TRANSMITTAL FORM
CGC/TRS/439
Date: 27 August, 2014
Subject: Method Statement of Tie-ins for Portable Water and Sanitary Waste Water
Line
Site Development of Logistics Area for Jubail 2
Project Manager
1 of 1
Wasel Box2648- Jubail35513- Tel.! Fax. 3443260- ~.S,A. :i.J->_,...11 ~~~ '-SWI->Hni • <J&l/W."-- roo\\' ~I -~HAt.,.> ,J,...\3
. Email: cgc@cgcsaudi.com :~_,_fo':il ~,Y.ll
f\ c:_c:..:i ...J-:!.:i-=:--.:i I ...9-:!-=?- l.:i-:! l.....t ~S. _;.....t e_ ...J~
cI.JJ c r::p ~ :l:t!!. lW-i .:r:. 51<~ ~ Btl ~ ~
46~_:-._ CHINA GEO.ENGINEERING CORPORATION (SAUDI) BRANCH
TRANSMITTAL FORM
Subject: Method Statement of Tie-ins for Portable Water and Sanitary Waste Water
Line
Site Development of Logistics Area for Jubail2
Project Manager
I of I
Wasel Box 2648- Jubail35513- Tel. I Fax. 3443260- K.S.A. ~_,.....11 ~,_,.Jil.SWI-lf trn • u&f...:.,"V.- roo\ r t..l,;.;JI - n fAy ,J...,IJ
Email: cgc@cgcsaudi.com :~.,jiS~I .>,!yll
Royal CotllilllSSlOll for Jubail & Yanbu
Contract ~o .: 270-C02
Site D evelopment ofL ogist1cs Area for Jubai1 2
China Geo-Engineering Corporation Saudi Branch
1/14
TABLE OF CONTENTS
3. REFERENCE ....................................................................................................... 4
4. EQUIPMENT TO BE USED............................................................................... 4
5. MATERIALS ........................................................................................................ 4
2/ 14
1. SCOPE OF WORK
The purpose of this method statement is to provide the sequence and methodology for
the construction of tie-in with Marafiq for Site Development of Logistics Area for
Jubail 2, Contract No. 270-C02. This method statement will be in compliance with the
contract requirements and project specifications. The tie-in covers the installation of
pipe and valves for potable and sanitary water and construction of valve chamber.
Permission obtainment
Soil excavation
Thrust block
Testing
2. ABBREVIATIONS &DEFINITION
3/ 14
3. REFERENCE
Approved ITPs
RC Guidline Specification:
4. EQUIPMENT TO BE USED
Dump Truck
Excavator
Compactor
Heating Blankets
Temperature Controller
Generator 25/50 KW
5. MATERIALS
RTRP Pipes
Pipe Fittings
4/ 14
Valves
Warning Tape
Joint Materials
6. TIE-IN LAYOUT
PWlineRTRP DN250 will connect with the existing DN700 PW line in VC – 16A
under contract number 138-C02R where is at the north of Road T-274 opposite lot 10.
and a VC will be constructed under this project at the other connection pointwhere is
at the intersection Road T-274 and Road T-301. At this location PW line RTRP
SWWline RTRP DN150 which is dicharge pipe for LS-04 will connect with the
existing Manhole SWW 311-MH-06 which location is north of T-274 opposite lot 9.
5/ 14
SWW line tie-in detail at north of T-274 opposite lot 9
6/ 14
7. PREPARATION& PLANNING
As per Marfa requirements, the permit will be required while we start the performance
of tie-in for PW and SWW line. The performance will be conducted when the permit
or partly.
One (1) set of Original white prints Drawings (Signed & Stamped) & Two (2)
copies.
Original (4) sets of O&M Manuals (Hard copies arranged in Box files)
7/ 14
OriginalHydro test report/ Certificate (Soft & Hard Copy)
7.2.4. Excavation
The sequence of work for PW line is similar to SWW line, but the VC – 01 at
intersection Road T-274 and Road T-301 tie in will be precast at the location near the
When we start the work of tie in, One civil teamwhich is for precast of VC-01 will be
8/ 14
Field Civil Engineer 1 Qi Lei 0558986101
Surveyor 1 Gao Erfeng 055 306 5164
Foreman for Civil Work 1 Mohamed 0557478549
Foreman for Mech. Work 1 Riku 0502719315
Carpenter 2
Steel Fixer 2
Mason 2
GRP Laminator 3
Pipe Fitter 4
Labor 8
8.1. Material for civil works i.e. rebar, timber, scaffolding tube will be transported
8.4. Pipe, fittings and prefabricated parts will be transported by the suitable trucks
8.6. Tie the products in place by using nylon or canvas sling belts while loading or
unloading.
8.8. Standard pipe lengths shall be lifted at minimal two supporting points.
8.9. Protect internal parts against rust and corrosion while shipping of valve.
8.10. Set butterfly valves closed or slightly open while storing valve.
8.11. Use sling to handle butterfly valve and other accessary which will be
9/ 14
8.12. Do not use hand wheels and stems of valve as lifting or rigging points.
9. PROCEDURE OF WORKS
As mentioned before, there are 3 tie-ins in the project. The sequence of construction is
as follows.
9.1. Construction for PW Line Tie-in at Intersection Road T-274 and Road T-30
The site will be make levelling for fabrication according to the requirements. The
valve chamber VC-01 will be precast on site.We plan to fabricate it dividing into
three portions.The first portion is for the base slab to the center of pipe where the
level is 5.60m, the second portion is from level 5.60m up to 7.30m which is the top of
top slab, and the third portion is for top slab. The fabrication sequencesare as shown
The RC standard and ITP approved will be followed strictly when precast the valve
chamber.
10/ 14
After finishing the fabrication of VC-01 and obtaining the permit form Marfa, we will
start excavation. As per the underground utilities information from Marfa and other
department, we will dig the soil using the excavator firstly, and excavating manually
The lean concrete will be placed when the FDT of subgrade is positive.
The VC will be shifted to the correct position where the lean concrete has been cast.
The weight of first portion for the base slab will be 80T, and will be lifted by crane
150T hired from local market. And the second portion for the wall of VC will be 50T.
RTRP pipe and valves will be fixed after finishing installation of the precast VC.
RTRP pipe and valves installation will follow the related method statement and the
RC standard.
The installation of waterproofing membrane for the external concrete wall will follow
the instruction from supplier and refer to the related civil work method statement.
Backfill shall not be placed until all items have been inspected by the
No backfill shall be placed until concrete has developed strength of notless than 15
9.2. Construction for PW line tie-in at the north of Road T-274 opposite lot 10 and
11/ 14
SWW line tie-in detail at north of T-274 opposite lot 9
These connections will be similar to the tie-in at Intersection Road T-274 and Road
T-30. The soil excavation will be conducted and the pipesand valves installation will
installed gradually.
All mechanical and civil inspection will be performed as per ITPs approved by RC.
10.1. Prior to commencing any earthworks or excavation etc., the permit will be
10.2. Tool box meeting will be conducted by supervisor or foreman every morning,
10.3. Where possible hazards may arise during installation activities, the necessary
10.4. Safety measures will be taken to prevent accident or injury at all times. This
may include barriers, warning tape/ net, signage, flagman, and proper lighting.
10.6. Provision of adequate cool drinking water, shade, and salt water tablets will be
inplace.
10.7. Ensure that all traffic management is set up correctly to comply with
localregulations.
10.8. During the lamination works, the technician will be prohibited strictly smoking.
10.9. Lifting plan will be prepared by competent person. And lifting plan for the load
10.10. The lifting plan will be prepared and submitted for RC review and approval
10.11. The contractor shall undertake all works in accordance with appropriate
12/ 14
Environmental requirements.
13/ 14
Piping Works Fire Assign a man to control the
chemical material such as resin
and woven roving glass etc.
Lifting Work Mechanical/ Hydraulic/ Annual 3rd party Inspection
Structural Daily Operator Inspection
Incorrect Selection of Crane Appointed Competent Person
lifting Plan
Lifting Work INADEQUATE: Lifting Calculation
Capacity Lift Plan
Lift Height Qualified Rigger
Rigging
Lifting Work Load Fastening Failure Lift Plan
Design Calculations
Lifting Work Manufacturer Failure Manufacturer’s Servicing
Instruction
Lifting Work Environment: Manufacturer’s Instructions
Temperature Lifting Plan Method Statement
Lighting Permit to work
Overhead Power Lines Goal Posts
Soil Conditions Geotechnical Survey
Underground Services Lifting Plan - Drawings