1. Engineering will put together the DCAP package of all engineering drawings, specifications, and attachments.
2. Engineering will create the electronic requisition in CostPoint for all requisitions initiated by Engineering as these items are finalized and need to be
quoted (i.e. sent to Purchasing).
3. Engineering will wait for the e-req to be fully approved in CostPoint (they will receive notification when req is approved).
4. Engineering will then print a PDF of the req for inclusion in the package.
5. The package will then be distributed to all on list for approval as per current process.
Costpoint Process
Step A – Log into Costpoint
Access to Costpoint is thru the following Link https://citrixapps.babcockpower.com/Citrix/Babcock-StoreWeb
OR
1) “Identification” data
a. “Requisition ID” – Enter the normal Engineering Long Lead item requisition number; Example L121116101
b. “Rev” = “0” Default and should not require change.
c. “Approval Process” = (Click on magnifying glass and then enter Project Manager from the below list)
i. BACONLL – Bill Arwood / Condenser
ii. BAFWHLL – Bill Arwood / FWH
iii. BAMSXLL – Bill Arwood / MSR/IPX
iv. GACONLL – Grant A / Condenser
v. GAFWHLL – Grant A / FWH
vi. GAMSXLL – Grant A / MSR/IPX
vii. JLCONLL – Jear / Condenser
viii. JLFWHLL – Jear / FWH
ix. JLMSRXLL – Jear / MSR/IPX
x. SLKCONLL – Dave S / Condenser
xi. SLKFWHLL – Dave Slack / FWH
xii. SLKMSXLL – Dave Slack / MSR/IPX
xiii. STKCONLL – Dan S / Condenser
xiv. STKFWHLL – Dan S / FWH
xv. STKMSXLL – Dan S / MSR/IPX
d. “Status” = “Pending” until “Submit for Approval” is selected when ready to distribute.
• Click on “more values” and a full listing of available options will appear.
b. Update the “Organization” in this tab to agree with product area. (NO NOT update “Organization” in the “Header” tab)
• Open the pull-down menu and select appropriate “Organization” with “(POC)” in the “Org Name”
a. Can enter Requested Date (due date materials needed on site, start date for subcontractors, etc) This can be modified later.
• If unknow, leave blank.
b. Leave all other fields blank.
f)
g) Enter data in appropriate fields and add lines or modify similar to requisition lines.
c.
d. Look for “Message(s) at bottom of screen with input Error(s) and Warnings listed.
i. Saving may not be possible until all error and messages are resolved.
e. Click on “Open”
a)
d)
e)
f) Printing will now require the “In Approval” box be checked.
g)