NIT for Repair/ Maintenance (PMGSY)

MADHYA PRADESH RURAL ROAD DEVELOPMENT AUTHORITY


(AN AGENCY OF PANCHYAT & RURAL DEVELOPMENT DEPARTMENT, GOVT. OF M.P.) 5th Floor, Block-II, Paryavas Bhawan, BHOPAL M.P. 462 004

NOTICE INVITING TENDER No. 14MTN/2011


No. 7779 / NIT -Maint. / F.A. / 2011 Dated 04 / 06/ 2011

Chief General Manager, on behalf of the Madhya Pradesh Rural Road Development Authority invites online percentage rate tenders from the Contractors registered in appropriate class/category with M.P. P.W.D. or Contractors of equivalent categories registered with other States/ Central Government, Departments, Institutions, Undertakings and Authorities for REPAIR / MAINTENANCE OF THE RURAL ROADS FOR FIVE YEARS CONSTRUCTED UNDER PRADHAN MANTRI GRAM SADAK YOJNA on the SSR issued by MPRRDA effective from 20.03.2009 with upto date amendments for the package(s) shown in the column 2 of table below :PAC (in Rs. lakh) Initial Rehabilit ation works Annual Routine Maintena nce Renew al of Bitumi nous Surfac e Time allowe d for comple tion of work of part I in month

S.N o

Package Number

Name of District

Name of PIU

No. of Roads

Total length of Roads (In KMs.)

Emergen cy Works Total

Cost of tender docum ent

Part I

Part II

Part III

Part IV

1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

2 MP47MTN004 MP07MTN017 MP07MTN019 MP07MTN020 MP07MTN018 MP07MTN0012 MP10MTN011 MP10MTN012 MP10MTN013 MP10MTN014 MP12MTN008 MP12MTN009 MP14MTN005 MP16MTN 001 MP16MTN 002

3 Ashoknagar Chhindwara Chhindwara Chhindwara Chhindwara Chhindwara Dewas Dewas Dewas Dewas Dindori Dindori Gwalior Hoshangaba d Hoshangaba d

4 Ashoknagar Chhindwara-1 Chhindwara-1 Chhindwara-1 Chhindwara-3 Chhindwara-5 Dewas Dewas Dewas Dewas Dindori-1 Dindori-2 Gwalior Hoshangabad Hoshangabad

5 4 3 4 3 4 2 5 6 1 2 1 3 6 3 5

6 20.55 18.85 12.20 8.23 14.05 7.45 24.92 16.14 6.80 4.54 9.80 6.66 20.845 11.3 16.22

7 12.39 12.97 34.93 0.84 20.37 2.46 87.62 55.58 50.06 8.63 7.23 0.78 0.00 0.00 0.00

8 24.94 23.85 15.44 10.42 17.78 9.43 30.10 19.50 8.21 5.74 12.40 8.39 25.18 14.16 20.44

9 110.28 94.12 66.37 39.83 71.96 33.91 95.47 70.22 9.49 22.95 47.01 27.9 107.42 60.62 87.02

10 29.53 23.60 16.36 10.06 17.94 8.67 42.64 29.06 13.55 7.46 11.88 7.26 26.52 14.95 21.49

11 177.14 154.54 133.10 61.15 128.05 54.47 255.83 174.36 81.31 44.78 78.52 44.33 159.12 89.73 128.95

12 4 2 2 1 2 4 3 3 3 1 1 1 NIL NIL NIL

13 11900 11900 11900 9400 11900 9400 14400 11900 9400 4400 9400 4400 11900 9400 11900

-1-

NIT for Repair/ Maintenance (PMGSY)

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45

MP16MTN004 MP-16 MTN 006 MP17MTN005 MP17MTN007 MP23MTN007 MP29MTN003 MP29MTN005 MP29MTN006 MP29MTN007 MP32MTN003 MP31MTN 008 MP31MTN005 MP36MTN013 MP36MTN014 MP36MTN012 MP36MTN010 MP39MTN006 MP39MTN014 MP43MTN004 MP43MTN009 MP43MTN002 MP43MTN011 MP43MTN006 MP43MTN013 MP50MTN004 MP50MTN001 MP50MTN001 (A) MP50MTN003 MP50MTN002 MP50MTN002 (B)

Hoshangaba d Hoshangaba d Indore Indore Mandla Raisen Raisen Raisen Raisen Rewa Ratlam Ratlam Seoni Seoni Seoni Seoni Shajapur Shajapur Ujjain Ujjain Ujjain Ujjain Ujjain Ujjain Singrauli Singrauli Singrauli Waidhan Singrauli Singrauli

Hoshangabad Hoshangabad Indore Indore Mandla Raisen-1 Raisen-1 Raisen-1 Raisen-1 Rewa-1 Ratlam Ratlam Seoni Seoni Seoni Seoni Shajapur Shajapur Ujjain-1 Ujjain-1 Ujjain-1 Ujjain-1 Ujjain-1 Ujjain-1 Waidhan-1 Waidhan-1 Waidhan-1 Waidhan-1 Waidhan-2 Waidhan-2

4 2 5 3 1 2 2 1 1 7 3 2 4 7 6 2 3 3 2 1 2 1 2 1 2 2 1 1 1 2

15.76 9.00 15.97 5.00 31.00 12.74 21.075 14.72 7.5 32.56 25.18 9.70 14.42 31.85 22.07 9.58 9.1 9.98 5.69 5.1 7.73 5.50 7.9 7.00 20.04 6.93 1.55 5.28 14.365 9.335

3.45 3.39 1.24 8.07 3.56 0.00 0.00 4.44 9.00 22.71 0.00 11.93 0.00 0.00 0.00 22.38 4.59 2.68 2.53 0.00 0.00 0.0 0.00 0.95 64.12 30.21 0.00 1.92 5.68 2.08

19.35 10.96 19.69 6.41 39.23 16.11 26.67 18.63 9.49 40.81 31.87 12.28 18.25 40.3 27.65 11.87 11.71 12.16 6.69 6.45 9.83 6.73 9.74 8.86 24.35 8.37 1.87 6.68 17.36 11.49

77.57 45.04 74.57 21.9 166.35 68.37 116.76 67.70 39.03 180.02 117.68 53.74 68.03 165.26 113.60 44 48.84 42.15 27.58 28.26 41.47 30.47 39.07 38.78 107.54 38.39 8.59 28.33 76.54 45.16

20.08 11.88 19.1 7.28 41.82 16.90 28.69 18.15 11.50 44.16 29.91 15.59 17.25 41.12 28.25 11.17 13.03 11.39 7.36 6.94 10.26 7.44 9.76 9.72 26.37 9.34 2.09 7.00 18.78 11.33

120.45 71.27 114.6 43.65 250.96 101.38 172.12 108.92 69.02 287.70 179.46 93.54 103.53 246.68 169.5 89.42 78.17 68.38 44.16 41.65 61.56 44.64 58.57 58.31 222.38 86.31 12.55 43.93 118.36 70.06

3 1 2 3 1 NIL NIL 1 1 3 NIL 2 NIL NIL NIL 4 3 1 3 NIL NIL NIL NIL 1 4 4 NIL 1 1 1

11900 9400 11900 4400 14400 11900 11900 11900 9400 14400 11900 9400 11900 14400 11900 9400 9400 9400 4400 4400 9400 4400 9400 9400 14400 9400 1400 4400 11900 9400

-2-

NIT for Repair/ Maintenance (PMGSY)

NOTE: 1. 2. The tenders are invited online for the works shown in table above. The amount of earnest money is 1% of the PAC as shown in column 11 rounded off to the nearest thousand rupees. Performance security to be submitted at the time of agreement @ 2.5% of the contract price remaining 2.5% & S.D 5% will be recovered from running payments.

3 (i) The amount of earnest money is 1% of PAC rounded off to the nearest thousand rupees. Original Earnest Money Deposit Instrument and cost of bid document in the form of D.D payable to MPRRDA Bhopal should reach either in the Office of the concerned PIU or Head office, Bhopal by 04.07.2011 up to 15:00 PM. Scanned copy of the E.M.D. instrument and D.D (cost of bid document) is to be uploaded online along with the bid documents. Affidavit as required in para4.4 B (a) (ii) of SBD (ITB) should be submitted in original with EMD. In case registration is based on revenue solvency, copy of valid revenue solvency certificate should also be submitted. (ii) Bid documents consisting of qualification information and eligibility criterion of bidders, plans, specifications, drawings, the schedule of quantities of the various classes of work to be done and the set of terms & conditions of contract to be complied with by the Contractor can be seen online from 10.06.2011, 10:30 hrs. on the website http://mprrda.mpeprocurement.gov.in. Tender documents will be issued online from http://mprrda.mpeprocurement.gov.in as per time schedule mentioned in Key Dates after making online payment of service charges Rs. 606/- through Debit Card/Cash Card or Internet Banking. Contractors submitting Tender online, if awarded work, will have to sign agreement on the authentic copy of the tender document, available in the office of GM PIU concerned. (iii)

Technical bids will be opened online as per time schedule mentioned in Key Dates in the office of concerned General Manager, Project Implementation Unit.
Financial bid shall be opened online as per time schedule mentioned in Key Dates at MPRRDA Head Quarter, Paryavas hawan, Bhopal. If the office happens to be closed on the date of opening of the bids as specified, the bids will be opened on the next working day at the same time and venue.

(iv)

4. 5.

The time allowed for completion work included in Part- I of each package is shown in column no.12 The site for the works is available and may be visited on any working day.

6. Initial Rehabilitation (PartI) work consists of special repair of roads, strengthening of crust, raising of formation, addition of openings in CD works etc. as per schedule attached and maintenance thereof during defect labiality/maintenance period. Contractors are to quote rates keeping in view Rural Road specifications and relevant codes. The work done by the contractor will be measured and paid as per agreement. 7. Routine Maintenance (Part II) work relates to performance based regular routine maintenance of roads as per IRC 82 and SP 20 section 1900 which includes, but not limited to, items specified in contract data to clause 16 of tender document and other relevant clauses of the agreement. Contractor is required to survey the road regularly and attend repair works as and when required and keep the road in good traffic worthy conditions. He will also maintain CDs and Bridges during contract period. These works will be non-measurable and the contractor will be paid at the rates given below plus tender percentage subject to provision of clause 38 of GCC, per km. per year for such maintenance. Payment will be released once in 2 months @ 1/6 of the annual rate sanctioned, on the certificate of consultant/engineer that roads have been maintained as per agreement. Rates applicable after B.T renewal / seal coat renewal, Ist year Rs. 12,800.00 per km per year. IInd year Rs. 17,000.00 per km per year IIIrd year Rs. 25,000.00 per km per year IVth year Rs. 30,000.00 per km per year

(a)

-3-

NIT for Repair/ Maintenance (PMGSY)

Vth year Rs. 36,000.00 per km per year (b) 8. Rate applicable to the road length where no BT renewal / seal coat renewal has been done - Rs. 36000.00 per km per year Renewal of bituminous surface (Part-III) work relates to renewal of bituminous surface of existing PMGSY roads as per schedule of items attached and maintenance thereof during defect labiality/maintenance period. Contractors are to quote rates keeping in view Rural Road with the tender document specifications and relevant codes. Chainages for renewal of bituminous surface and time limit will be intimated by the GM, PIU from time to time as per requirement. The work done by the contractor will be measured and paid as per agreement. Emergency works (Part-IV) work relate to unexpected damages as a result of natural phenomena such as strong storms, washouts, flooding, earthquakes etc. for which schedule and time limit will be provided by the GM PIU as and when required alongwith maintenance during defect labiality/maintenance period. Contractors are to quote rates keeping in mind Rural Road specifications and relevant codes. The work done by the contractor will be measured and paid as per agreement. Amount included in the PAC for emergency work (Part-IV) is a provisional sum and contractor will have to carry this work as directed by the Engineer-in-charge (GM). Payment for such work shall be made at agreemented rate (rates for particular item given in the applicable SOR + Tender premium) For non SOR items of work, payments shall be determined by the engineer with reference to rates of similar item in the SOR or on the basis of standard data analysis of rural roads. Contractor shall have no claim if no emergency work is required to be executed during the contract period.

9.

10. Any variation (plus or minus) in the cost of bitumen, steel, cement, HSD, labour and other material during the contract period shall be adjusted as per Price Adjustment Clause.(annexure-I) This will be applicable to works included in Part-I, Part-III & Part-IV. No price adjustment will be payable for routine maintenance work (Part II). 11. Names of the roads and their length is given in the schedule of items. 12. To qualify for award of the Contract, each bidder should have in the last five years: a.) Achieved in any one year during last 5 years a minimum financial turnover (in all cases of civil engineering construction works only) volume of construction work of at least 75% of estimated cost of works. b.) Satisfactorily completed, as prime contractor, at least one similar work (road work) equal in value to one-third of the estimated cost of work for which the bid is invited, or such higher amount as may be specified in the Appendix to ITB. c.) He should also fulfill qualifying criterion laid down in Para 4.4 to 4.7 of (ITB) of tender document. 13. The bid for the work shall remain open for acceptance for a period of ninety days from the date of opening of bids. If any bidder/ tendered withdraws his bid/ tender before the said period or makes any modifications in the terms and conditions of the bid, the said earnest money shall stand forfeited. 14. A bidder shall not be permitted to bid for works in the Project Implementation Unit responsible for award and execution of contracts in which his or his spouses near relative(s) (defined as first blood relations, and their spouses) is/are posted as Accountant/Accounts Officer or as an officer in any capacity between the grades of General Manager and Sub-Engineer (both inclusive). 15. No Engineer of Gazetted rank or other Gazetted officer employed in Engineering or Administrative duties in an Engineering Department of the State Government is allowed to work as a contractor for a period of two years after his retirement from Government service, without government permission. If the contractor or any of his employees is found at any time to be such a person who had not obtained the permission of the Government as aforesaid, before submission of the tender or engaged in the contractors service his contract is liable to be cancelled and earnest money will be forfeited, 16. This NIT replaces the NIT printed in the tender document. Conditions of this NIT and those in the annexure-1 will prevail over the conditions of tender document. 17. Other details can be seen in the bidding documents.

Key Dates
S. No 1 MPRRDA Stage Tender Preparation And Release of NIT Contractor Stage Start Date & Time Expiry Date & Time 06.06.2011 10:30 09.06.2011 22:00

-4-

NIT for Repair/ Maintenance (PMGSY)

2 3 4 5 6 7 8

Close for Bidding Generation of Super Hash Open EMD & Technical Bid Open Financial / Price-Bid

Tender Purchase - Online Tender Download Submit of Bid - Hash Online Submit Bids Online - Reencryption -

10.06.2011 10:30 10.06.2011 10:30 10.06.2011 10:30 30.06.2011 10:30 01.07.2011 10:30 04.07.2011 15:30 07.07.2011 10:30

24.06.2011 17:30 25.06.2011 17:30 27.06.2011 17:30 30.06.2011 23:00 02.07.2011 17:30 05.07.2011 17:30 07.07.2011 17:30

Chief General Manager M.P. Rural Road Development Authority Bhopal

-5-

NIT for Repair/ Maintenance (PMGSY)

Annexure-I Various clauses of tender document are amended as below. 1. Add following as sub clause 16.2.3 Payment for routine maintenance will be performance based. Performance indexes assigned to various routine maintenance items/activities are as given in maintenance activity table below para 12. If performance of contractor during the period under consideration fulfils less than 70 out of 100 points, no payment will be made to the contractor for that period. If performance index is between 70 to 80, proportionate deduction in payment will be made for each item/activity of the work not attended during that period. If performance index is more than 80 out of 100, full payment shall be made to the contractor. Clause 37 Replace the existing provisions with the following; Any variation (plus or minus) in the cost of bitumen, steel, cement, HSD, labour & other materials during the contract period shall be adjusted as per provision of sub clause 37.1. Class 37.1 Price Adjustments Any variation (plus or minus) in the cost of Bitumen/Steel/HSD/Cement labour and other materials during the subject to note 3 of this sub clause shall be adjusted as under; Adjustment for Bitumen & Steel - Any variation (plus or minus) in the cost of Bitumen/Steel will be paid or deducted on the theoretical consumption of Bitumen/Steel. The difference in price will be worked out on the basis of basic rates prevailing on the date of tender and any variation during the agreement period only. This difference in prices will be calculated on Bulk Supply rates of I.O.C./ rates of Steel Authority of India respectively. The Bitumen has to be brought from public Sector Oil refineries situated in India. For this purpose rate of nearest I.O.C. refinery and that of nearest SAIL stock yard shall be the basis for calculation. Adjustment for Fuel and Lubricants - Any variation in the cost of Fuel and Lubricants will be paid or deducted on the basis of adjustment for Fuel and Lubricants formula. Price adjustment for increase or decrease in the cost of POL (fuel and lubricants) shall be paid in accordance with the following formula: Pr (F1-F0) Vr = 0.75x-------xR1 x-----------100 Fo Vr = The amount of price adjustment in Rs. R1 = The cost of Executed work during the month. Fo = The official retail price of High Speed Diesel (HSD) at the existing consumer pumps of IOC of the district hqrs. where PIU is situated, on the last date of submission of tender. F1 = The average official retail price of High Speed Diesel (HSD) at the existing consumer pumps of IOC of the district hqrs. where PIU is situated, during the period under consideration. Pr = 10 (Ten) percent

2.

3.

A.

B.

-6-

NIT for Repair/ Maintenance (PMGSY)

C.

Adjustments in the Contract Price for Cement - The Contract Price will be subject to adjustment on account of variation in the cost of cement which is delivered to the site and used in the Permanent Works according to the formula given below: S x (M - Mc) x T Vc = --------------------Mc Vc = Adjustment to the Contract Price on account of increase or decrease of cost indices of cement as applicable. S = Basic Price for cement on the date of NIT (for calculating price adjustment) Rs.4300.00 per MT. M = Base cost index for cement ( which shall be the index for cement, as shown in 'Index Numbers of wholesale prices in India - By Groups and Sub-Group (Month end/year end data)' (Base latest available), released by the Office of the Economic Adviser, Ministry of Industry, Government of India, prevailing at the time of specified in para F) of Sub-Clause 70.3. (prevailing during the period under consideration) Mc = Base cost index for cement ( which shall be the index for cement, as shown in 'Index Numbers of wholesale prices in India - By Groups and Sub-Group (Month end/year end data)' (Base latest available), released by the Office of the Economic Adviser, Ministry of Industry, Government of India, prevailing at the time of specified in para F) of Sub-Clause 70.3. (prevailing at the time of tender) T = Quantity of cement in MT, based on theoretical consumption. D. Labour VL = 0.75x PL /100 X R X (L1 L0) / L0 VL = Increase or decrease in the cost of work during the month under consideration due to changes in rates for local labour. L0 = The consumer price index for industrial workers for the State on the lost date of submission of Bid, as published by Labour Bureau. Ministry of Labour, Government of India. L1 = The average consumer price index for industrial workers for the state for the month under consideration as published by Labours Bureau, Ministry of Labour, Government of India. PL = Percentage of labour components of the work. (20%) R = The cost of executed work during the month.

E. Other Materials Vm = 0.75x Pm /100 X R X (M1 M0) / M0 Vm = Increase or decrease in the cost of work during the month under consideration due to changes in rates for local materials other than bitumen. M0 = The all India wholesale price index (all commodities) on the lost date of submission of bid, as published by the Ministry of Industrial Development, Government of India, New Delhi. M1 = The all India average wholesale price index (all commodities) for the month under consideration as published by Ministry of Industrial Development, Government of India. New Delhi.

-7-

NIT for Repair/ Maintenance (PMGSY)

Pm = Percentage of other construction material component (other than those included AB&C) of the work -20% R = Cost of executed work during the month. Note: - 1. No other adjustment to the Contract Price on account of fluctuation in the cost Materials shall be made. In determining the amount of any adjustment to the Contract Price pursuant to this condition no account shall be taken of any overheads or profits. Price variation clause will be applicable during the period given in each work order for part I, III & IV works. This will not be payable beyond the period allowed for completion of particular work unless specially permitted in the time extension order. 4. Replace the maintenance activity table given in the contract data against clause 16.2 as below;

Routine Maintenance Activities and their frequency with performance index (Ref. Class 16 of GCC) Sl. Name of Item/Activity Frequency of operations in Performance No. the year Index 10 1 Restoration of rain cuts and dressing of Once generally after rains or berms as per clause 1902 of the as and when required). Specifications. As and when required 20 2 Making up of shoulders as per clause 1903 of the Specifications. As and when required 50 3 Maintenance of Bituminous surface road and / or gravel road and/or WBM road including filling pot holes and patch repairs etc. as per clause 1904, 1906 of the Specifications. Twice (In case of hill roads 3 4 Maintenance of drains as per clause 1907 of the Specifications. as and when required). Twice (In case of hill roads 5 Maintenance of culverts and cause ways as per clause 1908 and 1909 of as and when required). the Specifications. 5 6 Maintenance of guard rails and parapet Maintenance as and when rails as per clause 1911 of the required. Repairing once in a Specifications year. Maintenance as and when 2 7 Maintenance of road signs as per clause 1910 of the Specifications. required. Repairing once in every two years. 2 8 Maintenance of 200 m and Kilo Meter Maintenance as and when stones as per clause 1912 of the required. Repairing once in a Specifications. year. Once generally after rains (In 3 9 Cutting of branches of trees, shrubs and trimming of grass and weeds etc. case of areas having rainfall as per clause 1914 of the more than 1500 mm per year, Specifications. as and when required.

-8-

NIT for Repair/ Maintenance (PMGSY)

10 11 12 13

White washing parapets of C.D. Works White washing guard stones Re-fixing displaced guard stones Repair of old joints sealant (CC joints) as in

Once in a year Twice in a year Once in a year Maintenance as and when required. 2 3

Chief General Manager M.P. Rural Road Development Authority Bhopal


Encl.No. 7780 /NIT-Maint. / F.A. / 2011 Date 04/06/2011

Copy to:1. Secretary, Ministry of Rural Development, Rural Development Departments Govt. of India Krishi Bhawan, New Delhi. 2. Secretary, Public Works Departments / Agriculture Department / Finance Department Mantralaya Bhopal 3. Commissioners Public Relation, Ban Ganga Bhopal. 4. Engineer in Chief Public Works Departments, Satpura Bhawan, Bhopal. 5. Chief Engineer, Public Works Departments, Jabalpur/ Gwalior / Indore/ Bhopal /National Highway / Bridge. 6. Managing Director Rajya Setu Nigam, Arera Hills, Bhopal. 7. Chief Engineer, Central Public Works Departments, Arera Hills, Bhopal. 8. All Divisional Commissioners 9. All Collectors 10. Chief Executive Officers, Zilla Panchayat (all). 11. Chief General Manager, MPRRDA, Indore & Jabalpur. 12. General Manager Programme Implementation Units (all).

Chief General Manager M.P. Rural Road Development Authority Bhopal