S C H E D U L E O F M V A C W O R K

2 0 1 5 2 0 1 6
No. Description September October November Desember Januari Februari Maret April May Juni Juli August September November
2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4
1 Preaperation

2 Submitel data & Xample product

3 Shopdrawing process

4 Submitel drawing

5 Material for intallation on site

6 Fabrication & Installation ;


Ducting installation
Pipe installation
Testing Installation

7 Material & equipment mechine on site

8 Setting & installation mechine

9 Testing & commisioning

10 As built drawing

11 Finish
2 0 1 7
Desember Januari Februari Maret April May Juni Juli August September November Desember
5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5
SCHEDULE MVAC DUCK WORK & PIPE WORK

No. Description START FINISH DURATION O C T O B E R N O V E M B E


24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
I LANTAI - 6 ( DUCT WORK )
1 ZONA - A
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
2 ZONA - B
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
3 ZONA - F
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
4 ZONA - G
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
5 ZONA - K
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
6 ZONA - L
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
II LANTAI - 6 ( PIPE WORK )
3 ZONA - F
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
4 ZONA - G
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
5 ZONA - K
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
NOT YET COUNTRUCTION
2 0 1 5
R D E S E M B E R
20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
SCHEDULE MVAC DUCK WORK & PIPE WORK

2 0 1 5
No. Description Start Finish Duration O C T O B E R N O V E M B E R
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
I LANTAI - 5 ( DUCT WORK )
1 ZONA - A
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
2 ZONA - B
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
3 ZONA - F
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
4 ZONA - G
Pemasangan installasi ducting
Request MOS
Pemasangan AHU,FCU,FAN
Pemasangan MCC Panel
Testing
5 ZONA - K
Pemasangan installasi ducting
Request MOS
Pemasangan AHU,FCU,FAN
Pemasangan MCC Panel
Testing
6 ZONA - L
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
II LANTAI - 5 ( PIPE WORK )
1 ZONA - A
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
TESTING
2 ZONA - B
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
TESTING
3 ZONA - F
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit AHU
TESTING
4 ZONA - G
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit FCU & AHU
TESTING
5 ZONA - K
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit FCU & AHU
TESTING
6 ZONA - L
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit AHU
TESTING
NOT YET COUNTRUCTION
2 0 1 6
D E S E M B E R J A N U A R I
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
SCHEDULE MVAC DUCK WORK & PIPE WORK

2 0 1 5
No. Description Start Finish Duration O C T O B E R N O V E M B E R
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5
I LANTAI - 4 ( DUCT WORK )
1 ZONA - A
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
2 ZONA - B
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
3 ZONA - F
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
4 ZONA - G
Pemasangan installasi ducting
Request MOS
Pemasangan AHU,FCU,FAN
Pemasangan MCC Panel
Testing
5 ZONA - K
Pemasangan installasi ducting
Request MOS
Pemasangan AHU,FCU,FAN
Pemasangan MCC Panel
Testing
6 ZONA - L
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
II LANTAI - 4 ( PIPE WORK )
1 ZONA - A
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
TESTING
2 ZONA - B
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
TESTING
3 ZONA - F
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit AHU
TESTING
4 ZONA - G
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit FCU & AHU
TESTING
5 ZONA - K
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit FCU & AHU
TESTING
6 ZONA - L
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit AHU
TESTING
NOT YET COUNTRUCTION
2 0 1 6
D E S E M B E R J A N U A R I
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
SCHEDULE MVAC DUCK WORK & PIPE WORK

2 0 1 5
No. Description Start Finish Duration O C T O B E R N O V E M B E R
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8
I LANTAI - 3 ( DUCT WORK )
1 ZONA - A
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
2 ZONA - B
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
ZONA - C
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
3 ZONA - D
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
4 ZONA - F
Pemasangan installasi ducting
Request MOS
Pemasangan AHU,FCU,FAN
Pemasangan MCC Panel
Testing
5 ZONA - G
Pemasangan installasi ducting
Request MOS
Pemasangan AHU,FCU,FAN
Pemasangan MCC Panel
Testing
ZONA - H
Pemasangan installasi ducting
Request MOS
Pemasangan AHU,FCU,FAN
Pemasangan MCC Panel
Testing
6 ZONA - K
Pemasangan installasi ducting
Request MOS
Pemasangan AHU,FCU,FAN
Pemasangan MCC Panel
Testing
7 ZONA - L
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
II LANTAI - 3 ( PIPE WORK )
1 ZONA - A
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
TESTING
2 ZONA - B
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
TESTING
3 ZONA - F
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit AHU
TESTING
4 ZONA - G
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit FCU & AHU
TESTING
5 ZONA - K
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit FCU & AHU
TESTING
6 ZONA - L
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit AHU
TESTING
NOT YET COUNTRUCTION
2 0 1 6
D E S E M B E R J A N U A R I
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
SCHEDULE MVAC DUCK WORK & PIPE WORK

2 0 1 5 2 0 1 6
No. Description START FINISH Duration O C T O B E R N O V E M B E R D E S E M B E R J A N U A R I
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
I LANTAI - 2 ( DUCT WORK )
1 ZONA - A
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
2 ZONA - B
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
3 ZONA - C
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
4 ZONA - D
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
5 ZONA - F
Pemasangan installasi ducting
Request MOS
Pemasangan Ducting keAHU,FCU,FAN
Pemasangan MCC Panel
Testing & Comisioning
6 ZONA - G
Pemasangan installasi ducting
Request MOS
Pemasangan Ducting keAHU,FCU,FAN
Pemasangan MCC Panel
Testing & Comisioning
7 ZONA - H
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
8 ZONA - J
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
9 ZONA - K
Pemasangan installasi ducting
Request MOS
Pemasangan Ducting keAHU,FCU,FAN
Pemasangan MCC Panel
Testing & Comisioning
10 ZONA - L
Pemasangan installasi ducting
Request MOS
Pemasangan Ducting keAHU,FCU,FAN
Pemasangan MCC Panel
Testing & Comisioning
II LANTAI - 2 ( PIPE WORK )
1 ZONA - A
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
Testing
2 ZONA - B
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
Testing
3 ZONA - C
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
Testing
4 ZONA - D
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
Testing
5 ZONA - F
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
Testing & Comisioning
6 ZONA - G
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
Testing & Comisioning
7 ZONA - H
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
Testing
8 ZONA - J
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
Testing
9 ZONA - K
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
Testing & Comisioning
10 ZONA - L
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
Testing & Comisioning

NOT YET COUNTRUCTION


SCHEDULE MVAC DUCK WORK & PIPE WORK

2 0 1 5
No. Description Start Finish Duration O C T O B E R N O V E M B E R
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2
I LANTAI - LG ( DUCT WORK )
1 ZONA - A
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
2 ZONA - B
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
3 ZONA - C
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
3 ZONA - F
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
4 ZONA - G
Pemasangan installasi ducting
Request MOS
Pemasangan AHU,FCU,FAN
Pemasangan MCC Panel
Testing
5 ZONA - K
Pemasangan installasi ducting
Request MOS
Pemasangan AHU,FCU,FAN
Pemasangan MCC Panel
Testing
6 ZONA - L
Pemasangan installasi ducting
Request MOS
Pemasangan exhaust fan
Pemasangan MCC Panel
Testing
II LANTAI - LG ( PIPE WORK )
1 ZONA - A
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
TESTING
2 ZONA - B
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit VRV dan FCU
TESTING
3 ZONA - C
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit AHU
TESTING
4 ZONA - G
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit FCU & AHU
TESTING
5 ZONA - K
Installasi Pipa & Riser CHWR Dan CHWS
Pemasangan pipa drain riser dan main line
Request MOS
Pemasangan unit FCU & AHU
TESTING
NOT YET COUNTRUCTION
2 0 1 6
D E S E M B E R J A N U A R I
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30