekeeping Downgrade
No Cordon below
work
Lifting using Cranes & 6.03 SA Overhead equipment Competence Fatality -
Lifting using Mechanical 9.01 Bad weather/ winds/ No work area Injury
means other than cranes 15.04 lighting cordon Damage
Dropped object Bad weather Delay 4 3 12 (medium) -
Failure of equipment Lack of Impact Reputation
Nip point glove/ load control Incentive $
Lifting overhead Downgrade
Naked Flame Hot Work 31.0 SA, E Fire / explosion Gas cylinders leak Injury -
11.03 Use of propane / LPG Fuel storage Damage
2.03 Smoke/ Fumes Work conflicts Delay
2.04 Poor Housekeeping/ Incentive $ 3 3 9 (medium) -
3.01 combustibles Downgrade
19.06 Hot Sparks/ Slag
20.06
Use of Grinders/ Hand Held 8.04 SA Use of hazardous hand Gas cylinders leak Injury -
Grinding Machines 8.05 tools (grinding, sawing) Fuel storage Fatality
Equipment with moving Work conflicts Damage
or rotating parts Delay
Poor Housekeeping/ 4 4 16 (high) -
Fire / explosion Reputation
Use of propane / LPG combustibles
Incentive $
Disc failure Hot Sparks/ Slag Downgrade
Incorrect disc
Confined Space Entry 19.01 SA Insufficient oxygen Running Mobile plant Injury -
19.02 atmospheres Hot Work Fatality
20.02 Excessive CO2 Inadequate lighting Damage
25.09 Smoke/ Fumes (hot Entry to Restrictive/ Reputation
25.04 work/ exhausts0 enclosed space / Delay 5 4 20 (high) -
Darkness// Shadow Excavation Incentive $
Drowning / Water ingress Downgrade
Heat Stress
Page 4 of 6
EPCI of Wellhead Platforms, Associated Pipelines and Brownfield Modifications for Zawtika Development Project Phase 1D PTTEPI/ ……………
Call for TENDER No. MMC20-5039 COMPANY’s preliminary SSHE Risk assessment Exhibit L Annex-3
Pressure Shock/
Hammer
Cold surfaces
Page 5 of 6
EPCI of Wellhead Platforms, Associated Pipelines and Brownfield Modifications for Zawtika Development Project Phase 1D PTTEPI/ ……………
Call for TENDER No. MMC20-5039 COMPANY’s preliminary SSHE Risk assessment Exhibit L Annex-3
CONTRACTOR shall update for Offshore as part of Preparation Plan
Page 6 of 6