Project Name: THREE STOREY STEEL CARPARK

Project Location: MC ArthurHighway, Sto.Domingo,Angeles City,Pampanga 07-Dec-20

Activity ID Activity Name Original Duration Start Finish December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 2021
29 06 13 20 27 03 10 17 24 31 07 14 21 28 07 14 21 28 04 11 18 25 02 09 16 23 30

Project: 3F-BLDG
3F- THREE STOREY STEEL CA 150 07-Dec-20 30-May-21

PS-100 PROJECT START 0 07-Dec-20


PC-101 SUBSTRUCTURE COMPETION 0 30-Jan-21
PC-102 SUPERSTURCTURE COMPLETION 0 30-Apr-21
PC-103 PROJECT COMPLETION 0 30-May-21

WBS: 3F-BL
3F-BLDG.1 Preliminaries 12 07-Dec-20 19-Dec-20
A1000 Permits, Bonds and Insurance 1 07-Dec-20 08-Dec-20
A1010 Mobilization/Demobilization 12 07-Dec-20 19-Dec-20
A1020 Temporary Facilities 12 07-Dec-20 19-Dec-20

WBS: 3F-BLDG.2
3F-BL Construction Work
WBS: 3F-BLDG.2.1
3F-BLD
Sub-S100
Substructure
Layout and Staking
SAMPLE FILES BY JOVY RECABLANCA 150 07-Dec-20

54 07-Dec-20
3 07-Dec-20
30-May-21

30-Jan-21
10-Dec-20
Sub-S110 Excavation Works - Footing and Tie Beam 9 10-Dec-20 19-Dec-20
Sub-S120 Gravel Basecourse 5 17-Dec-20 22-Dec-20
Sub-S130 Footing & Pedestal Rebar 12 26-Dec-20 07-Jan-21
Sub-S140 Formworks- Footing 11 29-Dec-20 09-Jan-21
Sub-S150 Soil Poisoning- Footing 2 09-Jan-21 11-Jan-21
Sub-S160 Concreting-Footing 2 12-Jan-21 14-Jan-21
Sub-S170 Formworks of Pedestal 10 13-Jan-21 23-Jan-21
Sub-S180 Rebar Tie Beam 8 14-Jan-21 22-Jan-21
Sub-S190 Formworks- Tie Beam 8 15-Jan-21 23-Jan-21
Sub-S200 Soil Poisoning- Tie Beam 2 24-Jan-21 26-Jan-21
Sub-S210 Concreting- Pedestal & Tie Beam 2 25-Jan-21 27-Jan-21
Sub-S220 Backfilling/Compaction 3 27-Jan-21 30-Jan-21
WBS: 3F-BLDG.2.2
3F-BLD Superstructure 76 01-Feb-21 30-Apr-21
WBS: 3F-BLDG
3F-BLDG.2.2.1 Ground Floor 52 01-Feb-21 02-Apr-21
Sup-S100 Steel Column (Ground Floor to Second Floor) 9 01-Feb-21 11-Feb-21
Sup-S110 Stee Beam including Steel Braces 16 09-Feb-21 27-Feb-21
Sup-S120 Slab On Grade 16 17-Feb-21 07-Mar-21
Sup-S130 Ramp ( Ground to Second Floor) 10 08-Mar-21 19-Mar-21
Sup-S140 Stair ( Ground to Second Floor) 12 19-Mar-21 02-Apr-21
Sup-S150 Painting Steel Works 12 19-Mar-21 02-Apr-21
WBS: 3F-BLDG
3F-BLDG.2.2.2 Second Floor 57 17-Feb-21 24-Apr-21
Sup-S160 Steel Column (Second Floor to Roof Deck) 10 17-Feb-21 28-Feb-21
Sup-S170 Stee Beam including Steel Braces 16 01-Mar-21 19-Mar-21
Sup-S180 Steel Deck and RC Slab 16 19-Mar-21 07-Apr-21
Sup-S190 Ramp (Second Floor to Roof Deck) 10 27-Mar-21 08-Apr-21
Sup-S210 Stair (Second Floor to Roof Deck) 12 03-Apr-21 17-Apr-21
Sup-S200 Safety Railings 18 03-Apr-21 24-Apr-21
Sup-S220 Painting Steel Works 10 10-Apr-21 22-Apr-21
WBS: 3F-BLDG
3F-BLDG.2.2.3 Roof Deck 40 15-Mar-21 30-Apr-21
Sup-S230 Stee Beam including Steel Braces 16 15-Mar-21 02-Apr-21
Sup-S240 Steel Deck and RC Slab 16 02-Apr-21 21-Apr-21
Sup-S250 Safety Railings 14 14-Apr-21 30-Apr-21
Sup-S260 Painting Steel Works 10 19-Apr-21 30-Apr-21
WBS: 3F-BLDG.2.4
3F-BLD Others 46 07-Mar-21 30-Apr-21
Othrs130 Sidewalk 0 07-Mar-21

Actual Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 1 of 2
07-Dec-20 Three Storey Steel Carpark
Primary Baseline Remaining Work Milestone
Project Name: THREE STOREY STEEL CARPARK
Project Location: MC ArthurHighway, Sto.Domingo,Angeles City,Pampanga 07-Dec-20

Activity ID Activity Name Original Duration Start Finish December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 2021
29 06 13 20 27 03 10 17 24 31 07 14 21 28 07 14 21 28 04 11 18 25 02 09 16 23 30
Othrs160 Guard House 0 09-Apr-21
Othrs110 Slab Waterproofing 0 21-Apr-21
Othrs120 Firewall and Fire Exit Gate 0 21-Apr-21
Othrs100 MEPF Works including Lightings 0 30-Apr-21
Othrs140 Curbs,Speed Bumps, Whelel Stopper and the Like 0 30-Apr-21
Othrs150 Park Signages,Stripping & Stenciling 0 30-Apr-21
WBS: 3F-BLD
3F-BLDG.2.3 CLOSE OUT 30 26-Apr-21 30-May-21
CL-100 Punchlisting and Hand-over 30 26-Apr-21 30-May-21

Actual Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 2 of 2
07-Dec-20 Three Storey Steel Carpark
Primary Baseline Remaining Work Milestone