Professional Documents
Culture Documents
PGMP Exam Preparation and Study Guide, 3rd Edition
PGMP Exam Preparation and Study Guide, 3rd Edition
PGMP Exam Preparation and Study Guide, 3rd Edition
Study Guide
440 Questions & Answers
Third Edition
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
© June 2018 by Jean Gouix and Martial Bellec.
All rights reserved. These pages contain information about program management material
that is protected by copyright laws. No part of this publication may be reproduced, stored in
a retrieval system, or transmitted in any form or by any means: electronic, mechanical,
photocopying, recording or any other, without the prior written permission of Jean Gouix and
Martial Bellec.
We need you to help us stop Copyright Infringement. As authors of one of the best-sellers for
the PgMP® exam preparation, it happens that this book is unfortunately illegally copied. We
allow people to teach or do financial gain with our book but only under our prior written
permission. When you recognize that contents of this book are used in training sessions that
you attend or purchase, without any mention to a formal agreement with us, please notify us
immediately at program.support@orange.fr. We will then get in contact with the unfair
provider to obtain financial compensation.
Project Management Institute The Standard for Program Management - Fourth Edition,
Project Management Institute, Inc., 2017. Copyright and all rights reserved. Material from this
publication has been reproduced with the permission of PMI.
Your feedback is very important. If you feel you have discovered an error when reading this
study guide, please forward your remark to: program.support@orange.fr
ISBN : 978-2-9546078-1-8
II
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Contents
List of figures..........................................................................................................................VI
Preface.................................................................................................................................. VII
Introduction............................................................................................................................. 1
What is a program?...................................................................................................................... 1
Study Questions........................................................................................................................... 9
Introduction............................................................................................................................... 14
Study Questions......................................................................................................................... 17
Introduction............................................................................................................................... 22
III
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Introduction...............................................................................................................................27
Study Questions......................................................................................................................... 31
Introduction............................................................................................................................... 37
Study Questions......................................................................................................................... 42
Introduction............................................................................................................................... 48
Study Questions......................................................................................................................... 52
Introduction............................................................................................................................... 57
Study Questions......................................................................................................................... 62
Introduction............................................................................................................................... 67
Study Questions......................................................................................................................... 71
Introduction............................................................................................................................... 76
Study Questions......................................................................................................................... 81
Introduction............................................................................................................................... 86
Study Questions......................................................................................................................... 90
IV
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Questions - Answers.......................................................................................................... 93
Domain V Governance........................................................................................................ 95
Introduction............................................................................................................................... 95
Study Questions........................................................................................................................101
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
List of figures
Figure 1 : Program vs. Project.................................................................................................................. 3
Figure 2 : Interdependencies between Projects and Program........................................................... 3
Figure 3 : Portfolio vs. Program................................................................................................................ 4
Figure 4 : Operations vs. Program.......................................................................................................... 5
Figure 5 : The standard - Fourth Edition................................................................................................. 6
Figure 6 : Key elements of program strategy alignment.................................................................... 16
Figure 7 : Environmental analysis........................................................................................................... 16
Figure 8 : Program Life Cycle................................................................................................................. 22
Figure 9 : Program Definition ................................................................................................................. 23
Figure 10 : Program Delivery................................................................................................................ 24
Figure 11 : Program Closure................................................................................................................. 25
Figure 12 : Generic Mind map............................................................................................................. 26
Figure 13 : ECO Tasks Mapping - Initiating - Part 1......................................................................,.... 28
Figure 14 : ECO Tasks Mapping - Initiating - Part 2...........................................................................29
Figure 15 : ECO Tasks Mapping - Planning - Part 1........................................................................... 38
Figure 16 : ECO Tasks Mapping - Planning - Part 2........................................................................39
Figure 17 : ECO Tasks Mapping - Planning - Part 3........................................................................40
Figure 18 : ECO Tasks Mapping - Executing - Part 1............................................................................ 49
Figure 19 : ECO Tasks Mapping - Executing - Part 2............................................................................ 50
Figure 20 : ECO Tasks Mapping - Monitoring and Controlling - Part 1.............................................. 58
Figure 21 : ECO Tasks Mapping - Monitoring and Controlling - Part 2.............................................. 59
Figure 22 : ECO Tasks Mapping - Monitoring and Controlling - Part 3.............................................. 60
Figure 23 : ECO Tasks Mapping - Closing - Part 1................................................................................ 68
Figure 24 : ECO Tasks Mapping - Closing - Part 2................................................................................ 69
Figure 25 : Benefits identification .......................................................................................................... 78
Figure 26 : Benefits realization ...............................................................................................................79
Figure 27 : Benefits transition and sustainment ................................................................................... 80
Figure 28 : Stakeholders are diverse and numerous .......................................................................... 87
Figure 29 : Stakeholder map.................................................................................................................. 88
Figure 30 : Engaging Stakeholders ....................................................................................................... 89
Figure 31 : Governance Plan................................................................................................................. 96
Figure 32 : Governance Board vs. Program Management................................................................97
Figure 33 : Program Governance and Governance Board...............................................................99
VI
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Preface
About the First and Second Editions of this Study Guide
The first two Editions of this Study Guide generated an outstanding feedback from our
readers, as most of them reported that it helped them significantly to pass the exam. All really
appreciated the first sections, whose aim was to demystify program management, and to
enable them to try and answer initial sample questions. Most questions were indeed an
occasion to approach actual exam conditions, to clarify concepts, to understand the tricks,
to learn “subtle" differences between terms or situations, and to transform doubts into
certainties.
This PgMP® Exam Prep Study Guide 3rd Edition primarily aims at aligning the book to the
Standard for Program Management - Fourth Edition1 (the standard). We believe that this
Fourth Edition of the standard is a big step forward, as it mainly emphasizes and clarifies the
five major domains of program management: strategy alignment, benefits management,
stakeholder engagement, governance, and life cycle management. This approach is very
much in-line with the Examination Content Outline (ECO)2, April 2011, which we already took
as a reference document for the previous Editions of our study guide.
Although the standard is still based on the 5 same performance domains, it has evolved from
a process-based document to a principle-based one, which means that the standard shifted
away from supporting processes to supporting activities. These activities are aligned with
program life cycles phases.
Several artifacts are removed from the standard. For instance, the program plan is now
removed and more emphasis is now placed on the program charter. The mandate (or
strategic mandate) issued by executives is still referenced but with less emphasis.
For detailed information about the changes, please refer to Appendix X1 of the standard
1 The Standard for Program Management - Fourth Edition, Project Management Institute Inc.,2017
2 Program Management professional (PgMP) Examination Content Outline, Project Management Institute
Inc., 2011
VII
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
2- Comments from readers:
We have added 5 Study Questions to the 5 existing ones after each performance domain.
This book now contains 100 Study Questions which cover all program domains and
subdomains detailed in the standard and in the ECO.
Next, we received many suggestions from readers, to provide more information in order to
help them better understand program management fundamentals, which is a prerequisite to
address exam questions. As a consequence, we introduce 170 Tutorial Questions which are
directly related to the content of the standard.
So, in addition to the revised 170 Practice exam-like Questions which have been updated,
the reader will find 270 additional questions which are directly related to the standard
content.
Our Study Guide now contains a total of 440 Questions with answers, which doubles their
number when compared to the previous Editions!
We have been encouraged by several readers and PgMP® exam candidates to reference
our online courses in this Study Guide. This is why we have extracted a set of slides from the
PgMP® exam prep course, and inserted them after the performance domain sections of this
Study Guide.
For more information on these online courses, please refer to our web site:
www.jmetraining.com where you will find all needed information about the courses as well as
our coaching and presential services.
This book has 10 sections related to domains and program life cycle phases. Each section is a
tutorial that the reader may refer to: project practitioners, PMP®3 credentialed practitioners,
executives, consultants in project and program management, teachers, entrepreneurs or
salesmen in the field of project management, etc.
The book is primarily written for experienced practitioners in program management whose
goal is to become PgMP® credentialed.
VIII
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Thanks and Acknowledgments
We want to thank our spouses Mireille and Isabelle for their patience and support while we
spent many long hours reading PMI documents, creating new questions, updating the Study
Guide, and working on our computers. We also thank Olivier Gouix, Jean’s son, for the design
of the Study Guide covers. Olivier is an expert in professional video and graphics design.
(oliviergouix@gmail.com)
Jean and Martial
IX
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
About the Authors
Jean Gouix, PMP, PgMP
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
About our online PgMP® Exam Prep package
As a complement to this Study Guide, we have developed an online PgMP® exam prep
course.
Our course includes a series of online modules, all based on The Standard for Program
Management - Fourth Edition and the PgMP® Examination Content Outline, or ECO. It is a
complement to the Study Guide with many more details which are useful to prepare for the
exam. The modules consist in a series of slides, illustrated by several colored drawings, with
many references to the standard and to the ECO, and exam like questions/answers. This
course includes an audio A-to-Z case study which illustrates key concepts and artifacts (golf
estate program)
We also offer additional coaching sessions which you can tailor to your needs.
XI
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Rationale of this Book- Third Edition
How is our Study Guide structured?
The ECO is the result of a Role Delineation Study (RDS) which was conducted by PMI, in order
to specify the role of the program manager.
The Multiple Choice Questionnaire (MCQ) comprises 170 questions essentially scenario-based,
which address the five domains defined by PMI in the current Examination Content Outline
(ECO), dated 2011 as summarized in the following table6:
5 Program Management Professional (PgMP®), Examination Content Outline, April 2011. Published by PMI©
6 The number of questions has been rounded to the closest integer number
XII
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
About the Standard for Program Management - Fourth Edition
The objective of the standard is to offer information related to the good practices in program
management. Core and supporting activities are documented. These activities are mapped
onto the program life cycle phases where most of the work takes place.
The structure of the standard is identical to the structure of the ECO: both are based on the
same five domains (also called performance domains).
The THREAD that leads from the ECO, via the standard, to the exam questions is as follows.
Let’s take an example: You are a program manager engaged in stakeholder
management/engagement activities for your large program.
In addition, we have inserted mind maps related to the Program Life Cycle (PLC) subdomains
detailed in the ECO. In each mind map we list activities, key outputs, and we propose a link
to the tasks specified in the ECO document. Please note that this is our interpretation of the
link between the standard and the ECO, which is not formally expressed by PMI.
XIII
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Structure of the Study Guide
In section 1, a general presentation reviews the fundamentals of a program from the point of
view of both the standard and practical experience. The other sections simply follow the
domains/ subdomains as described in Table 1 and include a short summary, 10 Study
Questions and their answers.
• Study Test: 100 Study Questions (SQxx). For each of the 10 domains/subdomains:
o 5 Study Questions for an introductory section about program management
o 5 Study Questions scenario-oriented
o They provide ALL readers with a better understanding of the PgMP® exam
context, and assess whether they should go for it or not
• Tutorial Test: 170 Tutorial Questions (TQyy):
o A set of 170 Tutorial Questions which directly relate to the content of the
standard
o To make sure that ALL readers deeply understand the fundamentals and key
concepts of the standard before going to the practice test, at the pace of the
actual exam (4-hours)
o We recommend to reach 80 % of good answers before getting to the practice
test
The Tutorial Test questions are found in the middle of the book and candidates are
invited to attempt them in a single 4-hour session, under actual exam conditions.
The 170 answers are then given with a clear explanation or direct reference to the
standard or to the PMBOK® Guide.
XIV
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
We encourage you to read the following PMI® publications:
[1] The Standard for Program Management - Fourth Edition. Project Management Institute,
Inc. We also call it "the standard” in our book.
[2] PMI Code of Ethics and Professional Conduct. Project Management Institute, Inc.
[3] Program Management Professional (PgMP)® Examination Content Outline (ECO). Project
Management Institute, Inc. April 2011.
[4] The Standard for Portfolio Management - Fourth Edition. Project Management Institute,
Inc.
[5] A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Sixth Edition.
Project Management Institute, Inc.
Throughout this book these publications will be referred to by their number in brackets. For
example, [1, section 1.2xx] means "The Standard for Program Management - Fourth Edition,
section 1.2xx”.
XV
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Introduction
What is a program?
“A program is a group of related projects, subsidiary programs and program activities that
are managed in a coordinated way to obtain benefits not available from managing them
individually” [1, section 1.2]
A program must contribute to the strategic vision, goal, and mission of the performing
organization. It is often seen by the executive management as an efficient manner to
implement key parts of the strategy and transform them into tactical goals.
A program fulfills its tactical objectives thanks to an integrated, balanced and optimized
coordination approach. A collective pool of human resources, procurement sources, facilities
or equipment is monitored by means of a centralized Program Management Information
System (PMIS). Disagreements are smoothed out with the use of smart resource sharing; while
decisions, management and control follow the same rules and policies by means of a well-
established governance structure.
A program needs a strong collective vision so that its numerous stakeholders all commit to
the realization and adoption of the projected outcomes. While program performance is
assessed by means of pre-established metrics, communication towards stakeholders is
planned and carefully tailored to the available media (ranging from interpersonal
relationships through to modern internet tools). This is the minimum requirement to ensure a
smooth transition to operations.
Special attention is paid to risks that may jeopardize the targeted benefits. Program level risks
must be explicitly identified; their impacts must be adequately evaluated and mitigated.
Program managers are responsible for the definition of the overall vision and of the program
scope, in coherence with the strategic objectives. They have to define a comprehensive
roadmap explaining key program events and how and when the individual benefits may
contribute to those strategic objectives. The overall program budget is under their control
according to governance rules, which will clearly state the delegated level of their authority
within the program. Most of the time, they will be responsible for preparing major decisions or
arbitrations to be taken by the governance board. Program managers guarantee that
changes are managed fairly and uniformly throughout the program. In order to maximize
program outcomes, they always keep in mind the informal as well as clearly defined inter
dependencies between projects. Program level risks and issues are carefully registered and
monitored while project level ones are left to project teams.
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Their primary goal is to ensure stakeholder satisfaction and ultimately to make sure that
benefits are transferred to operations in a sustainable manner.
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Project vs. Program
The difference between a program and a project is simply depicted in Figure 1.
Benefits: they may be tangible (e.g. business or profit increase) or non-tangible (cultural
change, acquisition of a new technology, or change of a “century-old" process) and are
always defined with respect to the strategy of the performing organization.
Governance: programs are complex in nature and they focus the interests of several
diverging entities or people. Smart governance is necessary to make sure that decisions
are fair, appropriate and committed to by all.
Stakeholders: must be identified, ranked in terms of influence and adherence to program
benefits, or their ability to produce benefits.
Stakeholders Schedule
The relationships between a program and a project are iterative and cyclical (Figure 2).
While the program provides direction to projects, projects report performance to the program
when progressing, escalating risks and issues. Based on this performance evidence, the
program redirects the projects if necessary.
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Portfolio vs. Program
As depicted in Figure 3, a portfolio does not need to have interdependencies between its
constituent components. These components may be projects, programs or operations. They
may be linked in several ways, ranging from a same background technology, same business
units, same geographical areas or same lines of products.
Portfolio
Integrated
mode
However, the portfolio implements the strategic orientations of the performing organization
by allocating resources to these components. Thus, the portfolio is a powerful tool used to
meet the strategic objectives of an organization.
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Program Portfolio
Interdependencies Made up of constituent There are not necessarily
components that have dependencies between
interdependencies components within a
portfolio
Objectives Strategic goals, create benefits, Business driven only
not necessarily to make money:
skill acquisition, operation
transformation, public welfare
improvements, public research,
line of products, management of
major organizational changes,
etc.
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
The Standard - Fourth Edition in a nutshell
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Figure 5 depicts the 5 domains of the standard :
1. Strategy alignment (section 3 of the standard) is about making sure that the expected
benefits of the program are identified and realized according to the organizational
strategy. The question is not to elaborate this strategy but rather to initiate and
guarantee the delivery of sustainable benefits that serve this strategy.
2. The next essential domain is called benefits management (section 4) which follows a
rather classical approach: identification, analysis and planning, delivery, transition,
and sustainment.
3. Programs are complex in nature and most of the time, stakeholders (section 5) are not
only numerous but they also disagree about the directions to give or to update. A
complete domain is devoted to this aspect, covering stakeholder identification,
planning, and engagement. It is important to note that the standard refers to
stakeholder “engagement" rather than to stakeholder "management”. Indeed, the
question is not to manage the stakeholders themselves but preferably their
"expectations", thus their engagement to the program.
4. Governance (section 6) is about the program management framework, functions,
processes or procedures. A clear governance structure needs to be established and
individual roles must be well identified in order to avoid potential conflicts or clear
them. The responsibilities of the Governance board must be clearly defined, including
decision taking rules, and issue escalation processes. Components which compose
the program are not under the direct authority of the program (Governance) board
because they fall into the local management of the program itself. Sometimes, the
Governance board has the power to approve the passage of components from one
life cycle project phase to another. This is to make sure that the projects’ outcomes or
deliverables will clearly contribute to the realization of the final benefits, thus to the
strategic goals of the program.
5. Program Life Cycle (section 7) has been extensively simplified in the fourth edition of
the standard. Of course, a program, like a project, has a beginning phase - namely
definition phase - and an end - namely closure phase. The program delivery phase
lies in between and is an essential period of the program.
All work performed in a program for the purpose of program management is collectively
known as program activities, (standard, section 7.2.1). All program activities are
interpedendent and complementary. At program level, each activity produces outputs
(deliverables) used by other activities. They also use outputs (deliverables) created by
project-level activities.
The core activity (or better, activities) called Program Integration Management occurs
across the entire program life cycle. The standard identifies five core activities (section
7.2.2) which we will discuss in the next sections of this book.
Supporting activities which are related to program management such as
communications, procurements, quality, etc. very similar to the knowledge areas
identified in the PMBOK® Guide, but here identified at program level. Each supporting
activity is mapped onto the program life cycle phases where this activity will most
likely be performed.
Main outputs from all these activities are mentioned in the standard and in this Study Guide.
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
The standard mentions a number of program artifacts. The word “artifact” may sound unusual
at first, as its classical definition is “object fabricated by a human being”. In the standard,
artifacts should be understood as any formal, oral, written or informal program management
document, piece of work, action, study, etc. This Edition of the standard does not provide
anymore a comprehensive list of program artifacts. However, this Study Guide reflects our
understanding of when these key artifacts are initiated, developed and maintained during
the Program Life Cycle.
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
The following list of study questions will help you prepare for the exam.
Study Questions
5 questions directly related to the standard
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ5
What are the skills commonly required by program managers?
a- Stakeholder engagement strategic management leadership, analytical and integration
skills
b- Stakeholder engagement, change management, leadership, analytical and integration
skills
c- Stakeholder engagement, governance, benefits management, strategic alignment skills
d- Stakeholder engagement, strategic management, leadership, negotiation and integration
skills
10
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ8
A program is made up of a number of projects or discrete components. These components
mainly consist of activities organized to produce specific deliverables. Aggregation of these
deliverables at the program level serves the strategic benefits of the performing organization.
Program management targets the definition and production of strategic benefits. According
to the following choices, which one BEST describes how the discrete outcomes produced by
the projects will be organized at the program level?
a- The unitary deliverables produced by all discrete components should have a one-to-one
relationship with the benefits of the program. Then, it is easy to justify the budget for each of
them
b- Each project outcome is targeted in order to be directly transitioned to the operations
c- The interdependent components are integrated, controlled and monitored in order to
deliver program’s strategic benefits
d- All the unitary deliverables produced by the discrete components will be justified in front of
the SAME business objective as their hosting portfolio
11
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Questions - Answers
Study Question SQ1
b- The standard, section 1.4.3
12
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ9
a- No! This is correct; at the beginning, the program directs the projects and afterwards,
projects update performance and status, and based on this information, the program
redirects them, b- No! This is true; the program is in charge of giving clear goals to projects, c-
No! This is especially true in big programs, d- Correct answer! In fact the program may deliver
incremental benefits. In this case, projects providing early benefits may be terminated while
some others are still being executed.
The standard, section 1.4.3
13
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Domain I Strategic Program Management
Introduction
Number of questions in the exam: 15% = 25/26 questions out of a total of 170 questions
Identifying opportunities and benefits that achieve the organization’s strategic objectives
through program implementation [3, page 3]
It describes 11 tasks:
The Program Strategy Alignment Performance Domain is part of the program management
framework, and is detailed in section 3 of the standard.
Please note that the term ‘Strategic Program Management1 used in the ECO and the term
‘Program Strategy Alignment’ used in the standard relate to the same Performance Domain.
Highlights
The Strategic Program Management domain seeks to ensure that the program outcomes will
be aligned with the strategic objectives of the performing organization; this will be verified by
the Governance board throughout the lifetime of the program. As such, strategic
management is considered by company executives as a guarantee that the strategy of the
organization will be understood and implemented down to the lowest level of component
projects, related activities, and by all contributing individuals. Strategic management also
ensures that the impact of the benefits will be positive, sustained, and that the associated
costs are acceptable.
Thus, for simplicity’s sake, we can claim that strategic management targets a clear and
sound high level and comprehensive description of the program objectives and explains how
they refer to the more global strategic objectives of the organization.
14
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Posture
As a program manager regarding the strategy alignment domain, your posture should be as
follows:
• Strategy: Don’t get it wrong! You have to align the program objectives to the
performing organization’s strategy, but as a program manager, it is not your job to
define the strategy of the performing organization.
• Be clear and simple: You always have to clearly show that progress in the delivery of
benefits is aligned with the strategic goals of the organization. The program roadmap
and the benefits management plan are powerful tools to clearly inform and convince
executives, sponsors, program and project team members that the program direction
is sound and clear.
Key outputs
The outputs of strategic management should be easy to communicate, discuss and adapt. In
other words, the outputs come together to form a compacted resume of program basics
(Figure 6).
The Program Business Case is the justification (business impact, expected benefits, risk, etc.)
for authorizing the program.
The Program Charter defines WHAT the program’s goals and objectives are, formally
authorizes the program, provides the program manager with the authority for leading the
program and includes:
• Program Vision describes the ‘to be ' state of the program (‘where are we going to?’)
and guides the development of the program charter over its life
• Program Mission Statement is a list of actions beginning with an infinitive form of a
verb: “To verb xxx”. It summarizes ‘what needs to be done’ in order for the program to
succeed. It serves as a basis for listing all the actions that have to be carried out for
ultimate program success. It also describes the values and the purpose of the
program
• Program Goals and Objectives describe what the program is expected to deliver in
support of the business case
• Expected high-level benefits
• Metrics for success as well as key success factors
• Assumptions and Constrains
The Program Roadmap describes when major program events will occur, such as major
outcomes, benefits and milestones, as well as when major decisions will have to be made. It
may also describe how they will happen, especially when referring to relationships between
secondary outcomes or constraints like available funds, contract notifications or market
surveys.
15
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Figure 6 : Key elements of program strategy alignment11
Various studies help assess the program’s ultimate chance of success, such as environmental
analyses (comparative advantage, SWOT, feasibility studies, assumptions and historical
information analysis (Figure 7).
11 This figure is an excerpt from our online courses (Module 7- Strategy Alignment)
16
The following list of study questions will help you prepare for the exam.
Study Questions
5 questions directly related to the standard
17
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ14
What is the BEST definition of the program roadmap?
a- A chronological representation of the program’s intended deliverables and outcomes
b- A chronological representation of a program’s intended direction, graphically depicting
dependencies between major milestones and decision points in order to reflect the pace at
which benefits will be realized
c- A chronological representation of a program’s intended direction, in order to reflect the
pace at which resources will be consumed
d- A chronological representation of detailed schedules of future projects to be launched
18
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ18
Among the following answers, which one BEST describes why organizations initiate programs?
a- To optimize resource usage
b- To comply with regulation
c- To group several projects
d- To deliver benefits
19
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Questions - Answers
Study Question SQ11
d- The standard, section 3
a- Correct answer! Portfolio management is NOT concerned with managing components. This
is the responsibility of the program and project managers, b- Wrong answer! This is a true
statement. Portfolio management interacts with a number of organizational activities
(functional groups, production, manufacturing, finance, IT, HR, etc.) c- Wrong answer! This is
a true statement. The portfolio manager must regularly review the portfolio content d- Wrong
answer! This is part of the portfolio manager’s responsibilities.
The standard for Portfolio Management - Fourth Edition, sections 1.6, 1.7, and 1.8
20
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ19
a- No! This is the portfolio manager's role, b- No! This is the portfolio manager's role. The
program manager should ensure that the program remains aligned with the strategic
objectives, but not to confirm they are! c- Correct! d- No! This is the portfolio manager's
role.
PgMP® Examination Content Outline 2011 / Strategic program Management - Task 4 and
standard, section 1.7 (role of the program manager, second paragraph)
21
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Domain II Program Life Cycle
Introduction
Number of questions in the exam: 44% = 75 questions (approximately) out of a total of 170
questions. These 75 questions are spread over five subdomains which are examined in the
study guide.
Programs, like projects, have a life cycle which is composed of sequential, and sometimes
overlapping, phases. The breakdown of the life cycle into phases provides better control over
the program management activities. The standard breaks down the program life cycle into
three phases which may sometimes overlap: [1, Fig.7-1 ].
Highlights
• Progressively elaborate how the program will be aligned with the strategic objectives
of the performing organization,
• Define the expected program outcomes, and
• Obtain approval from the Governance board to further proceed.
13 This figure is an excerpt from our online courses (Module 5 - Program Life Cycle)
22
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
The Program definition phase is divided into two overlapping subphases:
• Program formulation in which the program sponsor and the program manager are
assigned. During this subphase, the business case, the program charter and the
program roadmap are developed. Please note that in many instances a preliminary
business case is established earlier and refined during this subphase. Also, estimates of
scope, resources, cost, risks, etc. are often conducted during this subphase.
• Program planning. The program charter is formally approved before entering into the
Program planning subphase, in which the program management plan is developed to
organize the delivery of the desired benefits. During this subphase, the program
governance structure is established, and the initial program organization is deployed.
The main objectives of the Program delivery phase are to, authorize, plan and perform
component activities in order to deliver planned program benefits. Proper integration of
component activities into the program is a key ingredient for the program success.
Components will iterate through three component-level subphases:
14 This figure is an excerpt from our online courses (Module 5 - Program Life Cycle)
23
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Figure 10 : Program Delivery 15
The main objective of the Program closure phase is to execute a controlled closure of the
program. The Governance board will agree with program closure when all benefits are
realized within the timeframe off the program, or when evidence shows that benefits will be
sustainable after the program closure, and when all outcomes are in place to transition the
program to a receiving organization. On some occasions, the program may be terminated
early, when it becomes evident that it will not achieve its objectives.
15 This figure is an excerpt from our online courses (Module 5 - Program Life Cycle)
24
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Operational
activities
At the end of each phase, a gate review should take place under the authority of the
steering committee (also called Governance board), and a go/no-go decision should be
made about moving on to the next phase or stopping the program.
Please note that Domain II (Program Life Cycle) of the Examination Content Outline (ECO) is
composed of five subdomains, which address program management tasks related to:
1. Initiating
2. Planning
3. Executing
4. Controlling
5. Closing
These subdomains are mapped onto the program life cycle phases where they mostly occur:
It should be noted that initiating, planning, executing, controlling and closing tasks occur in
EACH phase of the program life cycle. Any given phase must be initiated, planned,
executed, controlled and closed!
16 This figure is an excerpt from our online courses (Module 5 - Program Life Cycle)
25
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Generic Mind map
For each ECO subdomain of the Program Life Cycle, we have attempted to link Activity
Group described in the standard and their activities to outputs, and then to ECO tasks under
the following generic mind map format:
Posture
As a program manager regarding the program life cycle, your posture should be as follows:
Do not confuse the life cycle of a program and the life cycle of a project. A project
has a beginning and an end. This is very ‘structuring’, especially for gate reviews
which consider the ability of the project to ultimately deliver the outcomes and
authorize the project to continue to the next phase. For a program, the gate reviews
are more focused on performance and strategic alignment and may not be directly
related to the life cycle itself. For example, a high level gate review may be
specifically planned for sign-off by the final customer of an important interim benefit.
Concentrate your efforts on defining and closing the program. A program is complex
in nature, with many diverging opinions between stakeholders, especially at the
beginning; and benefits will not be sustained if you do not put in place a smooth
transition to operations.
26
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Domain II Program Life Cycle / Subdomain
Initiating
Introduction
Number of questions in the exam: 6% = 10 questions out of a total of 170 questions.
The Examination Content Outline describes tasks related to Initiating the Program as:
Defining the program and constituent projects, and obtaining agreement from stakeholders
[3, page 3]
It describes 6 tasks:
Initiating tasks identified in the ECO are mainly performed during the program formulation
subphase of the Definition phase of the program. The standard identifies the list of core and
supporting activities related to this subphase, and their key outputs. We have attempted to
relate outputs to ECO Task numbers (where applicable), which we present in Figure 13 and
Figure 14.
27
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Program scope management
Figure 14 : ECO Tasks Mapping - Initiating - Part 2
29
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Highlights
The tasks related to “initiation” aim to define the program direction, the needed resources
envelopes, and the financial framework (funding sources, flows of money, etc.). An initial risk
assessment needs to be performed. An initial list of benefits must be identified and documented in
the initial benefits management plan. The benefits' timeline is illustrated by means of a high level
roadmap. Two key persons shall be assigned at the end of the formulation subphase: the sponsor
that brings the strategic guidance and the funds in coherence with the first cost estimates, and the
program manager. The program manager will then structure the initial program core team and
move forward with an approved charter. The list of the most important stakeholders should be
known at this stage as well as their major expectations. The governance structure should be defined,
but will not be operational yet.
Posture
As a program manager regarding the initiating sub-domain, your posture should be as follows:
• First key - your sponsor: It is important to understand that most of the time; the decision to
run a program will come from the top of your organization. Your sponsor is a very important
person (or group of people) to work with. They provide the program rationale, its ultimate
direction, in-line with the more global strategy of the performing organization. Do not forget
that the sponsor provides the needed resources and that you must convince them that the
benefits will be realized with the allocated amount of resources, during this time frame, with
an accepted level of risks.
• Second key - the stakeholders: You cannot ignore the fact that some discrepancies in terms
of approaches, phasing, and objectives may exist, for instance between functional
managers, who will provide resources, and the program clients. You need to know them well
and build good working relationships with them.
• Third key- YOUR personal vision of the program: you have to mentally imagine what and how
your program will deliver. You need to have a clear idea of the major benefits, when they
should occur, and a good idea of the way you will deliver them. In other words, you already
have the headlines of the battle plan in your head before moving forward.
30
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
The following list of study questions related to ‘Initiating the program' will help you prepare for the
exam.
Study Questions
5 questions directly related the standard
31
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ25
Which activities support program formulation?
a- Program change assessment, program quality assessment, program initial cost estimate, and
program scope assessment
b- Program change assessment, program governance assessment, program stakeholders
assessment, and program schedule assessment
c- Program change assessment, program information management assessment, program initial
program cost estimate, and program initial benefits evaluation
d- Program strategy evaluation, program procurement assessment, program life cycle assessment,
and program communications assessment
32
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ28
Your construction company has run many programs during recent years, and almost all programs
run so far are very similar in nature. In your company, lessons learned have been captured, and
many standards (quality, regulations, success, etc.) have been developed and repeatedly re-used
in various programs. You have been nominated as program manager for construction program X
which is composed of three component projects: A, B and C. You are in the definition phase of
program X and you are in the process of identifying success criteria for the program and for the
component projects. According to the following options, what will be the MOST appropriate way to
handle this situation?
a- Define standard measurement criteria for success for program X and for the three component
projects
b- Define standard measurement criteria for success for program X but let each project manager
define the success criteria for their project. They have enough experience
c- Do not use standard measurement criteria for the success of program X. “Similar programs” does
not mean they are identical
d- Ask the PMO to define those measurement criteria. They are the experts
a- Continent A
b- Continent B
c- Continent C
d- Continent D
33
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ3Q
The concept of initiating Program X has been accepted by a group of company executives who
ask you to prepare the documentation to formalize the acceptance of the program, and to present
it at the next steering committee meeting. With a group of experts, you initiate feasibility studies,
conduct a series of SWOT sessions on risk identification, lead comparative analyses with competition,
and also perform cost/benefit analyses to define the expected benefits. What are you trying to
CREATE?
a- The program scope statement
b- The program roadmap
c- The program mandate
d- The program charter
34
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Questions - Answers
Study Question SQ21
b- The program management plan is developed during the Program Planning subphase, after
creation of the charter. The standard, section 7.1.2.1
a- No! The answer assumes that there is one invited person per nation, which is not mentioned in the
text. b- Correct! You should have 4 regional head-offices, managing 6 business unit managers. The
number of nations is a trap. c- No! You assume that all nations are represented in the 4 regional
head-offices, which is either not very likely or not clearly stated in the text. d- No! You assume that
all nations are represented in the 6 business units, which is neither very likely nor clearly stated in the
text.
a- Correct! This is a list of items you should include in the program charter (plus some more) b-
Wrong answer! The program charter should not include planned RFPs or RFIs. Too early! c- Wrong
answer! The program charter should not include screening and scoring options for vendors. Too
early! d- Wrong answer! The program charter should not include planned contract types. Too early!
PgMP® Examination Content Outline 2011 / Initiating the program - Task 1 and standard, section
7.1.2.1
35
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ28
a- Correct! Standards exist in your company; use them for the program and for the projects. This will
ease their monitoring and controlling. b- No! You should try to define standard criteria for all
projects, c- No! You should try to define standard criteria for all projects. d- No! The text says that
standard criteria have already been defined in your company. No need to define them again. Most
importantly: try to define STANDARD criteria for the program and for components!
a- No! Continents C and D outperform continent A. b- No! Continents C and D outperform continent
B. c- No! Continent D outperforms continent C. d- Correct! Continents C and D outperform continents
A and B. Continent D is preferred because it gives superior results when interest rates are higher,
which is the MOST probable case because of the global business situation.
a- No! The program charter is the correct answer, b- No! The program roadmap which is also an
output from the "Program initiation" does not formally authorize the existence of the program. The
program charter does! c- No! A program mandate may be issued by the program governance
board, but it only addresses the strategic objectives and the planned benefits for the program. The
program charter comes after the program mandate and is more complete, d- Correct! All are
activities performed during Program Formulation in order to create the program charter which
formalizes the existence of the program.
PgMP® Examination Content Outline 2011 / Initiating the program - Task 1 and standard, section 3.4.2
and section 7.1.2.16
36
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Domain II Program Life Cycle / Subdomain Planning
Introduction
Number of questions in the exam: 11%= 19 questions out of a total of 170 questions.
The Examination Content Outline describes tasks related to Planning the Program as:
Defining program scope and developing the program, including all constituent projects, and all
activities that occur within the program [3, page 3]
It describes 9 tasks:
Planning tasks identified in the ECO are mainly performed during the planning subphase of the
Program Definition phase of the program. The standard identifies the list of core and supporting
activities related to this subphase, and their key outputs. We have attempted to relate outputs to
ECO Task numbers (where applicable), which we present in Figure 15 , Figure 16 and Figure 17.
Please note that the standard 4th Edition does not mention the Program management development
core activity which was mentioned in the 3rd Edition and which we believe is a key activity,
because it creates one of the most important artifacts in program management: the program
management plan. We have added it in Figure 17.
37
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Program scope statement tf
Program communications
management plan
Program communicat
Program communications
management Communication requirements
inputs to Stakeholder register
38
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Figure 16 : ECO Tasks Mapping - Planning - Part 2
39
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Figure 17 : ECO Tasks Mapping - Planning - Part 3
40
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Highlights
“Planning tasks" are mainly performed during the program planning subphase of the Definition
phase. In this subphase, the program management plan is developed by the program
management team and approved by the Governance board. This management plan contains all
the subsidiary plans which are needed to proceed to the delivery phase of the program. This list is
rather similar to that of a project. However, the plans are all developed at program level even if
some portions of the plans may be generically applied to all components (for instance quality
standards, risk checklists or procurement processes and templates). At the end of the Definition
phase, the Governance board is working with a finalized structure and clearly established rules and
processes. However, the components are not yet formally authorized; this will be done in the next
phase.
Posture
As a program manager regarding the planning sub-domain, your posture should be as follows:
• Elaborate every plan in detail: the program management plan is rather similar, in terms of
exhaustive content, to the project management plan. It contains all the details explaining
how you plan program’s activities in order to organize, realize, transition and sustain the
strategic benefits. During this phase, you will need the help of several program team
members (including the PMO) that will support you during work decomposition (PWBS) and
specify how to do the work.
• Keep flying high: it is rather obvious that you will have to go into very specific details quite
often, but your role is to back off from time to time, in order to guarantee consistency
between all the plans, to understand interactions, and to compensate for negative side
effects from one plan to the next. It is exactly the same as building a complex house of
cards, stay patient, but always think in terms of your program's global balance.
41
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
The following list of study questions related to ‘Planning the program’ will help you prepare for the
exam.
Study Questions
5 questions directly related to the standard
42
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ35
The program management plan is developed during the program planning subphase of the
program definition phase, on a number of inputs. What BEST describes this list of inputs?
a- The organization’s strategic plan, the business case, and realized benefits
b- The strategic plan, the business case, and the governance plan
c- The business case, the program charter, and the assessments completed during program
formulation
d- The organization’s strategic plan, the business case, the program charter, and the assessments
completed during program formulation
43
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ38
44
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ40
You ore developing the schedule for your program. The program is composed of three component
projects: A, B and C. Project managers A and B are familiar with the critical chain method and plan
to use it on their projects. Project manager C plans to use the critical path method. In parallel you
have started to develop the program master schedule and you have prepared a Gantt chart which
shows the major activities and program milestones. You have set-up a meeting with your project
managers in order to choose a scheduling tool for the projects and for the program. What is the BEST
option for it?
a- Impose Gantt as the common scheduling method, because Gantt charts are very popular
b- Impose the critical chain method because the method is well known by two project managers
c- Impose a common scheduling tool
d- Let each project manager decide which tool she is most comfortable with
45
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Questions - Answers
Study Question SQ31
a- Wrong! Programs and projects should have access to a PMIS. b- Wrong! Programs and projects
should have access to a PMIS. c- Wrong! Programs and projects should have access to a PMIS.
d- Correct! You can use the existing PMIS as a base and extend it for the program and the two other
projects.
a- No! This is not enough to ask for program closure, b- Correct! If all exit criteria are met you can
ask for program closure. c- No! This is not enough to ask for program closure, d- No! This is not
enough to ask for program closure.
46
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ38
a- Wrong answer! b- Wrong answer! c- Wrong answer! d- Correct! Program packages are defined as
‘the lowest level of the PWBS’. And there are 9 of them!
PgMP® Examination Content Outline 2011 / Planning the program - Task 8 and PMBOK® Guide,
section 5.4 and section 6.2
a- Correct answer! Because of the worldwide coverage of the program, co-location should not be
considered as a team development option, b- Wrong answer! This should be applicable, c- Wrong
answer! Because they are junior technicians, training may be a good option, d- Wrong answer!
Team rewards should help to develop team spirit!
PgMP® Examination Content Outline 2011 / Planning the program - Task 15 and PMBOK® Guide,
section 9.4.2 (develop team - Tools and Techniques)
a- No! Although Gantt charts are very popular, you should not impose them. There may be more
appropriate scheduling tools accepted by all. b- No! This is not a valid reason. Try to have a
common tool. The critical chain method may not be adequate for project C or for the whole
program.c- Correct answer! Whatever scheduling tool is chosen, it should be the same for projects
and program scheduling. At least, for the sake of simplicity, you should try to only have one
common scheduling tool. d- No! Try to impose a unique scheduling tool. This will ease your job!
47
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Domain II Program Life Cycle / Subdomain Executing
Introduction
Number of questions in the exam: 14% = 24 questions out of a total of 170 questions.
The Examination Content Outline describes tasks related to Executing the Program as:
Performing work necessary to achieve the program’s objectives and deliver the program benefits
[3, page 3]
It describes 9 tasks:
Executing tasks defined in the ECO are mainly performed during the Delivery phase of the program.
The standard identifies the list of core and supporting activities related to this phase, and their key
outputs. We have attempted to relate outputs to ECO Task numbers (where applicable), which we
present in Figure 18 and Figure 19.
Note: ECO Tasks 19, 20, 21,23 are part of the program manager’s responsibilities. They are not linked
to any specific activity mentioned in the standard.
Please note that some of these activities, such as cost budgeting, cost estimation, risk identification,
risk analysis, and risk response management, are also heavily evoked during the Program Planning
subphase of Program Definition
48
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Program risk register updates
Program risk identification
Presentations
-------------------------------------------------------- 1
Prog ram communications I Public announcements
ECO Executing Sub
Domain. Part 1
! management
Information distributed to
stakeholders
-ECO Task 22
, . . . : ECO Task 18
Lessons learned reports f
Program information
Inputs to other management
management
plans
49
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Figure 19 : ECO Tasks Mapping - Executing - Part 2
50
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Highlights
The majority of the tasks related to “executing” are carried out during the Delivery phase of the
program life cycle. This phase is essential to the benefit creation. The components are initiated
(‘chartered’) once their interfaces have been carefully revisited in order to maintain a consistent
program architecture. They are then executed, and their closure is approved (but not performed
yet; see closure activities). Resources are prioritized and reallocated to meet program needs,
procurements are conducted according to prior resource allocations, appropriate sellers are
selected, contracts are signed, and payments are made. The budget is refined and broken down to
the component level. In order to keep stakeholders engaged, the necessary and sufficient
information is distributed to them.
Posture
As a program manager regarding the executing sub-domain, your posture should be as follows:
• Deliver! Your goal is to deliver the benefits; you are running a benefit factory, you have to
make sure that all processes are running in parallel, by ensuring with or without the program
team, that every single piece of work is duly defined AND delivered.
• This is not monitor and control: When focusing on delivery, you assume by default that the
interactions between activities are working satisfactorily. Clearing potential unbalance or
negative dependencies (delays or unsatisfactory outcomes) are activities which do not
belong to “executing” but more to “controlling”.
51
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
The following list of study questions related to 'Executing the program' will help you prepare for the
exam.
Study Questions
5 questions directly related to the standard
52
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ45
Which activity is defined as the CORE activity in the standard?
a- Program communications management
b- Program integration management
c- Program procurement management
d- Program scope management
53
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ48
You are managing a program that is composed of three component projects: A, B and C. You just
exited the definition phase. Project managers are identified and you start the execution of the
program in order to generate planned deliverables and to create expected benefits. Project A will
provide two deliverables, project B will provide three deliverables, and project C will provide four
deliverables. Projects B and C are more critical for the program success than project A. You
understand that, in order to initiate program components, you will have to issue component
initiation requests which will be reviewed by the program governance board. According to the plan,
you have issued a request to initiate component project A. This request has been rejected by the
board. What is the MOST probable cause for the board refusal?
a- Project A does not have a sponsor
b- Project A does not have an identified manager
c- Project A does not have a business case
d- Project A only provides two deliverables and project C provides four deliverables, so project C
should start first
54
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Questions - Answers
Study Question SQ41
b- The standard, section 7.1.3
a- No! You need to obtain governance board approval to close them. b- Yes! When you want to
transition a component of your program, you need to send a request to the steering committee
which will then approve or disapprove, c- No! You need to issue a component transition request,
not a component initiation request, d- No! You need to get approval from the steering committee to
close this component.
PgMP® Examination Content Outline 2011 / Executing the Program - Task 24 and standard, section
6.1.11
a- Correct answer! The program roadmap (which is part of the program management plan) provides
this information. b- No! The program business case does not contain this detailed information. c-
No! The benefits management plan provides all details about the realization of the planned benefits
but it does not specify when projects should be initiated, d- No! The program charter does not
contain this detailed information.
PgMP® Examination Content Outline 2011 / Executing the Program - Task 21 and standard, section
3.3
55
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ48
a- Wrong answer! By default, YOU are the project sponsor! b- No! The text says that all component
project managers are identified, c- Correct answer! This is the most probable cause for the board
refusal. The standard says that the program manager frequently acts as the sponsor for components
and the component needs to have a business case. d- No! This is not a valid reason. The text says
that the request for initiation is issued according to the plan.
PgMP® Examination Content Outline 2011/ Executing the Program - Task 16 and standard, section
6.1.11
a- Wrong answer! All are valid methods to communicate program status, b- Wrong answer! All are
valid methods to communicate program status. c- Wrong answer! All are valid methods to
communicate program status, d- Correct answer! Informal meetings are not considered a valid
method for communicating program status.
PgMP® Examination Content Outline 2011/ Executing the Program - Task 18 and standard, section
8.2.2.1
a- Correct answer! Lessons learned should be collected, and information sessions should be
organized with key stakeholders throughout each program life cycle phase. Lessons learned
updates are an output from the "Information distribution" activities, b- Wrong! Lessons learned should
be collected, and information sessions should be organized with key stakeholders during each
program life cycle phase, c- No! Lessons learned should be collected, and information sessions
should be organized with key stakeholders during each program life cycle phase. d- No! Lessons
learned should be collected, and information sessions should be organized with key stakeholders
during each program life cycle phase, not only when a major event occurs.
PgMP® Examination Content Outline 2011 / Executing the Program - Task 18 and standard, section
8.2.4.1
56
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Domain II Program Life Cycle / Subdomain Controlling
Introduction
Number of questions in the exam: 10%= 17 questions out of a total of 170 questions.
The Examination Content Outline describes tasks related to Controlling the Program as:
Monitoring progress, updating program plans as required, managing change and risk [3, page 3]
It describes 6 tasks:
1. Compare actual trends and variances to plans and identify corrective actions
2. Apply corrective actions
3. Manage program issues
4. Manage changes
5. Assess impact of changes and get approval from governance
6. Manage risks
Monitoring and Controlling tasks defined in the ECO are mainly performed during the Delivery phase
of the program. The standard identifies the list of core and supporting activities related to this phase,
and their key outputs. We have attempted to relate outputs to ECO Task numbers (where
applicable), which we present in Figure 20, Figure 21 and Figure 22.
57
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Figure 20 : ECO Tasks Mapping - Monitoring and Controlling - Part 1
58
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Figure 21 : ECO Tasks Mapping - Monitoring and Controlling - Part 2
59
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Figure 22 : ECO Tasks Mapping - Monitoring and Controlling - Part 3
60
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Highlights
The program is now executed according to “what is documented in the program management
plan", in order to deliver benefits in-line with the strategic objectives of the performing organization.
Very often, the complexity of the factors influencing the delivery of benefits make things happen
differently from what was originally planned.
In other words, according to Murphy’s Law17, "It is found that anything that can go wrong generally
does go wrong sooner or later”.
Therefore, the “Monitoring and controlling" activities simply target monitoring these deviations and
taking the right decisions with respect to the strategic outcomes of the program.
mitigating the reasons for deviations in order to keep the objectives unchanged or,
- if it is not possible, updating the program objectives to take into account the factors outside
the control of the program
These updates are the result of decisions taken at program level, and take into consideration
feedback such as: performance reports, risk register and related preventive actions, program
forecasts, or benefits realization reports. Actual deviations from the original plans are documented
by means of: change requests to the program management plan, budget, master schedule or
stakeholder strategy. Decisions are taken according to the governance rules in several ways:
payment approvals, plan updates or go/no-go decisions.
Posture
As a program manager regarding the executing sub-domain, your posture should be as follows:
• Watch and stay tuned! In order to make subsequent corrections, the first step is to always
have a clear view of what is going on. Stay informed in all aspects of the program by
soliciting and collecting information from those “who know”. This flow of information is the
basis of a sound, accurate and detailed understanding that legitimizes these changes.
• Define and share the changes: The second step is to define the necessary changes in all
aspects of the program. If you are the initiator, make sure that all interested parties commit
to the decision (program change control). If not, clarify the intention; do not forget that a
brilliant idea is only valid when it is understood and applicable by all.
• Implement the changes: track what, when, who, how to perform the changes. Make sure
that what has been decided is implemented as agreed; if not, the program’s credibility will
suffer, as this reflects your own capacity to keep the program on track.
17 http://en.wikipedia.org/wiki/Murphy's law
61
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
The following list of study questions regarding 'Controlling the Program' will help you prepare for the
exam.
Study Questions
5 questions directly related to the standard
62
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ55
CORRECTIVE and PREVENTIVE actions are needed to bring the program back in alignment with:
a- The strategic priorities
b- The original budget
c- The original schedule
d- The sponsor priorities
63
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ59
You are managing a program which has four component projects: A, B, C and D. During the
definition phase of the program, with the help of the PMO, you have defined several rules for your
project managers, such as: all issues must be logged in a project issues register, with a predefined
code, in order to be able to track them easily. You request that the status of those issues be reported
and discussed during your weekly status meetings with the project managers. During today’s
meeting, project manager C reports a high severity issue which has a major impact on the delivery
of a project outcome which is urgently expected at program level. During the meeting, project
manager A says that he encountered a similar problem, and it took him a long time to develop a
correction which works. The correction is documented. Project manager A proposes to provide the
fix to project manager C. What IMMEDIATE action should be taken?
a- The program manager immediately brings the meeting to a close and asks project manager C to
apply the fix right away
b- Project Manager C reads the documentation related to the correction, and then decides
whether or not to apply the fix
c- Project manager C applies the correction to project C with the assistance of a person from
project A
d- The program manager spends the necessary time to understand what the similarities between
projects A and C are
64
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Questions - Answers
Study Question SQ51
a- The standard, section 8.2.8
PgMP® Examination Content Outline 2011/ Controlling the Program - Task 30 and PMBOK® Guide,
section 7.3.2.3
PgMP® Examination Content Outline 2011/ Controlling the Program - Task 28 and standard, section
2.5.2 (program vs. project change) and PMBOK® Guide, section 4.6
65
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ59
a- No! This is a program review; you have many other items for today; please go on with the
meeting, b- Correct! Project manager C should first carefully read the existing documentation before
deciding to apply it or not. c- No! Project manager C should first read the documentation before
applying it. d- No! This may take too much time, and is not very productive.
PgMP® Examination Content Outline 2011 / Controlling the Program - Task 28 and standard, section
8.1.2.1
66
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Domain II Program Life Cycle / Subdomain Closing
Introduction
Number of questions in the exam: 3% = 5 questions out of a total of 170 questions.
The Examination Content Outline describes tasks related to Closing the Program as:
Finalizing all program activities, including all constituent components, executing transition plans,
archiving, obtaining approvals, and reporting [3, page 3]
It describes 5 tasks:
1. Complete a final report of actual trends and variances to original plans to determine
program performance
2. Obtain stakeholder approval for closure
3. Execute the transition to operations in order to maximize the sustainability of the program
4. Conduct the post review meeting and elaborate lessons learned
5. Disseminate lessons learned, best practices and recommendations for future programs
Closing tasks defined in the ECO are mainly performed during the Closure phase of the program. The
standard identifies the list of core and supporting activities related to this phase, and their key
outputs. We have attempted to relate outputs to ECO Task numbers (where applicable), which we
present in Figure 23 and Figure 24.
67
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Figure 23 : ECO Tasks Mapping - Closing - Part 1
68
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Figure 24 : ECO Tasks Mapping - Closing - Part 2
69
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Highlights
Closing a program is very similar to closing a project, with some additional specific activities. A final
report is issued, so that performance is assessed with respect to the original intention; this intention
consists mainly in delivering benefits aligned with the organization’s strategy. The final report
contains lessons learned which are consolidated, documented, disseminated and archived so that
future management initiatives can benefit from them.
Component projects as well as procurements must be closed BEFORE program closure. At each
component closure, program closure activities should be performed to capture information which
may impact the program, such as redeployment of component resources within or outside the
program, reallocation of unused budget, capture of lessons learned, etc. Disbandment of the
resources is organized, and most importantly human resources are returned to their functional
teams, except those who are needed to support operational transition.
Acceptance of the results is generally confirmed by receiving sign off from the sponsor, client or
steering committee.
The program manager may close the program only AFTER the steering committee (or the sponsor
alone) has delivered a formal closure acceptance.
Posture
As a program manager regarding the executing sub-domain, your posture should be as follows:
The following list of study questions regarding ‘Closing the Program’ will help you prepare for the
exam.
70
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Questions
5 questions directly related to the standard
71
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
5 questions scenario oriented
72
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ69
Program X has three component projects: A, B and C. All three component projects have been
closed with the agreement of the steering committee. One month later, the program is still not
closed. Generally, the final decision to close a program is under the sponsor’s responsibility. What is
the MOST probable cause for NOT closing program X?
a- Not all of the expected benefits have been realized
b- The program closure recommendation was not formulated by the steering committee
c- The steering committee has been disbanded
d- The program sponsor has left the organization
73
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Questions - Answers
Study Question SQ61
c- The standard, section 7.1.3.3
PgMP® Examination Content Outline 2011 I Closing the program - Task 32 and standard, section
72.2.5
PgMP® Examination Content Outline 2011 I Closing the program - Task 31 and standard, section
72.2.5
74
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ69
a- No! All expected benefits may not occur before the program ends. b- Correct answer! This is the
most probable cause for not closing the program. c- Wrong ansyyer! It may be true, but it is not the
most probable cause for not closing the program, d- No! That may be the case, but it is not a valid
reason not to close the program!
PgMP® Examination Content Outline 2011/ Closing the program - Task 32 and standard, section 6.2.2
PgMP® Examination Content Outline 2011 / Closing the program - Task 32 and standard, section
7.2.2.5
75
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Domain III Benefits Management
Introduction
Number of questions in the exam: 11%= 19 questions out of a total of 170 questions.
The Examination Content Outline describes tasks related to Benefits Management as:
Defining, creating, maximizing, and sustaining the benefits provided by programs [3, page 3]
It describes 8 tasks:
Both the Examination Content Outline and the Standard for Program Management address the
Benefits domain.
The standard describes the relationship between the program life cycle and program benefits
management [1, figure 4-1]. It is important to note that activities related to benefits management
are performed during several program life cycle phases. For instance:
Highlights
Programs are undertaken to create BENEFITS. This is the PRIMARY reason to create and manage
programs. Benefits will provide VALUE to the program beneficiaries that will utilize them.
Posture
The benefits are defined and scheduled in order to provide strategic progress to the performing
organization. As a program manager, you have to make sure that the benefits management plan
has the following characteristics:
• Have a clear big picture: you have to always be in a position to clearly and simply show the
rationale, progress, performance, aggregation, even sublimation of the major components
that contribute to the expected benefits. If your messages are complex, confusing, unclear;
76
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
• there is a high probability that a number of stakeholders will not understand their share of
involvement
• Prove the promise: the big picture described above is your “passport”, enabling you to cope
with barriers and reluctance. It is a convincing set of documents that efficiently shows the
power of your approach; you do not just promise, but you prove that the benefits will be
there, and be sustained.
FAQs
• What is a benefit?
The gains and assets realized by the organization and other stakeholders as the result of outcomes
delivered by the program [1, glossary]
The answer is clearly ‘yes’. Project benefits are usually produced in the form of deliverables. These
deliverables may be raised up to program level “as is”, or aggregated together to produce a
program-level benefit. In most cases, programs are undertaken to produce benefits which are
significantly larger than those coming from projects alone [1, section 4 introduction].
The answer should be ‘yes’. However, it is sometimes difficult to measure certain non tangible
benefits, such as: company image, morale improvement. In these cases interviews, polls, public
opinion, etc. should help to provide metrics. There should be an effort, in any program, to define
metrics for the planned benefits, such as ‘10% increase in revenue’, 20% workload reduction’, etc.
The answer is ‘no’. In some programs, benefits may be incremental. For instance, an increase in
revenue may occur step by step during the life of the program, and the targeted benefit may be
realized at the end of the program, or even after the program is over.
The answer is ‘not always’. In most programs, benefits will be realized before the end of the program,
but in some cases, all or some benefits will only be realized after the program is concluded. Please
also note that, in some cases, all benefits may be delivered at the same time (for example, the
construction of a big building). The program manager should develop both a transition plan which
describes how benefits will be transitioned to the receiving organization, and a sustainment plan
which will detail post-transition activities related to the benefits realization within the receiving
organization.
Because programs are undertaken to provide benefits to an organization, planned benefits, at least
major ones, should be identified very early on during the program's life cycle: the program business
case which ‘puts the program on track’ when it is accepted, should contain these expected
benefits. A program mandate is sometimes issued by executives along with a preliminary business
77
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
case. After approval of the business case, the program charter is developed and formally expresses
expected benefits. Then the program roadmap provides the benefits delivery timeline. During
program formulation, the program manager is usually not yet known. Therefore, planned benefits will
generally be identified by other persons close to the company strategy (executives, portfolio
managers, sponsors, etc.).
During the life of the program, new opportunities may appear and new benefits may emerge (Ex:
new customer request, market change, environmental opportunities, new organizations, etc.). After
endorsement by the Governance Board, the program manager should make every possible effort to
transform those opportunities into positive results for the performing organization.
First, benefits need to be identified and recorded in the benefits register which is developed during
the benefits identification phase. KPIs are identified for each benefit and are also recorded. The
benefits register will be updated during follow-up phases.
Projects that contribute to program benefits must be identified and the responsibility for realizing
those benefits must be clearly assigned. Additionally, metrics should be defined for each benefit.
Programs generate outcomes (results), and intermediate benefits which contribute to the final
expected benefits. The program roadmap indicates the major events related to the creation of the
benefits (intermediate or incremental, and final). The program roadmap is an input to the creation
of the more detailed program schedule. (See standard, sections 3.3 and 8.1.2.11). Benefit models
such as benefit mapping tools can help the program manager to ensure that final benefits,
intermediate benefits, program outcomes, project deliverables, etc. remain satisfactorily
78
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
interdependent and ‘aligned’ during the program's life cycle. The benefits management plan
details when and how planned benefits will be achieved.
The major goal of program management is to make sure that benefits are realized as expected.
Program governance provides the right structure to track benefit realization over the life of the
program, through day-to-day program and project management activities, phase-gate reviews,
health checks, audits, etc.
Sponsor
Business case
$$$
Monitoring and reporting on benefits metrics defined in the benefits management plan make it
possible to understand the extent of the realized benefits.
In addition, it is of primary importance to make sure that benefits remain aligned with the business
case content. This is also true at program closure.
79
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Who is accountable for benefit realization?
Project deliverables contribute to benefits. Therefore, project managers have their share of
responsibility! Additionally, the program manager is responsible for making sure that program
outcomes contribute to the realization of the benefits.
The standard considers that the sponsor has the responsibility to enable the delivery of benefits
[1, section 6.2.1].
• Benefits sustainment
During the program life cycle, the program manager must make sure that benefits will be sustained
by the receiving organization, after the end of the program. The program sustainment plan should
be developed prior to program closure to make sure that benefits will actually be delivered as
planned. [1, section 4.5].
The following list of study questions related to ‘Benefits management’ will help you prepare for the
exam.
80
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Questions
5 questions directly related to the standard
81
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
5 questions scenario based
82
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ79
You manage program X which is composed of four projects: A, B, C and D. From the beginning of
your program, you have been extremely sensitive to the fact that program outcomes must generate
benefits which are in line with the strategic objectives of your company. The program is well
underway, but you realize that several opportunities have emerged that your program could take
advantage of. You believe that with a few more resources added into the component projects,
more benefits could be generated. You think about what you should do in order to seize the
opportunities for your program. What is the IMMEDIATE action you should take?
a- You start interviewing new people with the objective of increasing the size of your project teams
b- You tell your sponsor that your program will be updated to seize these opportunities
c- You inform key stakeholders that your program will include these opportunities
d- You ask that the business case of your program be updated and re-evaluated with the new
opportunities
83
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Questions - Answers
Study Question SQ71
b- minimizing negative impacts is as important as realizing the benefits, and should be managed,
measured and properly communicated to affected stakeholders The standard, section 4
PgMP® Examination Content Outline 2011 / Benefits Management - Task 1 and standard, section
7.2.2.5
a- Wrong answer! 'Increased market share' is a benefit which can be measured and tracked,
b- Wrong answer! 'Lower manufacturing costs' is a benefit which can be measured and tracked.
c- Wrong answer! 'Faster product delivery' is a benefit which can be measured and tracked.
d- Correct! 'Better administrative support' does not mean that much. It will actually be difficult to
track and analyze. You need to be more specific. Other answers can be tracked and analyzed.
84
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ79
a- No! You are going too fast! You don't yet have the agreement to get new people, b- No! You
are going too fast! You should discuss it with your sponsor, but don't tell them yet that your program
will be updated; it's too soon! c- No! This is too early. You may inform key stakeholders about the
possibility of including these opportunities, but it is only a possibility. d- Correct answer! This is the best
action to take. The business case of your program will need to be updated and validated with the
new opportunities, before deciding to proceed or not.
PgMP® Examination Content Outline 2011/ Benefits Management - Task 8 and standard, section 4.5
85
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Domain IV Stakeholder Management
Introduction
Number of questions in the exam: 16% = 27 questions out of a total of 170 questions.
The Examination Content Outline (ECO) describes tasks related to Stakeholder Management as:
Capturing stakeholder needs and expectations, gaining and maintaining stakeholder support, and
mitigating/channeling opposition [3, page 3]
It describes 7 tasks:
The Examination Content Outline addresses the Stakeholder Management domain and the
standard for Program Management addresses the Stakeholder Engagement performance domain.
In fact, these domains are identical. The standard prefers to use the word ‘engagement’ rather than
the word ‘management’. The program manager does not directly manage stakeholders, but rather
needs to manage their expectations. The important point is that all stakeholders must remain
‘engaged’ throughout the program life cycle!
Highlights
Because of program characteristics (scope, length, cost, etc.), the number of program stakeholders
is usually much larger than on a given project. For this reason there is an emphasis on program
stakeholder management/engagement.
1. Program Stakeholder Identification. This Lists all stakeholders, creates the stakeholder register.
2. Program Stakeholder Analysis. This identifies stakeholders’ needs, expectations, interest,
influences etc. The program manager may develop a stakeholder map in order to visually
represent their position [1, figure 5.2].
3. Program Stakeholder Engagement Planning. This develops the stakeholder engagement plan
that contains stakeholders’ engagement metrics.
4. Program Stakeholder Engagement. This measures and ensures that all stakeholders remain
adequately engaged throughout the program’s life cycle. A log (record) should be
developed in order to track stakeholders' issues and concerns. The program manager often
utilizes strong communication, negotiation, and conflict resolution skills during this period.
5. Program Stakeholder Communications. The program manager must engage effective
communication with all stakeholders and pay maximum attention to key stakeholders with
‘high power' and ‘high influence’ over the program.
86
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Posture
You have to make sure that the relevant information is always given on time to your stakeholders.
You have to constantly update the stakeholder register, and really "keep in touch", through phone
calls, planned meetings, or simple courtesy visits.
When a stakeholder is losing engagement, e.g. non-attendance or non-participation in an
important meeting, or not preparing an expected presentation as previously agreed-upon; simply
find out what’s the matter and propose a sensible way forward.
Save your energy for the most important stakeholders, whether they are ‘positive or negative’ about
the program. Don’t waste much time on a degrading relationship that has little impact on your
program. Engagement is not about maintaining good social relations, but merely about the positive
impact on your program.
FAQs
• Who do we call ‘program stakeholders’?
Program stakeholders are the people and organizations that can positively or negatively impact the
program outcomes, or be impacted by the program outcomes. Because of their importance, the
program manager should identify them as soon as possible and develop a plan to ‘manage’ their
expectations. New stakeholders may join the program and others may disappear over its life time,
and stakeholders’ attitudes may evolve.
The main stakeholders should be identified very early on, even before program initiation. During the
program definition phase, the program manager will continue to identify stakeholders, build
categories (internal, external, etc.) and then sort them into smaller categories. Stakeholder
identification should occur throughout the life of the program. The stakeholder register contains the
list of all stakeholders, their expectations and the degree to which they support the program.
21 This figure is an excerpt from our online courses (Module 9 - Stakeholder Engagement)
87
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
A stakeholder map can be developed to visualize their expected influence on the program.
High
Low Interest
• The program sponsor who provides program resources and is accountable for enabling
program success. He/she is also often the program ‘champion’
• The portfolio manager
• The program Governance board members (or steering committee members)
• The program manager
• The program team members
• The component (project) managers and components team members
• The PMO (Program Management Office)
• Funding organization(s)
• Performing organization(s)
• Regulatory agencies
• Customers, vendors, suppliers, competitors, etc.
• What tools or sources can be used to identify and analyze program stakeholders?
22 This figure is an excerpt from our online courses (Module 9 - Stakeholder Engagement)
88
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Brainstorming sessions, historical information, focus groups, questionnaires, interviews, surveys, etc.
• How does the program manager track and measure stakeholders’ engagement?
In addition to the stakeholder register, the program manager will need to develop a stakeholder
engagement plan which describes HOW the stakeholders are engaged, and contains metrics to
measure stakeholders’ activities, such as attendance at and participation in key meetings, amount
of communication with the program team, engagement in program activities, etc. The stakeholder
engagement plan is a subsidiary plan of the program management plan.
An issue log will also be created in order to track and help solve stakeholders’ issues.
High
Power
Low
23 This figure is an excerpt from our online courses (Module 9 - Stakeholder Engagement)
89
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
The following list of study questions related to ‘Stakeholder management/engagement' will help you
prepare for the exam.
Study Questions
5 questions directly related to the standard
90
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ85
What is the primary role of the program sponsor?
a- The program sponsor is accountable for the program success
b- The program sponsor is accountable for enabling the program success
c- The program sponsor is responsible to achieve program objectives
d- The program sponsor provides only financial resources to the program
91
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ88
You ore managing a program in a construction company. You know that many stakeholders will be
impacted by the results of the program. You have performed an in-depth analysis of the
stakeholders and you have developed the stakeholder engagement plan. Key stakeholders have
been identified and recorded in the stakeholder register. A detailed communication plan specifying
key meeting dates has been distributed to all stakeholders. Your program is progressing well, but
your project managers report the fact that more and more key stakeholders do not show up at key
meetings. Your project managers do not know if this non-attendance is really impacting their
projects or not. You realize that, in the stakeholder engagement plan, certain information is missing
with regard to stakeholder engagement in program activities. What did you forget?
a- You did not develop stakeholder metrics in order to help track stakeholder attendance at key
meetings, and identify potential risks caused by their non-participation
b- You developed stakeholder metrics but you did not identify who the key stakeholders are, and
what their expectations are
c- You did not develop a stakeholder register with the list of key stakeholders and their expectations
d- You did not communicate to key stakeholders the fact that they should attend those meetings
92
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Questions - Answers
Study Question SQ81
d- The program manager is NOT a member of the steering committee. The standard, section 5
PgMP® Examination Content Outline 2011 / Stakeholder Management - Task 1 and standard, section
5.1
93
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ89
a- Wrong answer! This method may take a lot of time and may not be the most efficient, b- Wrong
answer! This method may take a lot of time and may not be the most efficient. Also, existing
checklists may not be appropriate for your needs. c- Wrong answer! You have already started to
interview some of them and you are looking for a more efficient tool. Individual interviews usually
take a lot of time! d- Correct answer! Focus groups with open-ended questions sessions allow
participants to interact with each other. Where groups are concerned, focus groups are known to be
more efficient than other methods. The text specifies that 'Many stakeholders come from the same
business unit'.
PgMP® Examination Content Outline 2011 / Stakeholder Management - Task 2 and standard, section
5.2
94
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Domain V Governance
Introduction
Number of questions in the exam: 14% = 24 questions out of a total of 170 questions.
Establishing processes and procedures for maintaining proactive program management oversight
and decision-making support for applicable policies and practices throughout the entire program
life cycle [3, page 4]
It describes 11 tasks:
Both the Examination Content Outline and the Standard for Program Management address the
Governance domain.
Highlights
A program is often much more complex to manage than a standalone project: it typically has
numerous stakeholders, complex risk management requirements, internal interdependencies
between components, and dependence upon external factors, etc. This makes decision-making
and following-up benefit realization highly complex, with many contradicting factors.
As a result, the governance plan aims mostly at properly managing the program by providing:
95
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
• A planned and uniform standard level of quality, risk mitigation and change control all of
which are subject to review or audits,
• A guarantee that effort is efficiently and unambiguously made, through usage of metrics and
accountability tools, in order to ultimately deliver benefits in-line with the strategic objectives
of the performing organization.
Most organizations establish a program Governance board (or steering committee) whose main
activities are to oversee program management activities and make decisions according to pre-
established rules.
96
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Figure 32 : Governance Board vs. Program Management25
Posture
As a program manager regarding the governance sub-domain, your posture should be as follows:
• Procedures: You have to make sure that the procedures for decision making processes are
clearly stated, shared and known by all stakeholders. These procedures should always be
referred to when there is a conflict.
• Decisions: You definitely need to make decisions, but not ALL of them! Some decisions must
be made by the Governance board. You should consider the Governance board as a single
individual in charge of approving or rejecting top level decisions, scenarios, and directions,
etc. Your job is to clearly explain the possible choices and alternatives, assessing them by
means of multi-criteria grids if needed, but the Governance board always has the final
WORD.
• Power: The Governance board is a committee where various powers and interests may
compete. Your role is not to impose your personal views and fight, but rather to create the
conditions so that the power, and the interests of all stakeholders are considered when an
important decision is taken. This may range from simply making sure that a consensus is
reached, to collecting relevant opinions when documenting a decision. Once the decision is
taken, you are empowered by the Governance board to ensure its pre-agreed, effective
implementation. Manage to win over opposition with explanations, and reserve the right to
say: “This is a decision taken by the members of the Governance board, and if you do not
agree with it, I can ask them to consider your alternative.”
97
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
FAQs
• What does ‘Program governance’ mean?
The standard defines ‘Program governance’ as ‘the framework, functions, and processes by which a
program is monitored, managed, and supported in order to meet organizational strategic and
operational goals'. Sound governance creates and manages the necessary and sufficient
conditions to make sure that the decisions will be made clearly, and shared by all stakeholders.
Obviously, we can also include the people in charge of ‘governing’ the program. (Governance
board members, program manager and program team members, component project managers,
etc.). The standard provides a list of main program governance roles (section 6.2)
The Governance board (also called Program board or Steering committee) is responsible for
providing appropriate support for the conduct of the program, approving appropriate program
governance systems and methods, providing and securing proper program funding, endorsing a
decision-making body for approving and supporting recommendations (for instance, the program
quality plan), as well as monitoring and tracking the progress of the program through phase-gate
reviews, health checks, reviews and audits.
The Governance board will usually authorize components initiation and closure. In addition, the
Governance board will approve program closure.
During the Program definition phase (program planning subphase), Program governance will issue a
Program governance plan which defines HOW and also who, when, etc. the program governance
will be conducted. The Program governance plan is usually included in the program management
plan.
98
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Program Governance
It varies according to the size and nature of the organization. This Governance board is usually
composed of senior-level persons, change manager, sponsor organization, functional managers,
etc. For small organizations, the program sponsor can be the sole member of the Governance
board. Please note that the program manager IS NOT a member of the program Governance
board. The program manager reports to the Governance board during the program’s life cycle.
The board should ensure that a mandate has been issued by senior-level people to initiate the
program. The board should also ensure that the program is correctly funded. Then, during the
program definition phase, the Governance board will approve the program charter and the
business case. The Governance board will approve the passage from one phase to another. The
Governance board will approve component initiation and component transition or closure, based
on pre-defined criteria. The board may also be involved in decisions related to changes and issues
(escalation process). The board will also approve recommendations for the program closure.
The program manager and the program team often have a similar governance function for
program components. The relationship between the program Governance board and the program
is usually similar to the relationship between the program management team and the component
projects even if, in some rare cases, the Governance board may like to have direct control over
components.
99
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
European cultural differences
In Continental Europe, program managers have a cooperative role: they are often only in charge of
asking for decisions to be made by the Governance board and executing the program according
to the guidance provided. This posture is often due to a weak balanced weighted matrix of
responsibilities within Continental European organizations, where functional managers and
respective directors have much more power than the program manager.
In US and UK management cultures, the program manager is often seen as THE boss throughout the
whole of the performing organization. In this case the program managers are supervised by
executive management (or by the steering board) which empowers them to set-up, execute,
control and close the program in order to drive the ultimate delivery of targeted benefits.
Please keep in mind that most exam questions refer to the second type of organizations.
100
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
The following list of study questions related to ‘Governance’ will help you prepare for the exam.
Study Questions
5 questions directly related to the standard
101
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ95
What is NOT TRUE about program quality governance?
a- Minimum quality criteria can be common to all components
b- Core quality management processes may be identified at component level
c- Specific program level quality processes may be defined
d- There is never a need to address this at program level because quality governance is addressed
at component level
102
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ99
There are several factors that may influence benefit realization: quality, stakeholders' engagement,
financial sourcing, market conditions, the political climate, etc. Another important factor is related to
risks. As a program manager, you have to regularly provide updated information related to program
risks to your governance board. Among the following choices, what BEST describes this updated
information?
a- It provides all details on project risks and on component risks. It allows the governance board to
make decisions based upon the severity of the risks that are affecting the program and the
components
b- It gives the minimum but sufficient information related to existing and new risks so that the
governance board can understand whether or not strategic benefits are jeopardized within this
program
c- It mainly consists of program and project risk register updates
d- It mainly consists in updating the risk register and the stakeholder register
103
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Questions - Answers
Study Question SQ91
d- Program decision making and NOT project decision making! The standard, section 6
104
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Study Question SQ99
a- No! As program manager, you have to provide PROGRAM LEVEL information to the governance
board. You cannot only provide details but must also provide a proven analysis showing how risks
may impact the strategic objectives of your program, b- Correct! This is the only purpose of this
document at governance board level, c- No, as program manager, you cannot provide details
only but must also supply a proven analysis showing how risks may impact the strategic objectives of
your program. Even if the risk register provides an exhaustive description, it does not explain how risks
impact altogether the strategic benefits of your program. d- No! As program manager, you cannot
only provide details but also must supply a proven analysis showing how risks may impact the
strategic objectives of your program. Even if the risk register provides exhaustive descriptions, it does
not explain how risks impact altogether the strategic benefits of your program.
PgMP® Examination Content Outline 2011/ Governance - Task 6
105
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
170 Tutorial Questions
Guidelines to test your knowledge of the standard
Before getting to the exam questions, you need to have a good knowledge of the Standard.
Most Exam Questions are scenario based, BUT a thorough understanding of the concepts
documented in the standard is A MUST in order to succeed!
We propose a list of 170 Tutorial Questions, denoted TQyy, (with answers) which are mostly
addressing concepts defined in the standard and some in the PMBOK® Guide.
By experience, we believe that you need to correctly answer around 80% of the questions before
taking the mock-exam test of 170 Practice questions.
Another purpose of this test is also to be trained to sit an exam for 4 hours in a row. You have 4 hours
maximum to complete all the questions.
While doing this Tutorial Test, please note each answer on a separate blank sheet.
106
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ3
One of the fundamental differences between projects and programs are found in the way they are
managed in response to change.
Which statement is WRONG about project and program change management?
a- Project change management is mainly used to monitor and control the amount of variance from
the cost and schedule baselines
b- Project change management is used to manage the variance caused by known risks
c- Programs use change management in a forward-looking proactive manner to adapt to the
evolving environment
d- Programs employ change and change management to constrain or control the impact of
variability on their baselines
107
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ7
What is NOT a true statement about governance?
a- Program governance focuses on controlling program scope, time and cost
b- Component project governance is often achieved through actions of the program manager
c- Project governance focuses on controlling project scope, time and cost
d- The program governance board is the decision-making body in charge of approving
recommendations about the program
108
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ11
You are managing a program which has three components. Each component has signed contracts
with various sellers. One of the sellers calls you and requests that his contract be modified for good
reasons.
What is the BEST way to handle this request?
a- Refuse to modify the contract because it has been signed by both parties
b- Ask the seller to contact directly the CCB (Change Control Board)
c- Accept because it is for good reasons
d- Ask the seller to follow the change procedure which is specified in the contract
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ16
To beat competition and increase market share, your company has decided to launch a top priority
program in order to develop and market a product which will use a brand new technology.
The program you will manage has three components. Your company wants to launch the program
as soon as possible but one of your components does not have all the needed critical resources.
What is the BEST scenario to solve the skilled resources issue for your strategic program?
a- Do nothing and tell the component manager to accept the risk
b- Tell the board that you would like to subcontract the difficult part to an outside company
c- Ask the component manager to send the team to training courses
d- Do not take the risk and stay with the old technology
110
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ20
You are managing a program which has great difficulty to deliver its planned benefits. It is
becoming obvious that one of the component projects, project A, is the main cause of the
difficulties.
WHAT should be your attitude with regard to this situation?
a- You ask manager A to take corrective actions
b- You ask manager A to take preventive actions
c- You ask the program sponsor to discuss with manager A
d- You look for a replacement of manager A
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ25
The management of your organization is in the process of deciding which program to launch,
between program X and program Y. Based on below information, which is the BEST option?
a- Launch Program X because it is strategic for the organization even though its business case shows
that expenses will be greater than short term revenue
b- Launch Program X because its business case shows that revenues will be much lower than
expenses
c- Launch Program Y because its business case shows that both expenses and revenues will be low
d- Launch both Program X and program Y because their business case is very similar
112
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ29
You want to formally communicate your program’s status.
What is NOT the best method to do this?
a- Face-to-face meetings
b- Presentation to a group of stakeholders
c- E-mails
d- Program team members meeting
113
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ34
You are managing program X which is composed of three projects: A, B, and C which have created
all expected benefits. Time has come to close the program, except the fact that some contracts are
still open but are due to close very soon.
You have the governance board agreement to close the program.
What should be your NEXT action?
a- You should close the program because you have the board agreement
b- You should close the program because all contracts will close soon
c- You should not close the program until all contracts are closed
d- You should close the program because all benefits have been created
114
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ38
When you started managing program X, you noticed that one of the key stakeholders was very
opposed to it. During the course of the program, you have spent a lot of time communicating with
this stakeholder, and you notice that this stakeholder has completely changed his attitude and is
now very positive about the program. Where should you record this change in his attitude?
a- In the stakeholder engagement plan
b- In the stakeholder register
c- In the issue log
d- In the stakeholder breakdown structure
115
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ42
The management of your organization is in the process of deciding which program to launch,
between program X and program Y. Based on below information, which is the BEST option?
a- Launch Program X because it is strategic for the organization even though its business case shows
that expenses will be greater than short term revenue
b- Launch Program X because its business case shows that revenues will be much lower than
expenses
c- Launch Program Y because its business case shows that both expenses and revenues will be low
d- Launch both Program X and program Y because their business case is very similar
116
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ46
Resource prioritization decisions should be based on the guidelines defined in:
a- The governance plan
b- The stakeholder engagement plan
c- The program charter
d-The program resource management plan
117
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ50
A program manager is managing a program with 8 team members, and 1 client.
How many communication channels exist between these stakeholders?
a- 12
b- 90
c- 45
d- 36
118
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ55
A detailed strategy for effective stakeholder engagement covers the following:
a- Stakeholder engagement guidelines and level of support in various components of the program
b- Stakeholder engagement guidelines to exclude negative individuals with the help of their
managers
c- Stakeholder engagement guidelines to provide rewards to individuals actively promoting the
program
d- Stakeholder engagement guidelines and level of support at program level
119
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ59
The program roadmap and the program master schedule are two important artifacts in program
management.
Which statement is NOT true about them?
a- Actually they are identical and synonymous
b- The program roadmap is an important input to the creation of the master schedule
c- The program master schedule shows when components should start and generate planned
deliverables
d- The program roadmap provides a high-level view of key milestones and decision points
120
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ63
During a formal phase-gate review, the program manager reports that all contingency reserves
have been used. What BEST option should be taken by the Governance board?
a- Immediately stop the program. Continuing is too risky!
b- Assess the risk level of the program and take a decision
c- Inject more money into the program. Any program should run with a contingency reserve
d- Do nothing because management reserve exists
121
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ68
What BEST defines the total cost of ownership of a program?
a- Development costs, implementation costs, direct costs, and indirect costs
b- Development costs, implementation costs, transition costs, and procurement costs
c- Development costs, implementation costs, transition costs, and sustainment costs
d- Implementation costs, transition costs, and overhead costs
122
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
At program closure time, lessons learned need to be archived. Lessons learned should be stored in
the:
a- PWBS
b- PMIS
c-OBS
d- LOL
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ78
Your program is progressing well but is on a very tight schedule. Identified risks at program and
component levels are well under control. The PMO is extremely efficient in supporting the overall
program. A new regulation just came out which may severely impact your program.
What is the BEST scenario to handle this new situation?
a- Send a note to all component managers telling them to immediately update their components'
risk registers with the new risk
b- Do not tell anything to your component managers who are extremely busy, and ask your PMO to
handle the new risk
c- Do not tell anything to your component managers who are extremely busy, and handle the new
risk yourself
d- Call a meeting with the PMO and your component managers. Explain the new situation
124
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
The success of a program is measured:
a - By how the organization is able to realize benefits from the program outcomes
b - By how the organization is able to satisfy the customer
c - By the results of the Earned Value method
d - Against the baseline
125
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ86
You are managing a program which is composed of four component projects. Projects are
producing their deliverables, but in order to create planned benefits, it is becoming evident that
another project needs to be initiated in order to integrate efforts of other projects. Time is critical.
What should be your immediate action?
a- Initiate a new project as soon as possible. Time is critical
b- Identify and document the activities needed to support the initiation of the new project, then
start the project
c- Identify and document the activities needed to support the initiation of the new project, then
present them to the Governance board for approval
d- Identify and document the activities needed to support the initiation of the new project, present
them to the program team for approval, and start the new project
126
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ90
You are managing program XYZ which has three component projects, A, B, and C. Projects A and B
have the same supplier. Project A has identified a major risk with this supplier but project B does not
have this risk. Project A manager is unable to resolve the risk which is becoming critical. You are well
aware of the problem. What is your BEST attitude with regard to this situation?
a- Do nothing as it is a project level risk
b- Ask project manager B to work with project manager A in order to resolve the risk
c- Handle the risk at your level
d- Escalate the risk to the program sponsor
127
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ94
Program X is due to provide outcomes and benefits for a customer. Program X is composed of
projects A, B, and C. You are the program manager and you are developing the communication
management plan. You are wondering who should and who should not communicate with the
customer?
a- Everyone on the program should be able to communicate with the customer
b- Before deciding who should communicate with the customer, you need to think about what
information needs to be communicated
c- Only managers should communicate with the customer
d- The program sponsor should be the only person communicating with the customer
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ99
Objective of the Program resource requirements estimate activity is to:
a- Provide a first estimate of resources needed for the program and planned components
b- Provide a first estimate of resources for the program only
c- Provide a first estimate of resources for the component projects only
d- Develop the resource management plan for the program
129
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ103
You are managing the program PMO which is in charge of transitioning the benefits to another
organization.
You also have defined a training plan which has been accepted by all. You contact the manager
of this organization and you find out that she is not ready to accept the benefits at this moment
because her organization has not completed training activities.
What should be your IMMEDIATE action?
a- Revisit the training content with her
b- Inform the program manager
c- Accept to delay transitioning the benefits until this organization is fully trained
d- Do nothing
130
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ107
A benefit can be transitioned to operations ONLY when:
a- All benefits of the program are ready to be transitioned
b- The formal work of all contributing program components to the program has ended
c- The program is not closed
d- All acceptance criteria of this benefit are met so that it contributes to the overall achievement of
the collective set of benefits
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ112
With the help of the PMO manager, you are creating the program schedule of your program which
is composed of three projects.
Project A manager prefers to use the critical path method, Project B manager prefers to use three-
point estimates, and Project C manager prefers to use Monte Carlo analysis. Project A is the most
critical project.
WHAT should be your action regarding scheduling tools?
a- Let Project managers use their preferred scheduling tool. No problem!
b- Impose the critical path method for all because Project A is most critical
c- Impose the Monte Carlo analysis because you are an expert in this technique
d- Ask the PMO to standardize the scheduling tools for the three projects
132
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
What is WRONG regarding Program Quality Assurance and Quality Control?
a- Program Quality Assurance does not include the analysis of the Quality Control results of program
components
b- Program Quality Control activity ensures that quality plans are implemented at project and
subsidiary program levels
c- Program Quality Control involves the monitoring of specific components or program deliverables
to determine if they meet quality requirements
d- Program Quality Assurance focuses on cross-program and intercomponent quality relationships
133
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ121
Communication requirements specific to particular stakeholders should be included in the:
a- Stakeholder register
b- Information management plan
c- Stakeholder engagement plan
d- Communications management plan
134
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ126
What BEST defines the activity called Program information archiving and transition?
a- Collection and distribution of program records
b- Distribution and archiving of records and documentation from components
c- Collection and archiving of records and documentation only from the program
d- Collection and archiving of records and documentation from the program and its components
135
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ131
You are currently identifying the key performance indicators (KPIs) for the expected benefits of your
program. What is the MAIN objective of the KPIs?
a- Monitor benefits sustainment
b- Measure customer satisfaction
c- Measure sponsor satisfaction
d- Monitor the delivery of benefits
136
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ135
Program strategy alignment is a performance domain is supported with inputs from environmental
assessments and a program risk management strategy.
What is NOT included in a risk management strategy?
a- Program risk thresholds
b- Initial program risk assessment
c- High-level program risk response strategy
d- List of most important risks
137
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ139
Program Manager X is currently evaluating the need for resources in her development program. It is
obvious that the planned allocation of resources is not sufficient. She knows that the program
budget is very tight.
What is the BEST option for her?
a- Subcontract one the component development projects
b- Talk to the program sponsor for advice
c- Talk to the portfolio manager and see if he can reallocate resources to her program
d- Cancel one of the component development projects and reallocate resources internally to her
program
138
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ143
What BEST characterizes the program charter?
a- It is prepared by the program management office (PMO) as an answer to the program business
case
b- It provides the program manager with the authority to apply organizational resources to program
activities
c- It is issued by the portfolio manager to set strategic goals to the program
d- It is elaborated by the program team just before the definition phase
139
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ148
Your program spans over several countries, with different cultures and different languages. Most
team members do not speak English which is your mother language. You are developing the
program communications plan for your program, and you wonder how to deal with this international
situation.
WHAT should you mention in the program communications management plan?
a- All communications will be done in English, because English is the most popular language over
the planet
b- All documents will be translated into country languages before diffusion
c- The communications language will first be discussed with country managers before
implementation
d- The communication language will be agreed upon by all stakeholders before implementation
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ153
During program closure, the program manager creates a final report.
What is the BEST answer with respect to the final report content?
a- Final lessons learned
b- Program’s performance assessment
c- Observations from team members
d- All of the above
141
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ157
Transitioning and sustaining activities are two complementary notions.
What is a WRONG statement about them?
a- Transitioned benefits will provide value to the receiving organization
b- Sustainment activities will help the receiving organization to ensure continued realization of the
benefits
c- Sustainment related activities are never part of a WBS
d- A sustainment plan should be developed by the program manager prior to program closure
142
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ161
Which of the following is under the responsibility of the program manager?
a- Manage the component projects
b- Interact with project and other program managers
c- Define the Company strategy
d- Manage the portfolio
143
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ166
Program changes can be classified in various categories. MOST OFTEN changes are:
a- Internal to the program
b- External to the program
c- Customer initiated
d- Both internal and external to the program
144
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ170
A Program Management Office (PMO) is:
a- A management structure
b- A governance structure
c- A supporting structure
d- An executive structure
145
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
170 Tutorial Questions - Answers
Please find below the answers to the tutorial questions.
Because there is no tangible threshold for this assessment, our recommendation is to take this
practice test until you achieve a result of 80%.
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ14
a- The standard, section 3.1
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ3Q
c- The PMBOK® Guide, section 9.1.3.1 (work to be performed)
148
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ45
b- The standard, section 8.1.2.3
149
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ61
b- The standard, section 8.3.1
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ77
d- The standard, section 6.2.2
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ93
d- The PMBOK® Guide, section 1.2.6.4
152
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ108
c- The standard, section 8.1.2.6
153
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ124
a- The standard, section 7.1.1
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ140
d- The standard, section 4.3
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Tutorial Question TQ156
a- The PMBOK® Guide, section 12
156
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
170 Practice Questions
Guidelines to be prepared for the PgMP® certification
This practice test intends to put the PgMP® candidate in conditions as close as possible to those in
the actual PgMP® exam. You have 4 hours maximum to complete all the questions.
While doing this practice test please note each answer on a separate blank sheet.
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ4
Your company is a major player in the field of telecommunications. Your company has embarked
on a major reorganization, and has decided to manage this initiative as a program. The program is
structured with three project managers and a PMO with four experts. The program is well underway,
but for some reason, the program manager has left the company. Because of your experience in
similar programs in the past, management has selected you as the new program manager. You will
start working Monday morning to take over the program. You have a lot of experience in the field of
telecommunications and in managing restructuring programs, but you lack a lot of information
about this specific program. In order to start properly, you first want to meet the most appropriate
person or entity. What is the IMMEDIATE action you should take?
a- Meet the PMO manager. After all, the PMO has a key role in the management of the program
b- Meet the Customer. After all, they are the best positioned to tell you what they expect from the
program
c- Meet telecommunication experts. After all, you are also an expert in telecommunications and
you will understand one another
d- Meet the program sponsor. After all, they champion the program initiative
158
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ6
Your company is a major player in the field of telecommunications. Your company has embarked
on a major reorganization, and has decided to manage this initiative as a program. The program is
structured with three project managers and a PMO with four experts. The program is well underway,
but for some reason, the program manager has left the company. Because of your experience in
similar programs in the past, management has selected you as the new program manager. You will
start working Monday morning to take over the program. You have a lot of experience in the field of
telecommunications and in managing restructuring programs, but you lack much information about
this specific program. At this moment, you only want to understand what the planned benefits of the
program are, regardless of when they may occur. Which DOCUMENT should you read in order to
answer that question?
a-The benefits management plan
b- The program initiative
c- The benefits register
d- The benefits log
159
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ9
You are a program manager within a humanitarian organization. This program targets to expand its
activities to new geographical regions. One of your project managers made the suggestion of
including a local small airline company in the program to optimize freight in his sub region. This
initiative could result in adding one more project to the existing program. The governance board
rejected initiating the new project. What is the MOST probable cause of the board’s refusal?
a- One of the key sponsors was not consulted previously
b- There are already too many projects in your program
c- The outcomes of this project were not sufficiently validated with respect to the organizational
strategy
d- You did not sufficiently argue that this new project coherently impacts the architecture of the
program
160
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ12
Your program is made up of six projects: A B, C, X, Y, Z. Project Y is the most important, project X
delivers essential outcomes to project Y while project Z is of secondary importance. You have been
recently asked by your governance board to reduce your overall budget. You propose to group
projects A, B and C in one single project in order to reduce your infrastructure costs, making project
leader A take over the responsibility of project leaders B and C. Several board members disagree.
What is the IMMEDIATE action you should take?
a- Make sure that project leaders B and C are redeployed within the organization
b- Update the business case
c- Demonstrate that projects A, B and C have strong interdependencies
d- Assess to what extent merging projects A, B and C will impact upon the three remaining projects
X, Y and Z.
161
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ16
Your program is made up of six projects: A, B, C, X, Y, Z. Project Y is the most important, project X
delivers essential outcomes to project Y while project Z is of secondary importance. There is a flu
epidemic in project team X and the project leader announces that the next deliverables will be
delayed by 2 weeks. These deliverables are part of outcome 1234 which is a major interim outcome
at program level. A gate review to authorize delivery to customer sign-off is scheduled within one
week. What is the IMMEDIATE action you should take?
a- Organize an extraordinary board meeting to announce this delay
b- Assess the impact of this delay on outcome 1234 against go/no-go decision criteria you already
have in place with your PMO
c- Announce a delay at the next board meeting
d- Ask project manager X to issue a change request
162
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ18
Your program has performed very well and all benefits are delivered. It delivered an important IT
component for the marketplace. You are preparing for the closure of the program with the program
team, as all outcomes have been signed off by the customer. However, in one of your customer’s
business units, a bug is reported that may affect the yearly back up process. It is agreed that release
maintenance is done every 3 months. Your program close out meeting is in one week. According to
the following options, what will be the MOST appropriate way to handle this situation?
a- You delay the closure until the bug is fixed
b- You keep the closure date as it is, report the bug to operations for the next release, and ask one
of the remaining experts to document a possible solution before the closure date
c- You keep the closure date as it is but negotiate with the functional managers that the team in
charge of correcting the bug will not be released until the bug is fixed
d- You delay the closure until the bug is fixed. You create a new release, and you install and perform
non regression tests in the business unit
163
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ21
Programs are undertaken to contribute to a company's strategic objectives, and to generate
benefits. In many situations, a well-managed program helps to obtain benefits and a level of control
that are not available when projects are managed individually. Assume you manage a program for
which benefits have been identified and recorded in the benefits register. Now it is time to develop
the benefits management plan which will guide benefits realization. Which answer is TRUE regarding
the benefits management plan?
a- The benefits management plan is developed by the sponsor because they are ultimately
accountable for enabling the program success
b- The benefits management plan ensures that all the planned program outcomes are achieved
before the close of the program
c- The benefits management plan ensures that all the planned benefits are realized before the
program finishes
d- The benefits management plan identifies which processes and procedures should be used to
manage the program
164
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ24
You are managing a program that will deliver a series of home automation sensors for the consumer
market. Your organization is a worldwide leader in the consumer industry, has R&D in several
countries, marketing and sales in 52 countries and subcontracts their manufacturing. This program is
in charge of adapting the existing product line for customers in emerging and promising markets on
another continent. You are now in the formulation subphase, and you are developing the program
charter. What is the IMMEDIATE action you should take?
a- Develop a general scope statement which will contain the program vision, local influences and
variables in order to facilitate global planning
b- Write a general scope statement to create the PWBS, in order to determine and plan program
deliverables
c- Assess to which extent the PMIS already in place in your organization needs to be adapted to
local constraints such as: cost and organization’s labor constraints, certification processes, R&D
funding
d- Create a detailed scope statement which will contain the budget objectives, local influences
and variables in order to facilitate global planning
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ27
As a program manager in your company, you know that benefits management is a key ingredient
of your program success. Even before your program was initiated, a group of executives from your
company met several times in order to identify the key benefits that your program could produce.
Following those discussions, a list of identified benefits was established and recorded in a program
document. During the life of the program, you will use this preliminary list of expected benefits as the
basis for benefits management. During the program life cycle, what is the FIRST document that
contains this preliminary list of expected benefits?
a- The program charter
b- The program roadmap
c- The program business case
d- The benefits management plan
166
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ30
On this diagram, what are the critical path, critical path length, shortest path and shortest path
length, respectively?
a- ABCG, 53, AHG, 40
b- ADEFG, 54, AHG, 39
c- ADEFG, 55, AHG, 40
d- ABCG, 54, AHG, 39
167
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ33
Program planning activities mainly occur during the program definition phase. But actually, planning
activities occur during each phase of the program life cycle; for instance each phase must be
correctly planned before being executed. Also, planning (or re-planning) activities should be
performed at key milestones of the program, such as gate reviews. Because of the extended
duration of the majority of programs, there are additional milestones where plans should be revisited
and updated to ensure ongoing usefulness. In which situation is it MANDATORY to update the
program plans?
a- When the Customer requests a major extension to the program scope
b- When the program is over three months late
c- When a program schedule change request has been accepted
d- When the measured quality of the program deliverables is below standard
168
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ36
You are in charge of a program for removing the waste produced in summer by the visitors to your
city. The overall cost is 1M€. Last year you had to remove the waste from June 1st through August
31st. However, the tourist office extrapolates from current bookings that visitors will only come from
July 1st through July 30th, with a 95% probability. What is the expected schedule variance?
a-1 month
b- 2 months
c- 3 months
d- Not enough information to answer
169
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ39
You are managing a program that has about thirty stakeholders, six of whom are identified as 'key
stakeholders' because you need their deep involvement for the success of the program. You are
developing the stakeholder engagement plan, and you want to make sure that key stakeholders
remain engaged during the whole length of the program. In order to avoid a potential crisis, you
want to be able to measure their attendance at meetings, measure participation trends and
identify root causes of non-participation. What is the BEST action you should take?
a- Develop attendance lists for the meetings, ask that they be filled in by those present at each
meeting, and create attendance trend curves
b- Develop the stakeholder register which will contain the list of key stakeholders
c- Develop a stakeholder map which will visually represent the stakeholders’ interactions
d- Develop stakeholder metrics which will allow the tracking of stakeholders’ attendance and
involvement in the program
170
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ42
You are currently in the definition phase of program ABCD. When establishing the benefits
management plan, interdependencies between the benefits have been thoroughly analyzed and it
is now clear that all benefits will be realized before program closure. However, a key external
stakeholder who may be positively impacted by the program is not really convinced that this will be
the case. According to the following options, what will be the MOST appropriate way to handle this
situation?
a- Explain the plan again; everything is nicely scheduled and interdependent, so do not worry
b- Go back to your program team and establish metrics that satisfy this external stakeholder
c- Go back to your program team and establish metrics that satisfy all stakeholders
d- You understand that the benefits may be not as positive as this stakeholder would like. You thus
decide to enhance the quality of the intended benefits
171
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ44
You are managing program X which is composed of four projects: A, B, C and D. From the beginning
of your program, you have been extremely sensitive to the fact that program outcomes must
generate benefits which are in line with the strategic objectives of your company. One KPI you have
defined for the program relates to the component project deliverables which must be produced on
time, and with the required quality level. At one program checkpoint, project manager C reports a
potential delay expected on a key project deliverable. If the delay occurs, it will impact one major
program objective. Project manager C says that the expected delay of the deliverable is due to the
potential late delivery of a piece of test equipment from an outside vendor. After discussing with
project manager C, you find out that no real commitment was ever given from the vendor on the
delivery date of this test equipment. What is the BEST action for you to take?
a- Ask project manager C to update the contract with the vendor with an urgent delivery date
b- Ask project manager C to immediately contact the vendor and explain to him the critical nature
of the situation
c- Pick up the phone yourself and give the order to the vendor to immediately provide the test
equipment
d- Inform the steering committee about the situation
172
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ47
The local authorities have decided to build a highway between two large cities. Several bridges also
need to be built. A business case has demonstrated the pertinence of the program. A large
construction program is launched and is forecast to last approximately four years. You have been
selected as its sponsor. During the definition phase of the program, and with the help of the local
authorities, you need to define its financial framework. What are the MOST COMMON funding
models used to create the financial framework?
a- Funded entirely within a single organization, funded within multiple organizations, funded and
managed entirely from outside the parent organization, and supported only by external sources of
funding
b- Managed within a single organization but funded separately, funded and managed entirely from
an inside organization, and supported with only internal sources of funding
c- Funded entirely within a single organization, managed within a single organization but funded
separately, funded and managed entirely from outside the parent organization, and supported with
internal and external sources of funding
d- Managed within a single organization but funded separately, funded and managed entirely from
outside the parent organization, and not supported with internal and external sources of funding
173
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ49
174
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ51
On this diagram, if D duration becomes 15, what are the critical path, critical path length, shortest
path, and float on the shortest path, respectively?
a- ABCG, 53, AHG, 14
b- ADEFG, 54, AHG, 14
c- ADEFG, 55, AHG, 13
d- ABCG, 54, AHG, 13
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ54
You are preparing a program charged with developing a set of new IT technologies that promises to
be a great business development opportunity within your organization. This program is located in the
corporate division that groups together a number of other corporate functions including: finance,
human resources, the strategic board, and corporate marketing. The intention is to spread the
benefits of your program over the entire organization that consists of 5 business divisions operating in
more than 50 countries and split into 3 geographical zones. You have created the high level
roadmap but failed to obtain formal approval from your executive sponsor. What is the MOST LIKELY
reason that the approval was denied?
a- The milestones and high level costs identified all major road blocks but did not contain sufficient
details per country
b- You did not identify integration needs and scenarios to make sure that the benefits will bring
sustained business development for the 5 business divisions and the 3 geographical zones which
represent the majority of the countries
c- You did not identify integration needs and scenarios to make sure that the benefits will bring
sustained business development for the 50 countries
d- You did not identify the skills and resources needed by each of the 50 countries
176
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ56
You are preparing a program in charge of developing a set of new IT technologies that promises to
be a great business development opportunity within your organization. This program is located in the
corporate division that groups together a number of other corporate functions including: finance,
human resources, the strategic board, and corporate marketing. The intention is to spread the
benefits of your program over the entire organization that consists of 5 business divisions operating in
more than 50 countries and split into 3 geographical zones. You have prepared an initial charter
that proposes high level costs, milestones and an overall schedule as well as the expected benefits.
What is the NEXT action you should take?
a- Propose this charter to the governance board in order to receive formal authorization to further
proceed with program preparation
b- Introduce this charter also to the stakeholders of lesser importance so that all really come on
board to join the program
c- Get the governance board to come together and organize a kick off meeting
d- Develop a detailed business case per country
177
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ59
Your organization operates energy plants in ten countries. You are leading the program in charge of
refurbishing the energy-producing plants with the new ABCXYZ technology. This will address the local
people’s important concerns, and make your organization more socially acceptable; but it will
reduce the overall business profits. Some board members have told you that this profit cut is not
acceptable. What should you say in your reply to them?
a- The program is a careful balance of tangible financial results and non-financial benefits.
Jeopardizing this balance may break the whole business in the long term
b- I will minimize the introduction of ABCXYZ technology in order to increase profit and I will try to
convince the local population
c- I will implement the new ABCXYZ technology to all ten countries because all business, however
small, is good for our company
d-1 will launch a project in order to assess the business increase by expanding ABCXYZ technology in
five new countries
178
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ62
The program you are managing spans three years. Phase-gate reviews are recommended to assist
program control and management as well as to facilitate governance. Phase-gate review dates
have been defined and you are aware that you need to show evidence that the program can
proceed to the next phase. Your program just finished the program definition phase. Phase-gate
reviews provide an opportunity to assess the program with respect to a number of strategic and
quality related criteria. During the gate review, the steering committee will look at some key criteria
in order to agree or not to proceed to the next phase. What is NOT mandatory when exiting this
gate?
a- Component projects are initiated in order to meet program objectives
b- The program governance structure is established
c- Expected benefits are in line with the program business case
d- The risk level remains acceptable to the organization
179
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ65
Any program needs to have an appropriate governance structure in order to perform correctly. The
program governance structure includes people such as the program manager, the sponsor, the
PMO, etc. who will be involved in the various phases of the program using policies, procedures,
standards that are derived from company assets. The governance plan should provide all the
necessary information related to the execution of the governance process. Once defined, this plan
is used during the program life cycle. Which is the BEST list of governance plan ingredients?
a- Definitions of roles and responsibilities, structure and composition of the program governance
board, stakeholder engagement plan, component initiation criteria and planned phase-gate
reviews
b- Definitions of roles and responsibilities, high level governance plan and meeting schedules,
financial model, and periodic “health checks”
c- Definitions of roles and responsibilities, schedule of planned governance meetings such as phase
gate reviews, program health checks and required audits
d- Definitions of roles and responsibilities, PWBS, structure and composition of the program
governance board, governance goals summary, planned phase-gate reviews
180
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ68
Environmental Analysis may be used to assess the validity of the business case and program
management plan. What is a CORRECT list of Environmental Analyses which may be performed by
the program manager?
a- Comparative advantage analysis, feasibility studies, and PMIS
b- Comparative advantage analysis, feasibility studies, mandate and SWOT analysis
c- Feasibility studies, SWOT analysis, assumptions analysis, and historical information analysis
d- Feasibility studies, SWOT analysis, Critical chain, and historical information analysis
181
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ72
You are preparing for an important governance board meeting. This meeting will review the
performance of the program so far. A board member has informed you that an important
stakeholder XYZ is very satisfied whereas another board member reports that another important
stakeholder ABC is not satisfied at all. What is the IMMEDIATE action you should take?
a- Ask XYZ to meet ABC and share why she is so happy. You expect that ABC will change his mind
when listening to XYZ
b- Meet ABC and explain why XYZ is happy
c- Meet ABC, listen carefully to his concerns, and put an agenda item at the next board meeting to
introduce consistent mitigation of these concerns
d- Meet ABC, listen carefully to his concerns, and provide some answers directly to him
182
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ75
Your program deals with many vendors and most of them will be common to several of your
program’s constituent projects. You have consequently decided to manage procurement at the
program level rather than at project level. You have assigned one procurement expert in your PMO
to manage all procurements on your behalf. This PMO expert has developed the procurement
management plan, and is now conducting procurements. As of today, not all vendors have been
selected, and no contract has been signed with any of them. When conducting procurements, the
PMO expert will generate several outputs. Which is the CORRECT list of these outputs?
a- Performance/earned value reports, request for quote (RFQ), awarded contracts, program
procurement plan, and quality checklists
b- Performance/earned value reports, invitation for bid (IFB), program budget updates, request for
roadmap and program procurement standards
c- Proposal evaluation criteria, signed agreements, agreements administration plan, and request for
proposal (RFPs)
d- Request for quote (RFQ), request for proposal (RFP), awarded contracts, and program roadmap
updates
183
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ77
You are managing a software development program which has four projects: A, B, C and D. Projects
A, B and C are in charge of developing various software modules and project D mainly performs test
activities for the other three projects. You have regular checkpoint meetings with the four project
managers, both on an individual basis, and during group sessions. During one checkpoint meeting,
project manager D reports a major risk that appeared recently on her project. One of her suppliers
may not be able to deliver the test equipment on time; it may be two months later than originally
planned. If this happens, it will jeopardize test sessions that are planned to start in one week from
now and may delay the creation of the planned benefit by two months. What is the BEST way to
handle the situation?
a- Take corrective action and modify the benefits management plan to take into account the two
months delay. Plans must reflect reality
b- Ask project manager D to immediately contact the supplier and work on an alternate solution if
possible. You should also inform the steering committee about the two months delay in the benefit
realization
c- Immediately inform the steering committee about the two months delay. They are most interested
in benefit realization
d- Ask project manager D to immediately contact the supplier and work on an alternative solution if
possible. You should also look at the plan to see what will be the consequence of the delay on the
benefit realization
184
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ79
You are managing a software development program which has four projects: A, B, C and D. Projects
A, B and C are in charge of developing various software modules and project D mainly performs test
activities for the other three projects. You have regular checkpoint meetings with the four project
managers and with the PMO. The projects are progressing with difficulty. Project execution is
complex, more complex than anticipated. Project members have little experience in their jobs and
project managers spend a lot of time helping and counselling them. Two project managers report
the fact that some of their members are showing a lack of motivation. Project managers ask you for
recommendations about what to do to help project team members perform better. The program
PMO is experienced in software development. What is the BEST option for you to take?
a- Ask the PMO to develop a training course on software programming development for the project
team members
b- Move PMO members to project teams in order to speed up software development
c- Hire an outside consultant to coach, train or mentor according to needs
d- Ask the PMO to perform an assessment of the situation and to recommend an action plan
185
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ82
The program you are managing is in charge of designing, building and delivering a new space
rocket to an important government agency. You have a change control board (CCB) at the
program level to assess change requests on a number of criteria: scope, quality, schedule, cost,
contracts, risks, etc. Because the program is quite large, changes that impact earned value less
than 5% are processed at project level, this is an example of:
a- Resource leveling
b- Smoothing
c- Tolerance
d- Delegation of governance
186
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ85
The program architecture defines the relationships among its components, related to both
operational and project activities. The program manager is responsible for managing all the
interfaces between these components. During the life of the program, new components may be
brought into the program and some may be removed from the program. In order to communicate
interface changes to stakeholders, guidelines should be developed. In which of the following
situations is it BEST to communicate a program interface change to stakeholders?
a- A change request is rejected and the program architecture does not change
b- A change request is accepted at the component level but has no impact on other components
c- A new PMO member has been brought into the group
d- A scope change in one component has an impact on the program architecture
187
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ89
You are the newly appointed program manager of company XYZ which specialises in global
humanitarian aid. The board members have expressed dissatisfaction with the program
performance during several board meetings. They state that it is difficult to see from the information
provided whether the program needs correction or not. As newly appointed program manager,
what is the IMMEDIATE action you should take?
a- Meet individually with each project manager to analyze their performance reports in order to
formalize requests for corrective actions
b- Update the business case
c- Travel to meet the three most important regional CEOs
d- Assess the completeness of the information provided in the reports with respect to the concerns
expressed by the board, and share a targeted update of the program report with all project
managers
188
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ92
You are planning the activities tor your program. The scope of the program is well defined; you
understand the program requirements and the program architecture are established. You now want
to decompose the work to be performed in the program and create the program work breakdown
structure (PWBS). You ask your project managers to do the same for their projects and create their
WBS. You plan to use the project's WBS as an input to creating the program WBS. You have drafted
a program WBS on your own and you also have received the projects' WBS from your project
managers. What is the BEST option now to create the PWBS?
a- Incorporate the first or first two levels of the projects' WBS into the program WBS
b- Include each entire project’s WBS into the program WBS
c- Select the projects' work packages and include them into the program WBS
d- Ignore the projects' WBS because they only relate to the projects and not to the program
189
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ95
You are planning the activities for a complex program composed of three projects and some
recurring activities. You are developing the program management plan which integrates the
program's subsidiary plans such as scope management, schedule management, etc. The program
management plan will be the primary input to program execution. You are now developing the
program quality management plan which will also be included in the program management plan.
You are aware that most quality planning activities occur at each component level. What is the
MOST appropriate list of elements you should include in the program quality management plan?
a- Program quality standards, program quality policy, quality metrics, quality assurance and control
specifications, and quality control activities required at component level
b- Program quality standards, program quality policy, quality checklists, and roles and responsibilities
for quality related activities at component level
c- Program quality standards, program quality policy, and program quality estimates of costs
d- Component quality plans, program quality standards, and program quality policy
190
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ99
You are managing a program composed of three projects: A, B and C. You want to evaluate the
performance of your program using earned value parameters collected from each individual
project. As of today, project A has a CPI of .8, and AC = 100. Project B has a SPI = 1.5 and EV = 200.
For project C, cost variance (CV) = 50 and AC = 150. Which option is TRUE about projects A, B and
C?
a- Project A is under budget
b- Project A is over budget and project B is late
c- Project B is ahead of schedule and project C is under budget
d- Project A is over budget and project C is ahead of schedule
191
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ101
Many stakeholders participated in your last program communication meeting. Many of them will sell
products and services provided by your program, in their respective geographical areas.
Performance reports have been introduced and are shown to be satisfactory, proving that the
delivery of these results will be done on time and with a good compliance to overall expectations.
However, some sellers are still not fully convinced by this information. What did you overlook?
a- You did not spend enough money on the catering, this explains the problems you had during
lunch on the first day
b- You did not sufficiently explain how the sellers will give the information to their teams
c- You did not sufficiently explain how products and services from you program are related to your
internal organization of projects
d- Your program delivers the same products and services to all sellers without any mention of
customization. They come from different regions and your program outcomes are too generic to
really meet their specific needs
192
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ103
Many stakeholders participated in your last program communication meeting. Many of them will sell
products and services provided by your program, in their respective geographical areas.
Performance reports have been introduced and are shown to be satisfactory, proving that the
delivery of these results will be done on time and with good compliance to overall expectations.
However, some sellers are still not fully convinced by this information. What is the IMMEDIATE action
you should take?
a- Take some senior executives from the governance board to one side and discuss with them, one
by one
b- Ask them for their own business plan for their geographical region and convince them that they
will increase their margins with your program
c- Gather the skeptical sellers in a separate meeting to define a specific transition plan. Explain that,
with your program, you will ensure that the outcomes will be transitioned to them, that the training
plans are adequate to their staff and that switching from the previous state will be evident
d- Gather all the sellers to review the transition plan. Explain that, with your program, you will ensure
that the outcomes will be transitioned to them, that the training plans are adequate to their staff
and that switching from the previous state will be evident
193
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ105
You have been recently appointed to a new program as program manager. This program has
received formal acceptance from the board and is now in the definition life cycle phase. One of
the key tasks is to create the scope statement of the program in order to have a high level view of
the business impact and to identify essential aspects that must be accomplished by the program.
What are the KEY topics you have to address when creating the scope statement?
a- Scope and limitations, program boundaries, assumptions and constraints, and acceptance
criteria
b- Scope, PWBS, organizational needs and requirements, assumptions and constraints
c- PWBS, organizational needs and requirements, charter of each component, assumptions and
constraints
d- Organizational needs and requirements, program charter, scope, assumptions and constraints
194
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ109
Your company has decided to regroup four existing projects and manage them as a program. You
have just been assigned as the program manager. For historical reasons, each existing project has its
own Project Management Information System (PMIS). Project managers have a lot of experience in
their domain of responsibility, and their PMIS have an excellent reputation in the company. You
wonder if you should establish a dedicated Program Management Information System (PMIS).
What is the BEST option to answer this question?
a- Your project managers' PMIS have an excellent reputation. So why bother to establish a PMIS at
program level? Use the existing PMIS “as is”
b- Your program will use a specific set of processes, tools, procedures, data, etc., which are different
from the projects' ones. As a result you should establish a dedicated PMIS at program level
c- Ask your PMO to decide since they will eventually be the only entity to use the PMIS at program
level
d- Ask the program sponsor since he provides the resources for the program
195
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ111
You have been identified as the potential program manager of a key program for your company.
The program is in the definition phase, a high-level business case has been built, and you know that
the governance board has many concerns about the level of risk for the program. During a recent
board meeting, the board members performed a SWOT analysis, and several risks were identified as
a result. Most of these risks originate from the external environment, such as strong competition,
potential impacts of the economic crisis on the program results, and only a few risks were identified
as internal to the organization. Because the program may bring many benefits to the company, at
the conclusion of the board meeting, the decision has been made to go ahead and start the next
program phase. What is the IMMEDIATE action you should take?
a- Ignore the majority of the risks identified by the board because most of the risks have been
identified as related to 'outside the company' and not under your control
b- Only record the top five risks identified during the board meeting
c- Record all the risks identified during the board meeting in the risk register. They will then be
reviewed for further analysis
d- Record all the risks identified during the board meeting and be ready to pass all of them to your
project managers when they will be on board
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ114
You are in charge of a program which has been running for three years. This program consists of six
projects focused on technological subsystems that are then subsequently integrated by a seventh
project, namely the “integration project,” to deliver a full range of IT software solutions for major
customers of your organization. The program is fueled by internal funds which are submitted for
board approval. This process is rather stable now as the financial effort is being tracked, monitored,
and controlled according to the program's expenditure. What is the MOST recommended action for
successful monitoring and control of the program financials?
a- Identify factors that create changes to the program management plan
b- Monitor contract expenditures to ensure that funds are made available before the contract starts
c- Communicate changes in the financial baseline to the governance groups and to the auditors
d- Manage the expenditures of the program architecture to ensure costs are within expected levels
197
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ117
Adequate stakeholder engagement is a key element of program management and is essential tor
the success of the program. The program manager has the obligation to properly identify the
stakeholders, manage their expectations, and make sure they remain engaged throughout the
program life cycle. The PMI® Standard for Program Management details three activities which
address the stakeholder engagement domain. What is the CORRECT list of activities recommended
by the standard?
a- Program stakeholder engagement, program stakeholder engagement planning, and manage
program stakeholders
b- Select program stakeholders, program stakeholder engagement, and program stakeholder
engagement planning,
c- Select program stakeholders, manage program stakeholder expectations, and program
stakeholder identification
d- Program stakeholder engagement, program stakeholder engagement planning, and program
stakeholder identification
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ120
In order to optimize various project results and generate benefits, your company has decided to
launch a program with three existing projects: A, B and C. You have been chosen as the program
manager and you are in the process of identifying the key stakeholders of your program. Each
component project already has its own list of key stakeholders recorded in separate project
stakeholder registers. Among the three component projects, project A is the most important for the
program’s success, followed by project B, and finally project C has the lowest priority. You want to
focus on the list of key stakeholders at program level. What is the MOST appropriate way to handle
the list of key stakeholders who may impact the program?
a- Identify and record key stakeholders who are unique at program level
b- Aggregate the list of key stakeholders identified in the three component projects A, B and C
c- Only focus on project A stakeholder register, because project A is the most important component
project
d- Identify and record key stakeholders who are unique at program level and key stakeholders
identified in each project
199
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ122
The organization’s strategic plan is a key input to several portfolio management activities. What BEST
describes the content of a strategic plan?
a- A vision and a set of objectives, a description of the organizational structure and organization
areas, and an inventory of all existing components
b- A vision and a set of objectives, a description of the organizational structure and organization
areas, and a description of funding sources and funding constraints
c- A description of the organizational structure, and a description of funding constraints
d- A vision and a set of objectives, a description of the organizational structure and organization
areas, measurable goals and guidance, and allocation funds to different types of initiatives
200
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ125
You are the program manager of a key program for your company. The program has the go ahead
from the governance board and is in the program definition phase. Key stakeholders of the program
have been identified, and you know that because of internal politics, some of them may not be very
supportive. You have identified three key stakeholders from whom support is absolutely necessary for
the success of the program. You wonder what to do next in order to get their support. According to
the following options, what will be the MOST appropriate way to handle this situation?
a- You contact them individually, when possible you discuss face to face, you explain the
importance of the program and you tell them why their support is absolutely necessary
b- You send them an e-mail summarizing the importance of the program and what you expect from
them
c- You ask the program sponsor to handle this situation, because it is the sponsor’s responsibility to
obtain stakeholder buy-in
d- You develop stakeholder metrics which will help you to manage key stakeholders' participation in
the program meetings
201
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ128
You are planning the activities for a complex program composed of three projects: A, B and C. You
and your team have finished developing what you consider to be the initial version of the program
management plan which integrates the program's subsidiary plans. You now do a thorough check
of resource utilization per component project. It is evident that on some months, the resources of
projects A and B will be underutilized, and on other months, there will be a lack of resources on these
two projects. Project C has no resource utilization problems and project C is the most critical for the
program’s success. No project has started yet. You look for a way to improve project A and B's
resource utilization problems. What is the BEST way to handle this situation?
a- When projects A and B have resource utilization problems, you can immediately transfer
resources from project C to projects A and B. In a program, each project must contribute to overall
program success
b- Before looking at other alternatives, you should first try to apply resource leveling techniques on
projects A and B
c- Before looking at other alternatives, you should first try to apply resource dispatching techniques
on projects A and B
d- Before looking at other alternatives, you should first try to apply the Monte Carlo technique to
optimize resource utilization on projects A and B
202
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ130
You are managing a program with three component projects: A, B and C. Project B has created all
its planned deliverables and project B’s manager now formally reports that he has completed all his
project’s closing activities. Based on this report, you approve the closure of the project and you ask
project manager B to release all of his resources. You receive a phone call from the program
sponsor asking you to immediately stop releasing project B’s resources. What did you do WRONG?
a- You cannot decide all by yourself to close a component project. The component closure
decision is a decision taken by the program management team
b- You cannot decide all by yourself to close a component project. The component closure
decision must come from the PMO
c- You cannot decide all by yourself to close a component project. The component closure decision
must come from the governance board
d- You cannot decide all by yourself to close a component project. The component closure
decision must come from the customer
203
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ132
You are managing a program for a major IT company in charge of upgrading the system for the
identification of citizens at the borders of your country. This is under contract procurement from the
Public Administration of the Interior's Ministry of Affairs. You are now in a board meeting with all
parties, including your sponsor and the group of public officers representing the Administration’s
interests. Your program is rather complex and risky, spread over numerous projects that focus on
several kinds of IT expertise: database, sensors, border personnel training, etc. When reviewing the
lengthy risk updates, the Administration claims that several risks are not under control. It anticipates
delays and quality problems, arguing the fact that projects are too numerous and difficult to handle.
According to the following options, what will be the MOST appropriate way to handle this situation?
a- You acknowledge the concern and propose to concentrate on major risks; these risks will be
escalated at program level, and project level risks will not be mentioned at board level
b- You acknowledge the concern and agree that it is your job to master this complexity. You argue
that the Public Administration has chosen your IT company because of its excellent achievements in
the past and that there are no evident reasons why this should not be also the case for your
program
c- You acknowledge the concern and argue that you organized the program in specialized
technical teams for day-to-day efficiency reasons that will be demonstrated at the end of the
program
d- You acknowledge the concern and update the risk register. Risks are quite numerous but you
think it is the best way to really show that they are under control
204
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ134
You are managing a program for a major IT company in charge of upgrading the system for the
identification of citizens at the borders of your country. This is under contract procurement from the
Public Administration of the Interior's Ministry of Affairs. You are now in a board meeting with all
parties, including your sponsor and the group of public officers representing the Administration’s
interests. They all recognized the accomplishment of your team. This is the final sign off for all
outcomes of the program. The sign off went smoothly and the success was celebrated in due form
between some governance board members and the public officers who have daily contacts with
your team. When getting back to your company, you realize that the whole program team is
surprisingly reluctant to perform the remaining necessary day-to-day actions. What is the MOST
probable reason for that?
a- People are sad to leave the program
b- You neglected to give proper recognition of your team’s performance in front of the
Administration
c- The program team thinks that you should have formally invited them to the celebrations with the
Administration
d- People are tired
205
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ136
You are managing a program for a major IT company in charge of upgrading the system for the
identification of citizens at the borders of your country. This is under contract procurement from the
Public Administration of the Interior's Ministry of Affairs. You are now in a board meeting with all
parties, including your sponsor and the group of public officers representing the Administration’s
interests. Your program is rather complex and risky, spread over numerous projects that focus on
several kinds of IT expertise: database, sensors, border personnel training, etc. The Administration has
said that not all border teams will use the new system. What is the MOST probable reason for this?
a- It is a really challenging program that will provide a major transformation to the Administration. It is
so broad that the Administration members did not even understand all of the impacts. They will
understand later
b- You think that the program is complex and that this is a normal situation. After proper training and
real deployment, border teams will get familiar with it and adopt it
c- The program is in the executing phase and there is little time to consider details which will occur
later
d- The Administration has a negative opinion of the program. The transition plan is not clear enough
to ensure that all border teams will use the system
206
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ138
Your pharmaceutical company has decided to reorganize some of its business units, and has
decided to manage this major effort as a program. A business case has been developed and the
program is approved. Also, it has been decided that two existing projects will become components
of this program. You have been asked to develop the program charter and the steering committee
has approved it. What is the BEST definition of the program charter?
a- The program charter formally authorizes the program and it details all planned benefits, their
metrics and their realization plan
b- The program charter provides the program manager with the authority to apply resources to
program activities, and to start delivering benefits right away
c- The program charter formally authorizes the program and it provides a governance mechanism
with approval and reporting procedures
d- The program charter formally authorizes the program and it provides the program manager with
the authority to apply resources to program activities
207
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ141
Your program is a nationwide reorganization of a government based agency. It consists of
centralizing warehouse plants in bigger cities to cut expenditure costs such as gas and vehicles
loans. This program is now 2 years old and you demonstrated that this program is on track so far. It is
composed of six projects: A, B, C, X, Y, Z. Generally, one of the reasons for a program to work
satisfactorily is that the interdependencies between the program and its components are well
managed, which is apparently the case here. What BEST describes these interactions?
a- The interactions between your program and its components tend to be iterative and cyclical
b- The interactions between your program and its components are scheduled to happen only
before the governance board meetings
c- The interactions between your program and its components are strictly limited to when an alert is
escalated to you
d- The interactions between your program and its components are daily, informal and based on
confidence between people
208
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ144
You have developed a program management plan which has been reviewed and accepted by all
stakeholders of your program. You are currently in the executing part of the program, and you want
to make sure that your four project managers A, B, C and D execute according to the program
management plan. During a checkpoint meeting, you request that each project manager reports
on the progress of their project, to enable you to synthesize the data on the overall program
performance and communicate the result to stakeholders. You know that stakeholders are mainly
interested in knowing, on a monthly basis, what the projected end program cost will be compared
to the planned cost. In order to communicate this information to stakeholders, WHICH cost reporting
tool should be used by your project managers?
a- Bar charts in order to show how costs are distributed per project over time
b- Pie charts in order to show the distribution of the costs per project over time
c- Earned value reports to highlight EAC vs. BAC
d- Earned value reports to highlight CPI vs. SPI
a- Update the program charter in order to reflect his participation in the program. The program
charter defines all program stakeholders
b- Update the program Gantt chart to include the delivery schedule expected from this expert. The
schedule is key
c- Update the program stakeholder register and inform other stakeholders about the participation of
this new stakeholder
d- Do nothing because this stakeholder will report to you
209
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ146
The program you are managing is spread over 9 countries, includes 23 external companies and
generates more than 50 external communications a year. You organize an open event every year in
order to distribute the essential information on your program. The objective of this event is not only to
summarize and distribute all the available information but also to receive feedback from all parties
about the achieved and future expected benefits. The open event took place last week and you
discovered that several medium-level stakeholders expressed negative concerns about the
program. They claimed that they do not see how it will serve their interests and do not understand
why so much money is being spent on it. What is the MOST probable reason to make them think like
this?
a- The 50 external communications were not appropriate for communicating your results
b- The 50 external communications were not appropriate for communicating your results, but
because they are directly produced by the project teams, you have no other choice than to
distribute this information
c- They think that one event a year is not enough, you should organize an open event every 20
external communications
d- They believe that the information provided in the 50 external communications is too detailed. You
should arrange for the information on your program to be better synthesized and not wait for the
open event to distribute it. Then you should ask them for feedback
210
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ148
The program you are managing is spread over 9 countries, includes 23 external companies and
generates more than 50 external communications a year. You organize an open event every year in
order to distribute the essential information on your program. The objective of this event is not only to
summarize and distribute all the available information but also to receive feedback from all parties
about the achieved and future expected benefits. The open event took place last week and you
are facing strong opposition from the program team over-archiving all distributed information into
the PMIS. This PMIS is provided by the corporate IT support. What is the FIRST action you should take?
a- Ask them to stop everything now and urge them to archive files
b- Develop an understanding of why they are opposed to the corporate PMIS and use
management reserve to purchase another PMIS in order to archive files
c- Ask your PMO to specify and negotiate a PMIS change with corporate people to make it more
acceptable by all
d- Argue that this is the PMIS corporate tool, used by several other programs and there is no other
specific PMIS just for us
211
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ150
You are managing a program that is in charge of developing a new set of drills for oil exploration.
There are many constraints because these drills should operate in a large set of conditions: depth,
underground structure, temperature and location. You have organized this program by project
characteristics: one of them consists of the design and manufacturing of the drills, which is located
on your corporate premises, while several others test the drills in their respective regions, ranging from
polar to equatorial conditions. An important objective of the program is to minimize the overall
future operational costs of the drills for your organization. Among the following options, which one
does NOT characterize the need of having a program in such a case?
a- The coordination of the logistics needed for the transportation of the drills between the corporate
location and the overseas sites
b- The coordination of human resources among the test projects
c- The compliance of the drills to global quality standards
d- The existence of high technical risks in each of the different projects
212
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ152
You are managing a program that is in charge of developing a new set of drills for oil exploration.
There are many constraints because these drills should operate in a large set of conditions: depth,
underground structure, temperature and locations. You have organized this program by project
characteristics: one of them consists of the design and manufacturing of the drills, which is located
on your corporate premises, while several others test the drills in their respective regions, ranging from
polar to equatorial conditions. A prime objective of the program is to minimize the overall future
operational costs of the drills for your organization. However, you recently observed that the total
test costs rose significantly when a number of drills of the same model all broke at a depth between
2100 and 2550 meters. What is the IMMEDIATE action you should take?
a- Check that the local drilling processes are understood and applied by the staff on each
respective platform
b- Gather information on what specific conditions exist on each site
c- Request a detailed issue report from each test project manager
d- Organize a meeting with all test project managers
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ155
Congratulations! You have been selected as the program manager in charge of managing a large
program which includes five projects, and lots of stakeholders. This program is key for your company.
Several benefits are expected as a result of this program that should establish your company as a
leader in its field. You are now proceeding in the first phase of the program life cycle, the definition
phase. You know that you should develop the program roadmap before the next steering
committee meeting. You have a list of identified key benefits and also a high level schedule of their
planned dates. You are not sure about the difference between the benefits management plan and
the program roadmap. From the list of below options, what is the BEST answer?
a- There is no difference between the two. They both relate to the creation of program benefits
b- They are different: the benefits management plan describes when and how the benefits will be
created, and the program roadmap is more general and provides a high level view of the key
milestones and decision points of the program, including benefits realization
c- They are different: the benefits management plan describes when and how the benefits will be
created, and the program roadmap does not address at all the creation of the benefits
d- They are complementary: both are outputs from ‘Benefits and planning’ activities
214
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ158
You have developed the roadmap for your program in which you have indicated the key
milestones to initiate and close components. Now you are certain that one of the components is
ready to be initiated: a business case and a project charter have been developed for the
component, and a project manager is assigned. A steering committee meeting is planned for the
end of this week, and you prepare a presentation for the governance board about your desire to
start this component as soon as possible. During the governance board meeting, you state your
case. The steering committee disagrees with the component initiation. What did you OVERLOOK?
a- You did not assign a project manager for that component
b- This project does not have a charter nor a business case defined
c- There is no component sponsor assigned
d- The program governance plan does not show component initiation criteria
215
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ161
Projects A, B and C are components of program X. You have just been selected as the manager of
project A. Your project has not started yet, waiting for the 'go' decision from the board. A steering
committee meeting is called today, and the decision to start project A is among the topics to be
discussed. Program manager X comes back from the meeting and tells you that, unfortunately, the
steering committee will not allow project A to start now. From the list of reasons, which one is the
MOST critical for the steering committee to refuse to start project A?
a- The business case for project A does not exist
b- Project A manager has not been selected yet
c- The total number of resources is not present on the project
d- Project A does not have a sponsor
216
©Jean Gouix and Martial Bellec. not for distribution, sale or reproduction
Practice Question PQ163
You manage a program which is in the definition phase, and you are developing the benefits
management plan which describes when and how planned benefits will occur. From the list of
planned benefits, you know that some of the identified benefits may not occur before the program
ends. In addition, based upon the characteristics of some of the benefits, you are not sure what will
happen to them when the program is over. You have heard about sustainment plans, but you are
not sure what they are about. From this list of options below, which is a TRUE statement about
benefits?
a- The delivery of the benefits should be sustained after the program is over. The sustainment plan
should address this issue
b- All benefits must be realized before the program ends
c- The benefits management plan only addresses the benefits which are generated before the
closure of the program
d- There is no sustainment plan in program management. This is not a program management
terminology
217
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ166
You are the sponsor of a major international program in company XYZ. This program is composed of
five projects, and it has a huge number of stakeholders spread all over the world. The execution of
the program is well underway and the steering committee has planned to meet soon for the
monthly checkpoint of the program. In order to provide a clear status of the program, the program
manager has prepared a set of slides. In his presentation, he states that three component projects
can be closed as their planned deliverables have been completed. Based on the presentation, the
steering committee agrees with the closure of the three projects. Before accepting to close the
projects, the steering committee should have asked WHICH question to the program manager?
a- What was the estimated cost at completion (EAC) for each project?
b- What is the status of the two remaining projects?
c- What is planned for the reassignment of resources from each closing project?
d- Do the three projects satisfactorily meet the criteria as stated in the benefits management plan of
the program?
218
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ169
You have been nominated as program manager for a program composed of three component
projects: A, B and C. You are in the definition phase of the program and you are in the process of
identifying the core team members of the program. You have a list of key roles you want to fill in the
program core team, and you start interviewing candidates. Now you have successfully identified
people and you want to document the link between the roles and identified candidates, as they
are coming into the core team. What DOCUMENT are you trying to build?
a- The RAM or responsibility assignment matrix
b- The OBS or organizational breakdown structure
c- The accountability matrix
d- The RBS or risk breakdown structure
219
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
170 Practice Questions - Answers
Please find below the answers to the practice test.
At the end of the formal PgMP® exam, PMI will provide you a qualitative assessment of your
performance, per domain:
Proficient - indicates performance is above the average level of knowledge in this domain
Moderately Proficient - indicates performance that is at the average level of knowledge in this
domain
Below Proficient - indicates performance is below the average level of knowledge in this domain
Because there is no tangible threshold for this assessment, our recommendation is to take this
practice test until you achieve a result of 80%.
220
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ4
a- No! First discuss with the program sponsor, b- No! You will definitely need to discuss with the
Customer, but you should first discuss with the sponsor, c- No! You lack information about the
program, not about technical elements! d- Yes! You should first meet the sponsor who is usually an
executive representing the company. They should provide you with the proper program
background, and this should help you to then meet with the other entities. All other answers refer to
meetings that can occur later.
PgMP® Examination Content Outline 2011/ Stakeholder Management - Task 7
221
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ10
a- No! The strategic mandate (when it exists) comes before the charter, b- Correct! In the program
life cycle, Company executives often issue a strategic mandate, supported by a valid business
case. The program charter will be issued during program formulation, then the program
management plan will be developed, and finally customer sign off occurs at program closure c-
No! Customer sign off is last. d- No! Customer sign off is last.
PgMP® Examination Content Outline 2011 I Executing the Program - Knowledge Specific to Domain
2 (Phase gate reviews) and standard, section 6.1 (mandate) and sections 7.1.2.1 and 7.1.2.2 (charter
and program management plan), and section 7.2.2.5(customer sign off during program closeout)
222
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ15
a- Yes! Check that the delay on project X deliverables has an impact on project Y before anything
else, b- No! Maybe resources of project Z are not adequate for project X; in this case you have to
evaluate this first, c- No! You cannot go to the governance board before evaluating the impact
internally to the program; maybe there is no need to escalate. d- No! An administrative task cannot
be the first one to perform.
PgMP® Examination Content Outline 2011 / Planning the program - Task 15
223
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ21
a- Wrong! The sponsor is not responsible for developing the benefits management plan. It should be
done under the program manager’s responsibility. b- Correct! All planned program outcomes
should be achieved before the program ends, but some benefits may occur even when the program
is over. c- No! All planned benefits may not occur before the end of the program, d- No! This has
nothing to do with the benefits management plan. Processes and procedures used to manage the
program should be specified in the program management plan.
PgMP® Examination Content Outline 2011 / Benefits Management - Task 1 and standard, section
4.2.1
224
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ27
a- No! The program charter is issued later. The business case is an input to the creation of the
program charter. b- No! The program roadmap is created during the program definition phase
which is the first phase of the program life cycle. c- Correct answer! Benefits are first documented in
the program business case which is developed during the program definition phase. Please note
that the standard also mentions the 'program mandate' as another document which may contain
benefits identified prior to the definition phase. d- No! The benefits management plan is developed
after expected benefits have been identified and documented.
PgMP® Examination Content Outline 2011/ Strategic program Management - Task 6 and standard,
section 3.1
a- Correct! b- Wrong answer! ADEFG is 51 long and AHG is 40 long, c- Wrong answer! ADEFG is 51
long, d- Wrong answer! AHG is 40 long and ABCG is 53 long.
PgMP® Examination Content Outline 2011 / Planning the program - Task 9 and PMBOK® Guide,
section 6.5.2.2
225
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ31
a- Wrong answer! Plans should be revisited at each component initiation in order to evaluate the
potential impact on the program, b- Wrong answer! Plans should be revisited at each component
closure in order to evaluate the potential impact on the program, c- Wrong answer! Plans should
be revisited at the identification of a new major risk in order to evaluate the potential impact on the
program, d- Correct answer! The fact that the portfolio has been modified might NOT impact the
program. So, it may not be necessary to perform planning activities at the program level. 'Each time' is too strong
The standard, section 1.5 and the Standard for Portfolio Management - Fourth Edition, section 2.3.4
(Portfolio optimization)
Practice Question PQ32
a- No! If three key resources leave the program, plans should be updated to reflect the change.
b- No! If the program scope change request has been accepted, then plans must be updated.
c- Correct! If the change request has been rejected, there is no need to update the plans. d- No! If
new components are coming into the program, plans will need to be updated. The standard,
section 1.7.1
Practice Question PQ33
a- No! The Customer may request a major scope change, which may be accepted or rejected.
b- No! This is a fact. This might not result in a modification to the plans, only a need to catch up, if
possible! c- Correct! An accepted schedule change request means that the schedule has
changed. The program plans must be updated. d- No! This is a fact. This may not result in a
modification to the plans, only a need to be at the right quality standard, if possible!
The standard, section 1.7.1
Practice Question PQ34
a- No! You need to discuss with the project manager, but you also need to show your authority!
b- No! This does not solve any issue at all. c- Correct! You show your authority, d- No! However, the
sponsor may think that she is paying for everything, including informal discussions with members of
YOUR team.
PgMP® Examination Content Outline 2011/ Governance - Task 7
Practice Question PQ35
a- Correct! This is the exhaustive list of artifacts of the "Program Performance Monitoring and
Controlling" activities, b- No! This is not the good definition of artifacts relative to the “Program
Performance Monitoring and Control” activity, c- No! Stakeholder engagement reports are not an
artifact generated by the "Program Performance Monitoring and Control” activity, d- No!
Stakeholders’ feedback and status of team morale are not artifacts generated by the "Program
Performance Monitoring and Control” activity.
PgMP® Examination Content Outline 2011/ Executing the Program - Task 20 and standard, section
7.2.2.3
Practice Question PQ36
a- Wrong answer! b- Correct answer! The difference is only the time which is needed: 2 months less
this year. c- No! July 1st to July 30th is one month for this year. June 1st to August 31st was 3 months
last year. Schedule variance = 3-1 =2 months, d- Wrong answer! You do have enough information!
PgMP® Examination Content Outline 2011/ Controlling the Program - Task 25
226
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ37
a- No! You will spend 2/3 less this year, b- Correct. Total cost = 1000000, this is the value of cleaning
the town. Planned cost per month =cpm= 1000000/3, cost variance = 2*cpm = 666666. c- No! This
is the cost for one month, not the cost variance, d- No! You will only have to remove the waste
during one month this year, compared to 3 months last year. There is a cost variance!
PgMP® Examination Content Outline 2011 / Controlling the Program - Task 25
227
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ42
a- No! Come on, any stakeholder is important enough to be taken into account, and clever enough
to understand what you explained, b- No! Because the metrics should be applicable to all. c- Yes!
This is the correct answer because the metrics should be applicable to all. d- No! This stakeholder is
not dissatisfied by the level of benefits you are proposing, they just need metrics to sign off.
PgMP® Examination Content Outline 2011 I Benefits Management - Task 1
228
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ48
a- Wrong! There are other inputs such as component payment schedules, operational costs, etc.
b- Correct! This is the main purpose of the program financial framework. c- No! This is true but there is
a key element missing: 'How the money will be spent', d- No! This is true, but too restrictive.
The standard, section 8.1.2.4
a- Correct! The critical path is the longest (length = 53). b- No! This path length is only 51; it is not the
longest one. c- No! This path length is only 40; it is not the longest one. d- No! This path length is only
50; it is not the longest one.
PgMP® Examination Content Outline 2011 / Planning the program - Task 9 and PMBOK® Guide,
section 6.5.2.2
a- No! The path length is only 50. b- No! The path length is only 51. c- Correct! Activity C is on the
critical path ABCG (length = 53) d- No! AHG is the shortest path (length = 40) and is not the critical
path.
PgMP® Examination Content Outline 2011 / Planning the program - Task 9 and PMBOK® Guide,
section 6.5.2.2
229
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ51
a- Not Correct! The float on AHG is 13! b- Correct! c- Not Correct! The float on AHG is 13! d- Not
Correct! ABCG is 53.
PgMP® Examination Content Outline 2011 / Planning the program - Task 9 and PMBOK® Guide,
section 6.5.2.2
230
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ55
a- No! This is strategy, and detailed budget evaluation is premature, b- No! The amount of time you
spent with them is not a valid reason; you may have good interpersonal relationships with them while
being poor at capabilities assessment, c- Correct answer! The abilities of the functional teams
providing resources to the program have to be fully examined in order to determine whether they fit
or not. d- No! The program has little human resources interaction at that stage.
PgMP® Examination Content Outline 2011/ Strategic program Management - Task 5
231
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ62
a- Correct answer! At the end of the program definition phase, component projects are not yet
initiated (started). All other answers provide valid phase-exit criteria, b- No! This is a requirement to
exit this gate, c- No! This is a valid exit criterion at any gate. d- No! This is a valid exit criterion at any
gate.
PgMP® Examination Content Outline 2011/ Governance - Task 3 and standard, section 7.1.1
232
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ67
a- No! Program organization in not an enterprise environmental factor (factor OUTSIDE the program).
b- No! PMO is not an enterprise environmental factor. The PMO is a management structure.
c- Correct! This is a partial list of the enterprise environmental factors. d- No! Program and
component managers are not enterprise environmental factors.
The standard, section 3.4.1
233
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ73
a- No! Gate reviews do much more: they also review strategic alignment, risk level benefits, etc.
only at program gates. b- No! An external audit is not the core method for assessing health; it is
more a complementary one. c- Wrong! Health checks are not scheduled in the program roadmap.
d- Correct! Periodic health checks represent the best way to assess program health in a sustained
way. Health checks are generally held between phase-gate reviews and the governance plan
should specify the metrics used during health checks.
PgMP® Examination Content Outline 2011/ Governance - Task 11 and standard, section 6.1.10
234
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ79
a- No! The PMO may not have the necessary skills to develop adequate training courses, b- No! The
PMO should first conduct an assessment of the situation, c- No! This cannot be the option until the
need is clearly stated, d- Yes! This is the best option. And then, according to the findings, you take
action.
PgMP® Examination Content Outline 2011/ Executing the Program - Task 19
235
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ85
a- No! The change request is rejected therefore no program architecture change and no interface
change. b- No! The change request has no effect on other components. No interface change.
c- No! This should not impact component interfaces. At least, this is not the BEST option, d- Yes! For
sure, this needs to be communicated to stakeholders as it impacts component interfaces.
PgMP® Examination Content Outline 2011/ Stakeholder Management - Task 5 and standard, section
4.2.2 and section 6.1.8
236
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ91
a- No! Ideal but this is time consuming and expensive, time is running on, and this list of 5 may be
incomplete; you have to make sure that this list is complete first, b- Correct! c- No! You should not
pass this problem to your program team; you need to solve the problem on your own. d- No! Never
ignore a concern coming from a board member!
PgMP® Examination Content Outline 2011 / Stakeholder Management - Task 2
237
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ97
a- Wrong answer! Program EV = 480. b- Wrong answer! Program EV = 480. c- Correct! For project
A, CPI (EV/AC) = 0.8 and AC = 100. So for project A, EV = 80. For project B, EV = 200. For project C,
cost variance (CV = EV-AC) is 50, and AC = 150. So for project C, EV = 200. For the program, EV =
sum of the components’ EVs = 80 + 200 + 200 = 480. d- Wrong answer! Program EV = 480.
PgMP® Examination Content Outline 2011 I Controlling the Program - Task 25 and PMBOK® Guide,
section 7.4.2.2
238
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ103
a- No! This puts you in a weak position; senior executives might not be very supportive, b- No! It is
not within the scope of your program to reconsider local business plans. c- No! Could be correct
but not all stakeholders will be engaged in the decisions that will be taken. d- Correct answer! You
also gain credibility from positive stakeholders if you explain other difficulties. Another advantage is
that they can moderate the expectations of the negative stakeholders and help you to minimize the
effort required to obtain a consensus.
PgMP® Examination Content Outline 2011 / Benefits Management - Tasks 3 and 8
239
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ109
a- No! You definitely need a PMIS at program level. The projects' PMIS may be outstanding, but
because the program needs to access data other than that of the projects, you cannot use their
PMIS 'as it is'! The program PMIS may use the projects' PMIS as a base, but also with additions.
b- Correct answer! The program manager uses financial tools, processes, etc. other than the project
managers' ones. There must be a PMIS dedicated to the program which may be based on the
projects' PMIS, but with additions relative to the program. c- No! The PMO is not the only body to
use the PMIS at program level; you, the program manager, will also use it. d- Wrong! The sponsor
provides the resources, but they are not responsible for establishing a PMIS at program level.
PgMP® Examination Content Outline 2011 / Governance - Tasks 5 & 8 and standard, section 7.2.2.1
240
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ114
a- Wrong! ... to the BUDGET BASELINE. b- Wrong! ... to ensure that funds ARE DISBURSED IN
ACCORDANCE WITH THE CONTRACTS, c- Yes! This is the best answer because it is the only one
which is fully compliant with the standard’s wording. d- Wrong! ... the program INFRASTRUCTURE.
PgMP® Examination Content Outline 2011 / Controlling the Program - Task 28 and standard, section
8.2.3
241
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ118
a- No! This is not PMI® terminology, b- Correct! This type of schedule network diagram is also
sometimes called a 'precedence diagram'. c- No! The critical path can be identified on any
schedule network diagram, but in this diagram, there is no indication of float, early start or early finish
dates for the activities. d- No! In this diagram, there is no indication of milestones; only activity
durations and activity relationships are identified.
PgMP® Examination Content Outline 2011 / Planning the program - Task 9 and PMBOK® Guide,
section 6.5.2.2
242
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ122
a- No! The strategic plan should not contain an inventory of all existing components. This is not
related to strategy! b- No! The strategic plan should not contain a description of funding sources
and funding constraints. This is too restrictive, and non strategic! c- No! The strategic plan should not
contain a description of funding constraints. This is too restrictive, and non strategic! d- Correct
answer! This is a correct description of a strategic plan’s content.
PgMP® Examination Content Outline 2011 I Strategic program Management - Task 1 and The
Standard for Portfolio Management - Fourth Edition, section 4.1.3.1
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ128
a- Wrong! Project C’s resources are critical for the success of the project! b- Correct answer! You
should first apply leveling techniques on the resources of projects A and B. c- Wrong! Dispatching' is
not a correct term, d- Wrong! The Monte Carlo technique has nothing to do with this situation.
PgMP® Examination Content Outline 2011/ Planning the program - Task 10
244
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ133
a- Correct! This information should not be provided during the board meeting, but it is essential to
have it internally. You have to manage how you release internal resources. b- No! Governance
means politics, but this cannot be solved during a closure meeting, c- No! An internal board
meeting could be a preparation meeting with participants from your organization only. Plausible,
but then the sponsor should have already stated this. d- No! This is more related to external
considerations.
PgMP® Examination Content Outline 2011 I Closing the program - Task 33
245
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ139
a- Correct! The text refers to a description of the scope statement, b- Wrong answer! The program
scope management plan describes HOW the program scope will be managed. c- Wrong answer!
The PWBS depicts the total work to be accomplished in the program, d- Wrong answer! The
program stakeholder engagement plan describes HOW stakeholders will be engaged.
PgMP® Examination Content Outline 2011 / Initiating the program - Task 2 and standard, section
8.1.2.12
246
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ144
a- No! Bar charts do not show estimate vs. planned, b- No! Pie charts do not show estimate vs.
planned. c- Correct! Earned value management (EVM) is recommended to show what the estimate
at completion (EAC) is vs. the planned budget at completion (BAC). d- No! Earned value is the
recommended tool but highlighting CPI (Cost Performance Index) vs. SPI (Schedule Performance
Index) will not help in this situation!
PgMP® Examination Content Outline 2011 / Executing the Program - Task 22 and standard, section
8.2.3 (implementing earned value management) and PMBOK® Guide, section 7.4.2.2 (earned value
formulas)
247
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ150
a- No! Cost minimization can be a good reason tor initiating a program, b- No! HR management
can be a good reason for initiating a program, c- Correct! The other answers are plausible reasons,
but this answer is better because it only concerns one or several projects. For instance, compliance
to global quality standards may only concern the design project. The need to have a "global"
quality standard does not mean that it applies to all projects but to all drills; do not mix program
management and quality management, d- No! High technical risks can be a good reason for
initiating a program.
The standard, section 1.3
248
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ156
a- No! Technical expertise is not always necessary, and scheduling management tools skills are
usually not necessary! b- No! Procurement skills and data bases skills are usually not mandatory, c-
No! Technical expertise is not always necessary, and project management skills are recommended!
d- Yes! This is an exact list out of the standard.
The standard, section 1.7.1
249
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ161
a- Correct! From the list this is the only element which could prevent project A from starting.
A business case is needed for each component project in a program. b- Wrong! You have been
selected as the project manager! c- Wrong! Or at least not the best answer. The fact that all
resources are not present should not delay the start of the project. d- Wrong answer! Remember,
most of the time, the program manager acts as the sponsor for component projects.
PgMP® Examination Content Outline 2011 / Executing the Program - Task 16 and standard, section
6.1.11 and section 7.1.3.1
250
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Practice Question PQ166
a- No! The EAC of each project has little to do with the closure decision, b- No! The status of the
two remaining projects has no impact on the decision whether to close or not the three projects.
c- No! This question is not appropriate for the decision to close the three projects. This should have
been addressed in the various project plans, d- Yes! This is the key question to ask before agreeing
or not to close the three projects. The deliverables may have been produced, but according to the
criteria defined in the benefits management plan, are we certain that expected benefits have been
(or will be) realized as per the defined criteria?
PgMP® Examination Content Outline 2011 I Benefits Management - Task 5 and standard, section
6.1.9 (second bullet, outcomes of program components) and section 4.2.1 (benefits management
plan)
251
© Jean Gouix and Martial Bellec, not for distribution, sale or reproduction
Acheve d’imprimer par:
www.imprimersonlivre.com
Roudenn Grafik
22190 Plerin