VISIBILITAS PENGERJAAN CFB (02 Agustus 2022)

Agustus September Oktober November Desember Januari


No Reg. Projek Nama Kegiatan Mulai Selesai

1 CFB02 Observasi Sub Sistem CFB02 2022-07-31 2022-08-02


2 CFB02 Pembuatan P&ID Sistem CFB02 2022-07-31 2022-08-02
2 CFB01 Penelitian Pendahuluan Nozzle 2022-08-02 2022-08-09
3 CFB01 Penelitian Pendahuluan Furnace & Cyclone 2022-08-10 2022-08-16
4 CFB02-HI01 Penelitian Pendahuluan HMI 2022-07-30 2022-08-04
5 CFB02-IC01 Penelitian Pendahuluan Instrumentasi 2022-08-05 2022-08-12
6 CFB02-FN01 Observasi sistem FD Fan 2022-08-12 2022-08-13
7 CFB02-FN02 Observasi sistem Seal R Fan 1 2022-08-15 2022-08-16
8 CFB02-FN03 Observasi sistem Seal R Fan 2 2022-08-17 2022-08-18
9 CFB02-FN04 Observasi sistem ID Fan 2022-08-19 2022-08-20
10 CFB02-BR01 Observasi sistem Burner 2022-08-22 2022-08-23
11 CFB02-SG01 Observasi sistem Steam Generator 2022-08-24 2022-08-25
12 CFB02-FR01 Observasi Furnace 2022-08-26 2022-08-27
13 CFB02-CY01 Observasi Cyclone 2022-08-29 2022-08-30
14 CFB02-JV01 Observasi J-Valve 2022-08-31 2022-09-01
15 CFB02-DN01 Observasi Drain 1 2022-09-02 2022-09-03
16 CFB02-DN02 Observasi Drain 2 2022-09-05 2022-09-06
17 CFB02-SF01 Observasi Screw Feeder 2022-09-07 2022-09-08
18 CFB02-DS01 Observasi Distributor 2022-09-09 2022-09-10
19 CFB02-HI01 Observasi sistem HMI 2022-09-12 2022-09-13
20 CFB02-IC01 Observasi sistem Instrumentasi & Controller 2022-09-14 2022-09-15
21 CFB02-WP01 Observasi kebutuhan power listrik dan Pengkabelan 2022-09-16 2022-09-17
22 CFB02-FN01 Rancang bangun sistem FD Fan 2022-09-19 2022-09-24
23 CFB02-FN02 Rancang bangun sistem Seal R Fan 1 2022-09-26 2022-10-01
24 CFB02-FN03 Rancang bangun Seal R Fan 2 2022-10-03 2022-10-08
25 CFB02-FN04 Rancang bangun ID Fan 2022-10-10 2022-10-15
26 CFB02-BR01 Rancang bangun Burner 2022-10-17 2022-10-22
27 CFB02-SG01 Rancang bangun sistem Steam Generator 2022-10-24 2022-10-29
28 CFB02-FR01 Rancang bangun Furnace 2022-10-31 2022-11-05
29 CFB02-CY01 Rancang bangun Cyclone 2022-11-07 2022-11-12
30 CFB02-JV01 Rancang bangun J-Valve 2022-11-14 2022-11-19
31 CFB02-DN01 Rancang bangun Drain 1 2022-11-21 2022-11-26
32 CFB02-DN02 Rancang bangun Drain 2 2022-11-28 2022-12-03
33 CFB02-SF01 Rancang bangun Screw Feeder 2022-12-05 2022-12-10
34 CFB02-DS01 Perancang bangun Distributor 2022-12-12 2022-12-17
35 CFB02-HI01 Perancang bangun sistem HMI 2022-12-19 2022-12-24
36 CFB02-IC01 Perancang bangun sistem Instrumentasi & Controller 2022-12-26 2022-12-31
37 CFB02-WP01 Perancang bangun power listrik dan Pengkabelan 2023-01-02 2023-01-07
38 CFB02 Pengujian Sistem CFB 2023-01-09 2023-01-14