Assigning Relationships in P6
Planningschool.net
Assigning Relationships in P6
Relationships
Manually in P6 By Excel
Assign Using Predecessor ID,
“Link Activities”
Predecessors / Successor ID, Relationship
Option
Successors Type, & Lag
01
Assigning Relationships in P6
1. Assign Predecessors / Successors:
• Assign Predecessors (or Successors) by clicking on “Assign” & selecting the required predecessor
(or successor)
02
Assigning Relationships in P6
1. Assign Predecessors / Successors (Cont.):
Right Click on the activity and select assign Predecessors / Successors and select one or multiple predecessor / successor
03
Assigning Relationships in P6
2. Right Click & Link Activities:
Select the predecessor first, then select successor(s) in
• Select the activities to be linked together in
the required order while pressing CTRL, then right click and
the required order (for example if I need
select “Link Activities”
Activity (B) to Start after completion of
Activity (A); then I should select Activity (A)
first then Activity (B) next and so on)
04
Assigning Relationships in P6
3. By Excel
05
Assigning Relationships in P6
3. By Excel (Cont.)
06
Assigning Relationships in P6
3. By Excel (Cont.)
07
Assigning Relationships in P6
3. By Excel (Cont.)
• In the exported sheet; insert (or adjust) the Activity ID of predecessor, the Activity ID of successor,
relationship type (FS,SS,FF,SF), lag, & status of predecessor and successor (Not Started, In
Progress, Completed) as shown below then save the file
08
Assigning Relationships in P6
3. By Excel (Cont.)
09
Assigning Relationships in P6