Professional Documents
Culture Documents
Report Pipariya
Report Pipariya
Table of Content
1. EXECUTIVE SUMMARY
Pipariya is a Nagar Palika and situated in District Hoshangabad of Madhya Pradesh. Co-ordinate of
town is 22°45'16.31"N & 78°21'23.65"E. Population of Pipariya is 48826 as per census 2011. For the
present scheme, base year, intermediate year and ultimate design year is taken as 2025, 2040 and
2055 respectively. At present, there is water supply scheme in Pipariya town that was executed in year
2016. At present, provision of water in Pipariya is given by surface water source.
Water in Pipariya is supplied by the 13.89 MLD of Intake Well at Narmada River at co-ordinate
22°54'59.74"N & 78°20'14.22"E. There are Raw Water Rising Mains of length 21 KM of dia range 400
mm of DI K-9 is laid in Pipariya, from where water is transported from Intake Well to WTP.
There are 10.56 MLD of WTP in Pipariya at co-ordinate of 22°45'10.91"N & 78°21'2.75"E that treat
raw water from intake well, from where water is transported to different OHTs at Pipariya by pumping.
There are Clear Water Feeder Mains of length 18 KM of dia range 150-400 mm of DI K-9 is laid in
Pipariya, from where water is transported from WTP to various OHTs.
In Pipariya, there are 6 number of OHT of cumulative capacity 3600KL, from where water is supplied
to residents of Pipariya.
In Pipariya, distribution network is laid in last water supply scheme of total length 90 KM. There are
5936 number of house service connection in Pipariya.
In the present scheme under AMRUT 2.0, base year, intermediate year and ultimate design year is
considered as 2025, 2040 and 2055 respectively. Water demand for the same years is calculated as
11.25MLD, 13.75MLD and 16.75 MLD respectively by considering 135LPCD water demand as per
guidelines from UADD, GoMP. Thus, installed capacity of Intake Well and WTP is sufficient to feed
water for intermediate design year.
As per discussion with ULB engineer, in Ward-1, 2, 3, 4, 5, 8 and 13, water is not supplied properly in
term of quantity. Command are of these OHT is confirm by site visit as well and verified by the ULB
engineer. Thus, two number of OHT is proposed in Pipariya of capacity 2000KL and 150KL and clear
water feeder mains of for these both 2 OHTs.
Clear water feeder mains of length 3241m of dia 100mm and 300mm of DI K-9 is also proposed to
feed these OHT from WTP. A separate pumping machinery (1W+1S) of discharge 32.42LPS and 42m
head is also proposed to feed proposed OHT.
Total house service connection proposed in AMRUT 2.0 is 6857.
The detail estimate of proposed component is prepared on UADD SOR 2019. Total net cost of the
scheme is estimated as 562.99 Lakhs. Period for construction is estimates as 12 months.
The project shall be executed by availability of 50% grant by Government of India, 45% grant by
Government of Madhya Pradesh and 5% share will be of ULB itself.
Yash Engineering Consultants Pvt Ltd is appointed as consultant as per work order from Pipariya Nagar
Palika. All the existing water supply data is collected from Nagar Palika, Pipariya. However, if any
discrepancy, it is kindly requested you to bring in our notice.
Particulars Details
Name of
AMRUT (Phase-2)
Project
Town,
Pipariya, Hoshangabad, Madhya Pradesh
District, State
Population
Year 2011 = 48826 Souls
(2011)
Household
10225
(2011)
Ward covered
under pipes All ward covered
water supply
Base year (2025) = 61090
Population
Intermediate year (2040) = 76240
Forecast
Ultimate Design Year (2055) = 93490
Existing Municipal Water Supply System
Name of Source Narmada River
Intake Well Capacity (MLD) 13.89
Location (Co-ordinate) 22°54'59.74"N & 78°20'14.22"E
Type of Pump VT Pump
Raw Water Number of pump (W
2W+1S
Pumping + S)
Machinary Head (m) 25
Pump capacity (KW) 50
Year
Dia Length Pipe
Raw Water of From To
(mm) (m) Material
Rising Mains laying
400 21000 DI K-9 2016 Inatke WTP
Type Conventional
WTP
Capacity (MLD) 10.56
Clearwater Number of pump (W
3
Pumping + S)
Machinery Pump capacity (KW) 50
Clear Water
DI K-9 18 km (150-450mm)
Feeder Mains
Capacity S.H.
650 15
650 18
Over Head 900 18
Tank 700 15
450 18
250 18
Total caapcity (KL) 3600
Particulars Details
Municipal
Ward covered under
Water Partial covered
municipal water supply
Coverage
Proposed Component in AMRUT 2.0
Dia Length Proposed/ Existing
Clear Water 300 3119 Proposed
DI K-9
Feeder Mains 100 122 Proposed
Total Length (m) 3241
Staging
Sr. No. OHT Capacity Height Proposed/Existing
OHT Details (m)
1 150 18 Proposed
2 2000 18 Proposed
HSC 6857
3. INTRODUCTION
Madhya Pradesh, the central state of the country, is geographically the second largest State
of the country. It covers almost 9.5 per cent of the area (308,000 Sq. Km.) and 6 per cent (72.5
million) of country’s total population. On the basis of the size of urban population, it ranks
8th and accounts for 5.58 per cent of the total urban population of India. According to the
2011 Census, MP registered 20.30 % decadal growth in urban population against the national
average of 17.64 %. In Madhya Pradesh, the decadal urban growth is much higher than (25.6
%) its rural counterpart (15.5 %). The 378 Urban Local Bodies of Madhya Pradesh
accommodate 20.1 million urban populations which accounts for 27.6 per cent of the total
population of MP.
Owing to the emergence of new towns within the proximity of large cities, new centers of
industrial and commercial activities, thermal power stations and partly creation of new urban
local bodies depicts faster growth in number of towns in the last one decade in comparison
to the national average. The number of towns in the State has increased from 253 in 1981, to
350 in 1991, 368 in 2001 and 476 in 2011.
Increase the amenity value of cities by developing greenery and well maintained open spaces
(e.g. parks) and
Reduce pollution by switching to public transport or constructing facilities for non-motorized
transport (e.g. walking and cycling). All these outcomes are valued by citizens, particularly
women, and indicators and standards have been prescribed by the Ministry of Housing and Urban
Affairs (MoHUA) in the form of Service Level Benchmarks (SLBs).
Earlier, the MoHUA used to give project-by-project sanctions. In the AMRUT this has been
replaced by approval of the State Annual Action Plan once a year by the MoHUA and the
States have to give project sanctions and approval at their end. In this way, the AMRUT makes
States equal partners in planning and implementation of projects, thus actualizing the spirit
of cooperative federalism. A sound institutional structure is a foundation to make Missions
successful. Therefore, Capacity Building and a set of Reforms have been included in the
Mission. Reforms will lead to improvement in service delivery, mobilization of resources and
making municipal functioning more transparent and functionaries more accountable, while
Capacity Building will empower municipal functionaries and lead to timely completion of
projects.
Bodies (ULBs) will strive to include some smart features in the physical infrastructure
components. The details of the Mission components are given below:
Water Supply
Water supply systems including augmentation of existing water supply, water treatment
plants and universal metering.
Rehabilitation of old water supply systems, including treatment plants.
Rejuvenation of water bodies specifically for drinking water supply and recharging of ground
water.
Special water supply arrangement for difficult areas, hill and coastal cities, including those
having water quality problems (e.g. arsenic, fluoride)
Sewerage
Decentralised, networked underground sewerage systems, including augmentation of existing
sewerage systems and sewage treatment plants.
Rehabilitation of old sewerage system and treatment plants.
Recycling of water for beneficial purposes and reuse of wastewater.
Urban Transport
Footpaths/ walkways, sidewalks, foot over-bridges and facilities for non-motorised transport
(e.g. bicycles).
Multi-level parking.
Green Space/Park
Development of green space and parks with special provision for children, senior citizens and
Divyang friendly components
implementation of Jal Jeevan Mission (u) in Pipariya in order to coverage of 100% population
of entire town with piped water supply scheme, improvement of city groundwater table,
improvement of existing water bodies and subsequently improvement of sanitation of town.
Population of Pipariya is 48826 as per 2011 census and project area is 1.16 SqKm. Pipariya is
situated in District Pipariya district and situated on the 22°45'16.31"N & 78°21'23.65"E.
4. Technical Report
Water in Pipariya is supplied by the 13.89 MLD of Intake Well at Narmada River at co-ordinate
22°54'59.74"N & 78°20'14.22"E. There are Raw Water Rising Mains of length 21 KM of dia range 400
mm of DI K-9 is laid in Pipariya, from where water is transported from Intake Well to WTP.
There are 10.56 MLD of WTP in Pipariya at co-ordinate of 22°45'10.91"N & 78°21'2.75"E that treat
raw water from intake well, from where water is transported to different OHTs at Pipariya by pumping.
There are Clear Water Feeder Mains of length 18 KM of dia range 150-400 mm of DI K-9 is laid in
Pipariya, from where water is transported from WTP to various OHTs.
In Pipariya, there are 6 number of OHT of cumulative capacity 3600KL, from where water is supplied
to residents of Pipariya. In Pipariya, distribution network is laid in last water supply scheme of total
length 90 KM. There are 5936 number of house service connection in Pipariya.
In the present scheme under AMRUT 2.0, base year, intermediate year and ultimate design year is
considered as 2025, 2040 and 2055 respectively. Water demand for the same years is calculated as
11.25MLD, 13.75MLD and 16.75 MLD respectively by considering 135LPCD water demand as per
guidelines from UADD, GoMP. Thus, installed capacity of Intake Well and WTP is sufficient to feed
water for intermediate design year.
As per discussion with ULB engineer, in Ward-1, 2, 3, 4, 5, 8 and 13, water is not supplied properly in
term of quantity. Thus, two number of OHT is proposed in Pipariya of capacity 2000KL and 150KL and
clear water feeder mains of for these both 2 OHTs. Total house service connection proposed in AMRUT
2.0 is 6857.
40000
30000
20000
10000
0
1975 1980 1985 1990 1995 2000 2005 2010 2015
In this method, the population curve of the Nagar Parishad (i.e., the population vs. past
decades) is smoothly extended for obtaining values for the future. The line of best fit has
been obtained by the method of least squares. Based on this comparison, a graph of
populations versus decades is plotted and extrapolated.
Semi Log Curve Method
y = 21298e0.2221x
50000 R² = 0.9535
5000
1981 1991 2001 2011
Thus, total water demand is calculated as 11.25MLD for base year, 13.75MLD for intermediate
design year and 16.75MLD for ultimate design year.
5.7 Appurtenances:
On line valves are provided in larger mains at 500 m to 1.5 km interval to facilitate repairs.
Non rising spindle Sluice valves are used for isolating or scouring and not intended for
continuous throttling as erosion of the seats and body cavitation may occur. Butterfly valves
are used to regulate and stop the flow. In large size butterfly valves are cheaper and occupy
less space. These may involve higher friction loss than sluice valve. Also not suitable for
continuous throttling. Sluice valve and butterfly valve for higher sizes require geared hand
wheel or power driven actuators. Scour valves are provided in valleys / depressions to
dewater pipe line. Air valve size is one fourth to on sixth of pipe diameter. Kinetic air valves
are used to release air entrapped during running of pipe line. Pressure relief valves, Check
valves, Pressure Reducing Valves, Ball Float Valves, Shut off valves are used for specific
purposes.
Losses during test shall be less than 0.1 litre per mm of pipe dia per KM of pipeline per day
for each 30 metre head of pressure applied.
Chemical Storage
A storage of 3 months is advisable. In cases where major storage is provided at a place away
from the feed equipment, a week’s storage space should be provided near the plant. Storage
should be damp proof & properly drained. For chemicals in bag, stack height should not
exceed 2 m.
In circular tanks where mechanical scrappers are provided, the floor slopes should not be
flatter than 1 in 12, to ensure continuous and proper collection of sludge. For manual cleaning
slope should be above 1 in 10.
Filtration
Rapid Gravity Filters (RGF): The distinctive features of RGF compared to slow sand filtration is
careful pre-treatment, higher filtration rate, coarser but more uniform filter media,
backwashing by reversing flow. Standard filtration rate is 4.8-6 m/hour. Practice is tending
towards higher rate (upto 10 m/hour) with better pre-treatment and use of coarser sand
(effective size 1mm). Maximum area of one filter bed 100 Sqm consisting of two halves of 50
sqm is recommended for plants greater than 100 mld. Also for flexibility of operation a
minimum of 4 beds should be provided which can be reduced to 2 for smaller plants. Where
filters are located on both sides of a pipe gallery, length to width ratio of filter bed is found to
be 1.11 to 1.66 averaging about 1.25 to 1.33. A minimum overall depth of 2.6 m including free
board of 0.5 m is adopted. It is not necessary to provide roof over the filters. The operating
gallery should be roofed. Effective size of sand shall be 0.45 to 0.7 mm, uniformity coefficient
1.7 to 1.3, ignition loss should not exceed 0.7% by weight, soluble fraction in hydrochloric acid
shall not exceed 5% by weight, silica content not less than 90%, specific gravity 2.55 to 2.65
and wearing loss shall not exceed 3%. Usually depth of sand should be 0.6 to 0.75 m but for
higher rate filtration when coarse medium is used deeper sand beds are suggested. Standing
depth of water over filter varies from 1 to 2 m and free board of 0.5 m.
Size of gravel varies from 50 mm at bottom to 2 to 5 mm at the top with a depth of 0.45 m.
In case of porous plate floor supported on concrete pillars, bottom gravel not required.
Disinfection
Satisfactory disinfection is obtained by pre-chlorination to maintain 0.3 to 0.4 mg/l free
available residual throughout treatment or 0.2 to 0.3 mg/l free available residual in the
plant effluent at normal pH values. At higher pH of 8 to 9 at least 0.4 mg/l is required for
complete bacterial kill with 10 minutes contact time. For 30 minute contact time dosage
reduces to 0.2 to 0.3 mg/l.
5.16 Pumping
NPSH available (suction pressure-friction loss in foot valve, suction pipe and fittings-velocity
head at suction face-suction head-vapour pressure) should be higher than the NPSH required.
Piping: Suction pipe should be short and straight, bends of long radius, size one or two sizes
larger than nominal suction of pump, use eccentric reducer so that no point on suction pipe
is higher than suction part of pump, velocity in suction pipe 2 m/sec, velocity in bell mouth
1.5 m/sec, suction strainer should have area at least 3 times area of suction pipe. Discharge
pipe may be one size higher than pump delivery; velocity may be 2.5 m/sec, discharge piping
connection to a common header by a radial tee or 30-45 degree bend. Dismantling joint be
provided between pump and valve. Valves: In case of suction lift provide foot valve. Provide
vacuum pump priming when suction pipe larger than 300 mm. In case of positive suction head
sluice valve or butterfly valve is provided in suction pipe for isolation. In delivery pipe a non-
return valve (NRV) and delivery valve i.e. sluice/butterfly valve should be provided. NRV
should be between pump and delivery valve. Size of valve should match size of pipe.
Pump House Size: Minimum space between two adjoining pumps or motor should be 0.6 m
for small and medium units and 1 m for large units. A clear space of 915 mm in width shall be
provided in front of switch board. If there are any attachments or connections at the back of
switch board space behind shall be either less than 230 mm or more than 750 mm in width
measured from farthest part of attachment/conductor. Service bay for overhauling/repairs
should be provided to accommodate largest equipment. A ramp or a loading unloading bay
should be provided. Head room and material handling tackle for vertical pump should be able
to lift, dismantle and carry motor and largest column assembly to maintenance bay.
to 200mm OD; butt welding for higher sizes with local fabricated joints. HDPE PE100 PN10
Class up to 300mm size and DI K9 class for higher sizes
As per discussion with ULB engineer, entire area of Pipariya is covered with water supply scheme.
There are six number of OHT in Pipariya, by which water is supplied to entire area. Thus, on the basis
of OHT, entire Pipariya town is divided in six water distribution zone.
As per discussion with ULB Engineer as site visit, there are two zone, where OHT capacity is insufficient.
The ward covered in these two zone is Ward-1, Ward-2, Ward-3, Ward-4, Ward-5, Ward-8 and Ward-
13. In one zone (mentioned here is Zone-1) is covered and in other zone (mentioned here is Zone-2)
Ward-1, Ward-2, Ward-3, Ward-4, Ward-5 and Ward-8 is covered. Population details of these two
zone is given as below:
For covering these two zone, following water supply component is proposed:
Two number of OHT in zone -1 and Zone-2 of capacity 150KL and 2000KL is proposed under AMRUT2.0.
Calculation capacity of OHT is given in below pages:
Multiplying Factor
Start End Multiplying Water Water Surplus
ive ive
Hour Hour Factor Inflow Outflow / Deficit 2
Inflow Outflow
Total 24 353705 353705 (Ltr/Hr) (Ltr/Hr)
0 1 0.2 0 2948 0 2948 -2948 1.5
1 2 0.2 16077 2948 16077 5895 10182
2 3 0.2 16077 2948 32155 8843 23312 1
Multiplying Factor
Start End Multiplying Water Water Surplus
ive ive
Hour Hour Factor Inflow Outflow / Deficit 2
Inflow Outflow
Total 24 4780931 4780931 (Ltr/Hr) (Ltr/Hr)
0 1 0.2 0 39841 0 39841 -39841 1.5
1 2 0.2 217315 39841 217315 79682 137633
2 3 0.2 217315 39841 434630 119523 315107 1
Clear Water Feeder Mains of length 3300m of dia range 150mm-400m is also proposed under AMRUT
2.0.
Rate of Total
Pipe Design Design
Start End Length Velocity HW Pipe Head Head
/ Flow Dia
Node Node (m) (m/s) Constant Material Loss Loss
Link (l/s) (mm)
(m/km) (m)
CWS-
P-2 PMP 14 78.87 1.12 300 133 DI 3.968 0.05
WTP
P-3 PMP J-1 1558 78.87 1.12 300 133 DI 3.969 6.18
OHT-
P-5 J-1 1547 73.44 1.04 300 133 DI 3.478 5.38
2
OHT-
P-4 J-1 122 5.43 0.69 100 133 DI 5.895 0.72
1
CWS-
P-2 PMP 14 64.84 0.92 300 133 DI 2.762 0.04
WTP
P-3 PMP J-1 1558 64.84 0.92 300 133 DI 2.761 4.3
P-5 J-1 OHT-2 1547 60.37 0.85 300 133 DI 2.419 3.74
P-4 J-1 OHT-1 122 4.47 0.57 100 133 DI 4.112 0.5
Separate pumping machinery is proposed for proposed two number of OHT as existing pumping
machinery is not sufficient. Separate sump at WTP campus is also proposed of 250KL capacity by
considering 1 Hour retention time.
Total number of House hold in base year 2025 is forecasted as 12793. Total number of existing house
service connection is 5936, thus 6857 new house service connection is proposed in AMRUT.
7. Estimate