A 10
B 5 A
C 3 A
D 2 B
E 15 C
F 10 D
G 5 A
H 4 B
I 20 E, G, J
J 30 F, H
25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77
Activity Time ES EF LS LF
A 10 0 10 0 10
B 5 10 15 10 15
C 3 10 13 39 42
D 2 15 17 15 17
E 15 13 28 42 57
F 10 17 27 17 27
G 5 10 15 52 57
H 4 15 19 23 27
J 30 27 57 27 57
I 20 57 77 57 77
SLACK
0 START
0
29 PATHS
0 A-B-D-F-J-I
29 A-B-H-J-I
0 A-C-E-I
42 A-G-I
8
0
0 END
Path 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
A-B-D-F-J-I
A-B-H-J-I GAP
A-C-E-I
A-G-I
Path 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
A-B-H-J-I
A-C-E-I
A-G-I