Professional Documents
Culture Documents
Procurement & Tendering: Philippine Institute of Certified Quantity Surveyors (Picqs)
Procurement & Tendering: Philippine Institute of Certified Quantity Surveyors (Picqs)
1. What is Procurement?
2. What is Tendering?
3. What factors govern the choices for Procurement?
4. What are the most common Procurement Options?
5. Detailed review of the common Procurement Options
6. Other Procurement Options?
7. What factors influence Tendering?
8. What are the most common Tendering Options?
9. Detailed review of the common Tendering Options.
10. Other Tendering Options?
11. Procurement & Tendering Overview
12. RICS APC (Procurement & Tendering)
Section 1 – What is Procurement? 5
Section 1 – What is Procurement? 6
• pro·cure·ment
1. the act of procuring, or obtaining or getting by effort, care, or the use of special means; or
Another Definition
• Procurement is generally seen as the process of obtaining goods and services for a stated task, in
return for money.
• In the context of construction, procurement is the process - led by the construction project manager,
of acquiring professional expertise.
• The purpose of procurement is to design and construct the proposed project, and covers the
acquisition of relevant expertise from professional construction consultants, main contractors, sub-
contractors, manufacturers and suppliers.
Section 1 – What is Procurement? 8
• ten·der (ten·der·ing)
• Tendering is the process by which bids are invited from interested contractors to carry out specific
packages of construction work.
• It should adopt and observe the key values of fairness, clarity, simplicity and accountability, as well
as reinforce the idea that the apportionment of risk to the party best placed to assess and manage it
is fundamental to the success of a project.
(from www.thenbs.com)
Section 2 – What is Tendering? 12
• Procurement should be based on understanding the client’s business needs and drivers and to
appreciate the market in which it operates.
• This is fundamental in establishing how efficiently the construction project can assist the client
in achieving their business success.
• In order to successfully deliver a construction project for the client, the construction project
manager will need to enlist the support of a number of design, costing and construction professionals
and organisations.
• How these professionals and organisations operate, when they are appointed, and what they actually
contribute to a project and when they carry this work out, is reflected in the chosen procurement
route selected.
• They will also be appointed by a tendering process of which there are several options. (For
discussion later in this presentation)
Section 3 – What factors govern the choice for
Procurement? 18
• The procurement strategy developed should balance risk against project objectives at an early stage.
Even at an early stage, initial concept designs can be developed to enable the client to look at how
initial designs will respond to their business needs.
• Construction as a process is typified by project risks and once these risks have been identified and
prioritised, a suitable procurement route to reflect the project risk profile can be selected.
• These risks include completing a project which does not meet needs, which is delivered late or costs
more than the client can pay or fund.
Section 3 – What factors govern the choice for
Procurement? 19
• Many procurement strategy selection techniques have been developed, with a view to assisting
clients in their choice of the most appropriate procurement approach for their projects.
• It is normal for this procurement process to be crystallised into formal contractual arrangements.
• The words that follow construction procurement can range from ‘strategy’, and ‘options’ to ‘routes’.
Generally it all means the same thing, i.e. what contractual organisational method will be used to
realise the project.
• Most conventional procurement selection techniques are based around the concepts of time, cost
and quality.
Section 3 – What factors govern the choice for
Procurement? 20
Section 3 – What factors govern the choice for
Procurement? 21
•T (sp pl )
• s (p l v l s )
•Q l ( l p )
Section 3 – What factors govern the choice for
Procurement? 22
• If early completion is a critical factor then design and construction activities can be overlapped
so that construction can commence earlier on-site.
Section 3 – What factors govern the choice for
Procurement? 23
• An assessment of the need for price certainty by the client should be undertaken considering that
there is a time delay from the initial estimate to when tenders are received.
• The extent to which design is complete may influence the cost at the time of tender. This may be
related to the cost of risk.
• If price certainty is required, then potentially the design should be complete before construction
commences and thus design changes avoided.
Section 3 – What factors govern the choice for
Procurement? 24
• Quality is very much linked to the other factors of Time & Cost.
• However, certain projects (such as Clean Rooms, Data Centres) require the quality (standard of
construction) to be flawless for their operation.
Section 3 – What factors govern the choice for
Procurement? 25
• The extent to which the delivered quality (finished standard of construction) will achieve is normally
linked to the speed (time) for the construction.
• The extent of the delivered quality (standard of finish – e.g. Gold Taps v’s Stainless Steel) is
normally linked to the cost (budget) constraints.
Section 3 – What factors govern the choice for
Procurement? 26
• As discussed, there are a number of variables that can influence the choice of a procurement
method.
• Once the primary strategy for a project has been established, (Time, Cost & Quality) then other
factors could also be considered when evaluating the most appropriate procurement strategy
02
QUALITY COST
• External factors – consideration could be given to the potential impact of the following which
influence the client and their business:-
• External factors – consideration could be given to the potential impact of the following which
influence the client and their business:-
COVID-19…….!
Section 3 – What factors govern the choice for
Procurement? 31
• Client characteristics – a client’s knowledge, experience of the organization with procuring building
projects and the environment within which it operates.
• Client objectives are influenced by the nature and culture of the organization. The degree of client
involvement in the project is a major consideration.
• Project characteristics – The size, complexity, location and uniqueness of the project should be
considered as this will influence time, cost and risk.
Section 3 – What factors govern the choice for
Procurement? 32
• Ideally the needs of the client should be identified in the early stages of the project.
• This is not always possible. For example - changes in technology may result in changes being
introduced to a project.
• Changes in scope mostly result in increased costs and time, especially they occur during
construction.
• It is important at the outset of the project to consider the extent to which design can be
completed and the possibility of changes occurring.
Section 3 – What factors govern the choice for
Procurement? 34
Risk
• The unique / bespoke nature of building projects means that clients who decide to build are
potentially confronted with high degrees of risk.
• The risk inherent in every construction project can be assumed by, or transferred to, another
party – usually the Contractor.
• Both parties must have a clear and similar understanding of the risk.
Section 3 – What factors govern the choice for
Procurement? 35
SUMMARY
• The selection of a procurement method should be viewed as an iterative process whereby project
objectives and constraints are compared with possible procurement solutions.
• Key to procurement is to identify the priorities in the objectives of the client and to plan a path to
completion using a procurement route that will be most appropriate.
• Priorities must be put in order of precedence, each in order before other, because by definition there can
be only one priority.
Section 4 – What are the most common
Procurement Options? 36
Section 4 – What are the most common
Procurement Options? 37
A number of procurement methodologies are available to satisfy a client’s priorities in the project
objectives. There are procurement methods that will achieve:
• Certainty of cost and time for a design developed by an architect employed by the client.
However, this is a sequential and consequently a slow process
• Relative speed and cost certainty. However, the design will usually be the responsibility of a
contractor and consequently the client will lose some control over the design process; and
• Relative speed for a design developed by an architect employed by the client. However, cost is
uncertain almost until completion.
Section 4 – What are the most common
Procurement Options? 38
4
1
• Traditional
3
2
• Design & Build
2
3 • Management Contracting 1
4
• Construction Management
Section 4 – What are the most common
Procurement Options? 39
• TRADITIONAL (where the Client engages the Design team and the Contractor directly)
• DESIGN & BUILD (where the Client engages the Contractor who in turn employers the Designers)
• MANAGEMENT CONTRACTING (where the Contractor performs the role of managing the works
contractors who carry out the works and are directly and contractually responsible to the
management contractor)
1
Traditional Procurement
• The client develops the business case for the project, and provides a Scope and Budget;
• The Client appoints a team of consultants to prepare a design, plus tender documents;
• The client appoints the building contractor to construct the works to the design, by the contract
completion date and for the agreed price (a Lump Sum);
• Sometimes most of the work is sub-contracted by the Main Contractor to specialist firms but the
Main Contractor remains liable overall; and
• The consultants usually administer the contract on behalf of the Client and advise on aspects
associated with design, progress and payments which must be paid by the client.
Section 5 – Detailed review of the common
Procurement Options 43
1
Traditional Procurement
This route is probably the most commonly used method of procurement and it is suitable for:
- cost certainty.
1
Traditional Procurement
Advantages:
• This strategy is a low-risk option for clients who wish to minimize their exposure to the risks of
overspend, delays or design failure
• Direct control of the Design Team to ensure the required quality is reflected; and
1
Traditional Procurement
Disadvantages:
• No one person is responsible for the Design & Construction as they are separated;
• The separation of the contractor from the design can mean missed opportunities for the contractor
or specialist contractor to input on buildability;
• The exposure to risk will potentially increase where the design phase is rushed, where unreasonable
time targets are set or where the tender documents are not fully completed.
• Time & Costs are could increase if the Design is then varied.
Design & Build Procurement 46
Section 5 – Detailed review of the common
Procurement Options 47
2
Design & Build Procurement
• The main contractor takes responsibility for both the design and construction and may use either in-
house designers or employ consultants to carry out the design.
• The contractor tenders against a Client Brief (Employer’s Requirements Document) and will often
follow an initial concept or scheme design prepared by consultants appointed to advise the client;
and
• The design will then be developed by the contractor and the works will be completed, usually for a
fixed price.
Section 5 – Detailed review of the common
Procurement Options 48
2
Design & Build Procurement
• The Design & Build approach gives the client a single point of contact.
• However, the client commits to the cost of construction, as well as the cost of design, much earlier
than with the Traditional approach.
• Changes made by the client during design can be expensive, because they affect the whole of the
Design & Build contract, rather than just the design team costs.
Section 5 – Detailed review of the common
Procurement Options 49
2
Design & Build Procurement
• There is potentially a high design/quality risk associated with this approach as the contractor develops
the design.
• To overcome this, there can be a refinement to this approach where the client has the design prepared
to concept or scheme design stage and the contractor takes on ‘finishing off’ the design and
construction (develop & construct).
• The contractor may re-employ the original designers to complete the design in a practice known as
novation.
Section 5 – Detailed review of the common
Procurement Options 50
• all clients, including inexperienced clients and those requiring distance from the project;
• faster construction.
• complex buildings
Section 5 – Detailed review of the common
Procurement Options 51
2
Design & Build Procurement
Advantages:
• Cost Certainty
Section 5 – Detailed review of the common
Procurement Options 52
2
Design & Build Procurement
Disadvantages:
• Tendering tends to be more expensive due to higher risk for the Contractor; and
• The client appoints designers and a contractor (management contractor) separately and pays the
contractor a fee for managing the construction works.
• A feature is the early appointment of the contractor to work alongside the design team to develop a
programme for construction and contribute to the design and costing of the works.
• The Contractor performs the role of managing the works contractors who carry out the works and are
directly and contractually responsible to the management contractor.
• This approach often means that design and the start on site overlap, with the design and tender packages
becoming available ‘just-in-time’ to suit the construction programme.
Section 5 – Detailed review of the common
Procurement Options 55
3
Management Contracting Procurement
• The management contractor will not normally carry out construction work.
• This preserves the management contractor’s independence and reinforces a consultancy relationship
with the client.
• Payment is generally made to the management contractor on the basis of the cost of the works
packages plus the agreed fee.
• Much of the success of this approach depends on the contractor’s team. Unless the team is drawn
from companies which are experienced in this kind of team working, the benefits are not always
realised.
Section 5 – Detailed review of the common
Procurement Options 56
3
Management Contracting Procurement
• There is less price certainty at the outset, because construction tends to start ahead of completion
of all design stages and at a point when many of the work packages have yet to be tendered.
• This often means adjustments (Value engineering) are made to the design and specification of works
packages later in the programme to keep the project within budget.
• However, the overall process of design and construction tends to be shorter than in either traditional
or design & build situations.
Section 5 – Detailed review of the common
Procurement Options 57
• complex buildings; or
• a developing brief
• inexperienced clients;
3
Management Contracting Procurement
Advantages:
• Management Contractor has early involvement and manages the works Contractor’s;
3
Management Contracting Procurement
Disadvantages:
• The Management Contractor is only responsible for workmanship to the extent that the Works
Contractor is responsible or able to pay;
• Contractors are contracted directly to the client and the construction manager manages the process
for the client on a simple consultancy basis.
• Although in a sense this gives the client a greater measure of control, it also means that the client
accepts a higher amount of risk compared to other procurement options.
• The management contractor is simply an agent, and usually cannot guarantee that the project will
be finished to time and cost.
• As it requires constant involvement by the client this approach is really only suitable for experienced
clients.
Section 5 – Detailed review of the common
Procurement Options 62
• complex buildings; or
• a developing brief
• inexperienced clients;
4
Construction Management Procurement
Advantages:
• The construction work is more closely integrated into the management of the project.
• Close liaison between the construction manager and design team leads to prompt identification of
and decisions relating to practical problems.
Section 5 – Detailed review of the common
Procurement Options 64
4
Construction Management Procurement
Disadvantages:
• The client has one more consultant and a number of contractors with whom to deal instead of only
one main contractor.
• The client’s financial commitment is uncertain until the last of the works contracts has been signed.
Quick Summary of Procurement Options 65
Section 5 – Detailed review of the common
Procurement Options 66
• Design and Build - the design and build procurement route starts with the appointment of a main
contractor to design and construct the works. In this way, it gives the client a single point of
responsibility for delivering the project.
Section 5 – Detailed review of the common
Procurement Options 67
• Construction Management - largely similar to that of Management Contracting with the exception
that within this route the Client is not in direct contractual relationships with the trade contractors
as it is with the former. They appoint a management team and a construction manager on a fee basis
which can be obtained in competition.
Section 6 – Other Procurement Options? 68
Private Finance Initiative [PFI] 69
Section 6 – Other Procurement Options? 70
• A recent/modern form of procurement to encourage private investment into public sector projects
(most commonly Schools, Hospitals and Infrastructure).
• Was introduced into the UK in circa 1992 as an initiative designed to reduce the pressure on public
sector borrowing.
Section 6 – Other Procurement Options? 71
Private Finance Initiative (PFI)
• A single contractor will be appointed to build, design and operate the project, in order to deliver
services demanded by the public sector.
• This contractor will have expertise in design, construction, facilities management and funding
capability.
• The contractor will finance the project and lease it to the client for an agreed period.
• To exploit the skills and knowledge of specialist private sector firms in facilities management and
property management rather than public sector professionals.
• To reduce the total life cycle cost of assets where conventional procurement methods gave no
incentive to the contractor to reduce maintenance costs.
Section 6 – Other Procurement Options? 73
• To convert public sector capital expenditure into service payments over an extended period of time.
• To transfer certain risks (and the cost thereon) to the private sector who are perceived as being
better equipped and more innovative in analysing and managing them.
Section 6 – Other Procurement Options? 74
Private Finance Initiative (PFI)
• Partnering refers to some form of collaborative approach in which Clients and Contractor’s are open
with one another in order to meet common objectives;
• Partnering is a management approach used by two or more organizations to achieve specific business
objectives by maximizing the effectiveness of each participants resources; and
• Partnering can be based on a single project (Project Partnering) but a greater benefit is available
when it is based on a long term commitments (Strategic Partnering or Alliance)
Section 6 – Other Procurement Options? 77
• Project Partnering – which is based on a Client and Contractor working openly on a single project,
can look to achieve potential cost reductions of around 2 – 10% when compared against a more
traditional procurement method.
• Strategic Partnering – which involves the client and contractor working on a series of construction
projects could potentially achieve savings on an average of 30% per project when compared against a
more traditional procurement method of a single project.
Section 6 – Other Procurement Options? 78
Project Partnering Procurement
• It can actually be used as a delivery method for the four discussed common procurement methods.
• Procurement is also more of a culture and a mental attitude rather than a dogmatic standard of traditional
procurement.
• Adversarial; • Collaborative;
Not for detailed discussion in this presentation, however you may wish to research further on….
• Traditional with Cost Plus & Target Cost (Fluctuating Fee / Bonus / Pain & Gain)
• Accountability;
• Auditability;
• Ensuring that the correct price has been paid for the proposed works.
When to Tender?
• In theory, tendering can occur at any time during the design process.
• For example a pure Design & Build project could be tendered at Concept Stage (RIBA Stage 1), with
the Contractor taking full responsibility for completing the concept design against high level
employers requirements through to construction and completion.
When to Tender?
• The timing of the tender will be dictated mainly by the amount of input required from the
contractor, which should have been identified in the Procurement route.
• If the tender is simply to build in exact compliance with the fully designed tender document
(Traditional Method) then the time for tender is different to a tender to design the concept and then
construct (Design & Build Method).
When to Tender?
Tender Documents
• The choice of Procurement route will have differing effects on how the tender documents are compiled.
• Under a Traditional Procurement route the design information, BOQ’s and Preliminaries will be issued.
• Whereas under a Design & Build Procurement route, the documents are compiled together in documents
called the Employer’s Requirements where the Contractor responds with the Contractor’s Proposal.
1
• Single Stage Tendering 3
2
2
• Two Stage Tendering
1
3 • Negotiated Tendering
Section 8 – What are the most common
Tendering Options? 92
• Single Stage Selective Tendering (The client or his PM or Architect and QS compile a list of the
preferred contractors for the proposed project who will receive the full documentation.)
• Two Stage Selective Tendering (The client or his PM or Architect and QS compile a list of the
preferred contractors for the proposed project in the 1st stage for a limited submission, with full
documentation for negotiation in the 2nd stage. )
• Generally considered as the most common type of tendering strategy for obtaining a price for the
whole of the construction works.
• Usually undertaken at RIBA Stage 4 so that the tenderers receive the most detailed information to
base their bid on (aligns most with Traditional Procurement method).
• The bidding contractors are given a predetermined amount of time to submit their tenders.
Section 9 – Detailed review of the common
Tendering Options? 96
• Invitation to tender documents are issued to a number of competing contractors who are all given
the same equal chance to bid for the project based on identical tender documentation.
• The client and/or his Project Team (PM, Architect and QS) compile a list of the preferred
contractors for the proposed project.
• Pre-selecting a limited number of contractors to tender for the works. Usually the full tender
documentation is issued to these selected companies.
Section 9 – Detailed review of the common
Tendering Options? 97
• The number of tenderers is normally limited to between five & eight, depending on the size and
nature of the contract.
• Tender receipts are then analysed, in terms of time, cost and quality, before a single contractor is
declared the preferred contractor.
• The preferred contractor then finalizes the process to enter into a formal contract with the client
to deliver the tendered works.
Section 9 – Detailed review of the common
Tendering Options? 98
Advantages:
• It should ensure that only capable and approved/selected firms submit tenders; and
• It tends to reduce the aggregate cost of tendering (Cost to the Client for Advertisements etc).
Section 9 – Detailed review of the common
Tendering Options? 99
Disadvantages:
• This is resultant from there being less competition (compared against Open Tendering – see later)
and also to the likely higher caliber of the tenderers selected.
Two Stage Tendering 100
Section 9 – Detailed review of the common
Tendering Options? 101
Two Stage Selective Tendering
• Often used where time is constrained as it enables design and tendering to overlap.
• Can be used if the design process would benefit from the technical input of a contractor in the later design
stages (complexity, unique elements).
• Similar process to Single Stage Selective tendering to select companies for the Bid
• The second stage is a process of negotiation or pricing with selected contractor on the basis of first
stage tender.
Section 9 – Detailed review of the common
Tendering Options? 103
• This may have benefits of competition and at the same time to have the advantage of bringing a
contractor into the planning of the project and making use of his practical knowledge and expertise;
and
Disadvantages:
• This is resultant from there being less competition (compared against Open Tendering – see later)
and also to the likely higher caliber of the tenderers selected.
Negotiated Tendering 105
Section 9 – Detailed review of the common
Tendering Options? 106
Negotiated Tendering
• When the client has a preference for a particular contractor due to previous work done for him.
• On completion of the design the contractor will price the bill of quantities and enter into a
negotiation with QS.
• The contract sum will be arrived at by negotiation and an agreement will be made between the
client and the contractor.
Section 9 – Detailed review of the common
Tendering Options? 107
Negotiated Tendering
Advantages:
• If it is part of a ‘framework’ or ‘supply chain’ then rates and the like may already be known; and
• Usually a good relationship between the Client and the Contractor has already been formed over
previous experience. (Could lead to reduced risk pricing)
Section 9 – Detailed review of the common
Tendering Options? 108
Negotiated Tendering
Disadvantages:
• Competition is eliminated which may lead to a higher price in some instances; and
• If a price can’t be agreed with the single tenderer, then it can be lengthy to approach a ‘reserve’
Summary of Tendering Options 109
Section 9 – Detailed review of the common
Tendering Options? 110
Choosing the most suitable tender strategy – Summary
Whilst all three of the most common tender strategies could in theory be used with almost any
procurement route, it is worthy to note that some suit certain strategies better than others.
• Traditional projects are generally advanced to a far greater level of design detail before tender. As
the Contractor is therefore not responsible for the design, it generally supports a single stage tender.
• D&B projects pass a larger proportion of risk and design responsibility to the Contractor. Therefore a
two stage tender can benefit from the Contractor’s understanding of the project so they can
influence the design. Single stage can also be used.
Section 9 – Detailed review of the common
Tendering Options? 111
Choosing the most suitable tender strategy – Summary
Whilst all three of the most common tender strategies could in theory be used with almost any
procurement route, it is worthy to note that some suit certain strategies better than others.
• A two stage tender strategy is also useful where a quick start on site is required as tendering and
design can be overlapped. Therefore it would seem a natural fit for the management routes
(Management Contracting and Construction Management). However, for an even quicker start on
site, Negotiation could be utilized instead
Section 9 – Detailed review of the common
Tendering Options? 112
Section 9 – Detailed review of the common
Tendering Options? 113
Overview of Timing of Tendering
Section 10 – Other Tendering Options? 114
Open Tendering 115
Section 10 – Other Tendering Options? 116
Open Tendering
• Any contractor, irrespective of size or capability, may apply for the documents and tender.
• The advertisement will carry brief details of the location, type, scale and scope of the proposed
work.
• In GCC Countries it is usually commonplace that some sort of Fee is paid to receive the tender to
help separate genuine and non-genuine bidders.
Section 10 – Other Tendering Options? 117
Open Tendering
Advantages:
• There can be no accusation of favoritism as might be suggested where a selected list is drawn up;
• An opportunity is provided for a capable firm to submit a tender, which might not be included on a
selected list; and
Open Tendering
Disadvantages:
• There is a potential danger that the lowest tender may be submitted by a incapable contractor; and
• Although both should be mitigated if the review process has been robust
Section 10 – Other Tendering Options? 119
Serial Tendering
• A hybrid/advance method of tendering which combines competitive tendering (single or two stage) with
negotiation;
• Often used for Clients who have a number of phases of similar work.
• In such cases, the original competitive tender would serve as a framework to negotiate following phases
of work;
• Where it is known that future phases of work will be required, the original tender documents can include
sections for schedules of rates to use in the negotiation.
Section 10 – Other Tendering Options? 120
Serial Tendering
• The advantage of Serial Tendering is that Clients know that the Contractor was selected in a
competitive environment in the first step, therefore the basis of follow on negotiations are sound;
and
• A disadvantage is that the normal pitfalls of negotiation apply and as time elapses the original tender
may no longer be applicable and would need to have been renegotiated anyway
Section 10 – Other Tendering Options? 121
Term Contracts
• Term Contract Tendering is generally for maintenance works, minor works and works for a
Client who has a continued supply of minor works which suits a schedule of rates.
• Tendering such works is carried out on a schedule of rates basis for common works and
mini work orders are then awarded for discreet works packages based on tendered rates.
• The Tendering strategy for Term Contracts demonstrates the competence of the
Contractor and shows that the priced schedule of rates represent value for money for the
Client and the proposed works.
Section 10 – Other Tendering Options? 122
Frameworks
• Open Tenders are usually used to advertise for firms to apply to be on a framework.
• Once a framework list is agreed then further works is awarded to firms on that list.
• This can be on a ‘call-off basis’ sometimes based on fee scales or rates or on ‘mini-tenders’ run like
a normal tender process.
• Generally reduces procurement costs for large numbers of contracts for similar work and greater
continuity of potential work for bidders, which increases competitiveness.
Section 10 – Other Tendering Options? 123
E-Tendering
• It allows companies to run tenders through a secure website. It offers a simple, secure, standard,
efficient and cost effective way to manage tenders online.
• The advantages of e-tendering are obvious. Documentation is distributed and returned via a secure
web-based system.
• This avoids the need for collating paperwork and also, important for construction, creates an
automatic audit trail.
• During the tender period, updates and queries and changes are exchanged through the same system
Section 11 – Procurement & Tendering
Overview 124
Section 11 – Procurement & Tendering Overview 125
Definition
OTHERS 04 TIME
• External Factors
• Client Characteristics
• Project Characteristics
•
•
Ability to Make Changes
Risk
03 01
02
QUALITY COST
Section 11 – Procurement & Tendering Overview 127
3 • Management Contracting 1
4 • Construction Management
Section 11 – Procurement & Tendering Overview 128
• Accountability;
• Auditability;
• Ensuring that everything required has been picked up;
• Parity/equality/fairness in the process;
• Helping to reduce claims or corruption; and
• Ensuring that the correct price has been paid for the proposed works.
Section 11 – Procurement & Tendering Overview 129
3 • Negotiated Tendering
Section 11 – Procurement & Tendering Overview 130
Section 12 – RICS APC
(Procurement & Tendering) 131
Section 12 – RICS APC
(Procurement & Tendering) 132
A quantity surveyor is expected to fulfil the following duties, (notwithstanding the detailed terms of any
appointment or contractual obligation).
• take an initial brief from a Client to understand their requirements for procurement/tendering;
• collate and produce the invitation to tender documents and issue them in the appropriate manner;
• deal with tender queries and ensure they are answered in a timely manner;
• open and analyse tender returns, collate tender queries from the design team
• Level 1(Knowing)
• The difference between procurement and tendering;
• The main types of procurement and tendering
strategies/procedures;
• Reasons for choosing one type of procurement route
over an other;
• Reasons for tendering strategies; and
• Practice Notes (RICS, JCT etc)
Section 12 – RICS APC
(Procurement & Tendering) 137
• Level 2 (Doing)
• Producing a Pre-Tender Estimate;
• Choosing the most suitable tender strategy;
• Review the RIBA Plan of Work;
• Setting up the tender;
• Assessing a suitable tender period;
• Producing/compiling tender documents;
• Issue the tender and the tender process;
• Receiving tenders and post tender activities; and
• Tender report and notifying tenderers.
Section 12 – RICS APC
(Procurement & Tendering) 138
• Level 3 (Doing/Advising)
• Advice on procurement strategies;
• Advice on tender strategies;
• Managing and reporting – tender compilation;
• Managing and reporting – tender period;
• Tender scoring techniques;
• Further advice on tender reports;
• Dealing with Alternative Tenders; and
• Managing and reporting - negotiation processes and
outcomes.
Section 12 – RICS APC
(Procurement & Tendering) 139
SUMMARY
• Level 1 (Knowing) – Read, Research, Question, Understand – theory and self orientated.
QUESTIONS ?