Question1. ) Calculate the IRR of the Mozal project.

What is the real expected


return using the CAPM so, Why would Gencorp/Alusaf invest in the Mozal project?

Answer:

The internal rate of return of the Mozal project has been calculated using the
projected cash flows presented in the exhibit 6 of case study, however, the
projected cash flows also show an outflow of funds for the dividend payments and
interest payments on subordinate debt, which should not be deducted because they
are part of the owner’s withdrawal. Meanwhile, due to the nature of subordinate
debts they are also like an equity,therefore, a revised cash flow has been
calculated in appendix 1. However, the IRR calculated using the projected cash
flows return a yield of 13.43%, meanwhile, the real expected return has been
calculated using the capital asset pricing model CAPM which required inflation
index rate.

Further, the inflation index rate has been calculated using the fishers’ index,
formula, hence, the resultant real cost of equity has been calculated as 12.91%.
Meanwhile, the IRR measures the return that a particular project is expected to
yield over the life of the project and the real rate of return on equity measures
the company’s specific required rate of return by the equity investors. Therefore,
based on the IRR of 13.43% and real expected return of 12.91% shows that the
project will generate cash flows in excess of the returns required by the equity
investors, hence, Gencorp/Alusaf should invest in the Mozal project to earn a
return of 13.43% on their investment.

Question2. ) What are the greatest risks? Have they been adequately addressed?

Answer:

The Mozal project involves the establishment of a venture between three entities
Eskom, Alusaf and Mozambican government and since the project will require
automated technology and will involve the Mozambican government, which is an
underdevelopedcountry, therefore, the project will be exposed not only to the
technological risks but will also be exposed to the excessive delays in timely
completion of the Mozal project. Furthermore, the operational risks would be
thereregarding the acquisition of resources, additionally, since the Mozal project
is a foreign investment project and would involve foreign currency, therefore,
investment in Mozal project will also involve currency risk.

Technology

Since the project involvesusage of high technology and the success of Mozal project
would largely depend on the success of technology used, therefore, the one of the
greatest risks of Mozal project would be the useof inappropriate technology.
Further, the project is exposed to risk of handling the construction of a project
that requires technology and skills. However, the Alusaf has been involved in the
aluminum business and recognizing the best technology is mere a light judgment for
him. Meanwhile, Alusaf had already used the smelter technology in Hillside smelter
that later turned out to be a meaningful decision. Additionally, the Gencor has the
skills and abilities of constructing the project because he has been the drive
force for handling Hillside smelter project. Hence, the technological risk has been
addressed appropriately because the proven smelter technology would be used in the
Mozal project.

Timely Completion of the Project


Since the government of Mozambique is directly involved in this project, therefore,
it would involve bureaucratic procedures to comply all the legal and legislative
requirements of the state and the Mozal project is subject to approval by the
government of Mozambique thereon.Hence, the project would be exposed to extensive
delays in the meantime. In contrast, Mozambique exists as a weak economy and lacks
sufficient infrastructure to provide a favorable sight to the project therefore,
the project would probably stuck with delays in its completion

However, in order to avoidunconditional delays the company is seeking prior


permission of the state to grant construction permit. Thus an agreement hasbeen
signed with the South African government to address risks associated with delays.
The charter of agreement demonstrates to establish a special liaison committee that
would assist to address the legal matters regarding the legal hindrance
(construction permit).

Meanwhile, the Mozal project demands same staff as previously allocated for the
hillside smelter project to ensure the accuracy and timely completion

Operational Risks

Further, the Mozal project would be exposed to operational risks, because 33% of
the total production cost will be the alumina and the prices of alumina are
readily fluctuating which will lead to high volatile cost of production, hence, the
operations would be exposed to fluctuations in the price of alumina. Meanwhile, the
availability of other raw materials such as petroleum and coke, would carry a
considerable operational risk and similarly the labor issues and the uncertainty of
the final product will also be an operational risk.

Operational risk has been mitigated through a mechanism between input prices of
alumina and the output price where the input price are function of London Metal
Exchange (LME)................

This is just a sample partial case solution. Please place the order on the website
to order your own originally done case solution.

It is June 1997, and a team from the International Finance Corporation (IFC)
recommends that the Council approve the $ 120 million investment in the $ 1.4
billion aluminum smelter in Mozambique, known as the Mozal project. Four factors
make investment controversial: it will be the largest investment by IFC in the
world, the total investment is nearly the size of Mozambique's gross domestic
project (GDP), Mozambique has only recently left the 20-year civil war, and a few
key contractual issues undecided. Because commercial banks refused to finance the
deal, if the IFC is involved, the sponsors asked IFC participation. Whether board
IFC will agree that this is the right time and the right place to make such a large
investment remains to be seen. "Hide
by Benjamin C. Esty, Fuaad A. Qureshi Source: Harvard Business School 20 pages.
Publication Date: November 22, 1999. Prod. #: 200005-PDF-ENG

Related Case Solutions & Analyses:


Mars Incorporated: Online Procurement Arthur Andersen (C): The Collapse of Arthur
Andersen Danfoss Motion Controls And Holip (A) (Abridged) Default ThumbnailDesso
(B): Making It Happen—The Implementation Of A C2C Business Model Default
ThumbnailDo Star Performers Need To Network? (B): Re-Entry & Visibility: Bénédicte
Foucart Default ThumbnailDr. Reddy’s: Medicine Is For People, Profits Follow
Elephant Dung And The Bioethanol Goldrush (B) A Chronology of Integrated Reporting
National Electric Corp. Maschinenbau Arrau AG (A)
← Previous Post Next Post→
Social Share
Share on Facebook Tweet
Hire us for Originally Written Case Solution/ Analysis

Buy Now
Like Us and Get Updates:

Harvard Case Solutions

Search Case Solutions


Search for:

You might also like