Professional Documents
Culture Documents
Ground Investigation Assignment - Luke Kinsella - KIN20004553
Ground Investigation Assignment - Luke Kinsella - KIN20004553
Ground Investigation Assignment - Luke Kinsella - KIN20004553
1
Luke Kinsella KIN20004553
TABLE OF CONTENTS
1.0 Scenario……………………………………………………………...……….…..…..Pg 03
2.0 Introduction………………….………………………………………...…..…….……Pg 04
5.0 Risks………………………………………………………………………..…...……Pg 16
5.1 Risk of Potential Ground Types…………………………………..…….……Pg 17
5.2 Design & Construction Consequences……………...…………..……………Pg 18
7.0 References……………………………………………….…...……………….………Pg 21
2
Luke Kinsella KIN20004553
1.0 SCENARIO
A major new road scheme is being proposed. A preliminary study has revealed that there are
pockets of clay and peat as well as firm rocky ground along the route. You are a highway
consultant instructed by a local authority to advise on which tests are needed for the likely
ground conditions associated with this scheme. You are aware that the value of soils testing is
not always fully appreciated by decision makers looking to cut costs. You will need to point out
the risks of failing to identify any ground problems before contracts are let and the works start
on site.
Explain the most likely soil types that you expect to encounter and the most appropriate soils
analysis tests that would be used for these.
Examine the use of these tests and the cost implications of these.
Evaluate the risks associated with each of the ground types that you expect to encounter and the
possible consequences for the design and construction of the road
3
Luke Kinsella KIN20004553
2.0 INTRODUCTION
This report was produced following preliminary soil investigation tests carried out on the
proposed route of a major new road scheme. The route was identified prior to this report and the
potential ground conditions will be the focus of the discussion and recommendations outlined for
further investigation.
The recommendations made in this report are limited to the available information and records
reviewed at the time of study.
4
Luke Kinsella KIN20004553
The primary objectives of site investigation and this report are as follows:
• To assess the suitability of the site and environs for the proposed works including
implications of previous use or contamination.
• To enable an adequate and economic design to be prepared, including the design of
temporary works.
• To plan the best method of construction; to foresee and provide against difficulties and
delays that may arise during construction due to ground and other local conditions.
• To determine changes that may arise in the ground and environmental conditions, either
naturally or as a result of the works, and the effect of such changes on the works, on
adjacent works, and on the environment in general.
• Where alternatives exist, to advise on the relative suitability of different sites, or different
parts of the same site.
The size and type of project will influence the scope of the investigation; however, all projects,
irrespective of size, should have some form of site investigation. Due to the nature of our project
and the preliminary findings available previous to this report, a detailed site investigation should
be considered.
As stated above; a previous study has revealed pockets of clay and peat as well as firm rocky
ground along the route. These preliminary findings span across all three basic soil types:
• Coarse soils: sands, gravels, cobbles, and boulders (firm rocky ground).
5
Luke Kinsella KIN20004553
From these initial findings we can assume the following soil properties along our proposed route:
• Clay:
o Possibly glacial till also known as boulder clay.
o Typically, boulders are very occasional. Few clay minerals, mainly rock flour of
silt size particles.
o Can be dense, weight density up to 2.47Mg/m3 for very stiff/hard lodgment tills.
o Dense lodgment tills can be very stiff, particularly at low strain, compared with
clay.
o Relatively high angle of friction for a ‘clay’, = 350.
o Little degradation in effective stress strength parameters at large strain (residual).
o Can behave as a fine cohesive or coarse cohesionless soil depending on its fine
contents.
o Low plasticity index can be difficult to work in wet weather, particularly with low
fines.
• Peat:
o Natural mixture of graded granular soil, clay, and organic matter formed at the
earths surface after years of decomposition of organic remains.
o Highly compressible material.
o Very limited ability to carry loads. Structures located in areas of peat need to be
supported on piled foundations taken to a suitable strong stratum below.
o Possible to build over peat if it is consolidated and drained for a considerable
period prior to construction.
All soil properties detailed above are typical parameters associated with each potential soil type.
Confirmation will be required via additional investigation and sampling.
The exact location of these pockets is also unknown – further investigation is required in order to
identify problem areas and mitigate risk.
6
Luke Kinsella KIN20004553
Figure 4.1, Figure 4.2, and Figure 4.3 below detail required depths for various situations. Our
proposed road scheme will span over a variety of geographical conditions and will require
differing characteristics to suit.
• To account for deviations in road vertical road alignments and mitigate the risk of
flooding; embankments and cuttings will be constructed. Testing in areas below the
proposed location of such features will need to adhere to recommendations detailed in
Figure 4.1.
• Linear structures such as road sections should adhere to the recommendations detailed in
Figure 4.2.
• Piling may also be required in areas of poor ground. Testing below areas subject to
piling will need to adhere to the recommendations detailed in Figure 4.3 below.
7
Luke Kinsella KIN20004553
8
Luke Kinsella KIN20004553
The investigation points are assumed to be boreholes or CPTs. CPTs are almost exclusively used
on infrastructure projects in the UK as the mobilisation cost of the rig is often deemed
prohibitive for building projects (P. Quigley, 2015).
As referenced above in Table 4.4; recommended spacing can range from 20 to 200m. Due to the
presence of problematic conditions already identified in a previous investigation, testing should
be carried out in a more conservative spacing – reasoning for this will be discussed later in the
report.
Appropriate field tests should be selected, considering the information and parameters that are
required for the geotechnical design.
BS 5930:2015 Section 7, details descriptions and appropriateness of testing methods – this is
expressed below in Table 4.5.
Although the new road may be proposed through untouched green field sites; utilities should be
identified before any intrusive work commences.
Table 4.5: The applicability and usefulness of in-situ tests (BS5930/EN 1997)
9
Luke Kinsella KIN20004553
Upon review of Table 4.5 above; the following techniques have been deemed appropriate along
the proposed road route. This is primarily based on the soil conditions received from a previous
site investigation and the applicability and usefulness of each in-situ test.
• Dynamic Probing:
o A sectional rod with a cone fitted at the base of a slightly greater diameter
than the rod. It is driven into the ground by a constant mass that is allowed to
fall on the rod.
o Interpolation of data between boreholes using site specific correlations with
known ground property data might be possible.
10
Luke Kinsella KIN20004553
The sampling categories and the number of samples to be taken shall be based on:
• the aim of the ground investigation.
• the geology of the site.
• the complexity of the geotechnical structure.
For identification and classification of the ground, at least one borehole or trial pit with sampling
shall be available. Samples shall be obtained from every separate ground layer influencing the
behaviour of the structure.
Table 4.6 below details test classifications for differing soil types.
Table 4.7 below details the geotechnical parameters that can be determined for each soil type via
the use of designated testing types.
Table 4.8 specifies the minimum number of samples to be tested in one soil stratum.
Table 4.9, Table 4.10, and Table 4.11 details the minimum number of samples to be tested in one
soil stratum for triaxial compression, direct shear, and incremental oedometer testing. These
testing methods are recommended following the results of the previous ground investigation
study and correlating these with recommendation from EN 1997.
11
Luke Kinsella KIN20004553
Table 4.8: Suggested minimum number of samples to be tested in one soil stratum (EN 1997 -2).
Table 4.9: Triaxial compression tests. Recommended minimum number of tests for one soil
stratum (EN 1997-2).
12
Luke Kinsella KIN20004553
Table 4.10: Direct shear tests. Recommended minimum number of tests for one soil stratum (EN
1997-2).
Table 4.11: Incremental oedometer test. Recommended minimum number of tests for one soil
stratum (EN 1997-2).
13
Luke Kinsella KIN20004553
drains away from the soil’s voids and the pressure is transferred to the soil
skeleton which is gradually compressed, resulting in settlements. The
consolidation procedure lasts until the excess pore water pressure is
dissipated.
o The increment of applied stress that causes consolidation may be due to either
natural loads (e.g. sedimentation processes), or human-made loads (e.g. the
construction of a road or an embankment above a soil mass) or even the
decrease of the ground water table.
o The testing procedure to quantify the critical soil properties associated with
soil consolidation is the Oedometer Test and is one of the most commonly
conducted, and important, laboratory tests in geotechnical engineering.
o Test aims at measuring the vertical displacement of a cylindrical, saturated
soil sample subjected to a vertical load while it is radially constrained.
o It is possible to estimate the number of weeks or months that it will take for
settlement to be complete.
Many Stakeholders will worry about the cost when the time comes to tendering for a ground
investigation. A bid too high will be overlooked, whereas a bid too low means margins are
squeezed. As stated above; the biggest unknown for a project is in the ground.
The matter of risk must be considered, and the simple fact that a more in-depth investigation
means the lower the risk. This level of risk can have a direct impact on the success of a project.
The ground investigation doesn’t add any direct revenue for the project, but poorly designed
investigations are often the cause of things going wrong later (Tim Chapman, 2011).
As shown in Figure 4.4 below; data suggests that there is a trend to increase the spacing of
investigation points as the size of the project increases and a similar trend appears to be emerging
for construction cost (P. Quigley, 2015).
Figure 4.4: Comparison between construction cost & the no. of boreholes (P. Quigley, 2015).
14
Luke Kinsella KIN20004553
The overall cost off the proposed road scheme has not been disclosed; nevertheless, Figure 4.4
gives an indication of the frequency of testing compared to the overall construction cost. This
should be regarded as a minimum, and this report recommends taking the upper range suggested
by EC7. The benefits of a thorough site investigation cannot be understated. One of the main
reasons can be justified below in Figure 4.5. Charts outline the impact of site investigation
expenditure on highway contract over-runs due to ground conditions in the UK.
Figure 4.5 above is a clear indicator that a higher frequency in SI, typically yields a lower
adjusted construction cost.
Further details are required about the construction project to access costs definitively.
15
Luke Kinsella KIN20004553
5.0 RISKS
Ground investigations are an essential part of the design process to evaluate risk and deliver
successful outcomes. A successful outcome can be achieved by design or, less reliably, a series
of coinciding fortuitous events.
Figure 5.1: Cost of Risk/Effort v Increasing Effort of SI (Ash & Russel, 1974)
Insufficient information about the ground conditions can result in significant problems. About 80
to 85% of all European building failures and damages relate to problems in the ground (Brandl,
2004). The impact of these delays can be very significant. The cost of remedial measures
including maintaining and committing extra resources to complete the project, loss in revenue,
and professional fees for legal and engineering experts required to resolve disputes typically
dwarf the ground investigation costs. As ground related risk is so significant it would seem
reasonable that better ground investigation and design should reduce this risk (P. Quigley, 2015).
The ability to mitigate risk is greatest at the start of a project and decreases rapidly as the project
progresses. Figure 5.2 below details many possible effects of unforeseen ground conditions on
construction.
16
Luke Kinsella KIN20004553
Considering the information available from the previous investigation, pockets of peat create the
greatest risk. The main issue relating to primary consolidation and secondary compression.
Figure 5.3 below details secondary compression with time.
• Primary consolidation
o Settlements arising from dissipation of excess pore pressures
• Secondary compression
o Settlement due to volumetric strains
Figure 5.4 below shows peat being in the ‘extremely high’ classification when it comes to
seconday compression, and clay types being in the ‘very high’ to ‘high’ classification.
Considering initial results found pockets of both; seconday compression is highly likely.
17
Luke Kinsella KIN20004553
As referenced above in Figure 5.5, compression can take a significant amount of time.
Considering our proposed route is constructed over areas subject to secondary compression, this
will lead to increased maintenance and remedial costs.
The main issue with rehabilitation of roads over peat is that the situation is ever changing. The
foundation is poor and prone to further settlement, and maintenance over time will typically built
up a significant volume of material under the road surface. Excavation at the extremities of the
road, even drainage, can also cause stability issues.
The main consequence of constructing a road over poor ground is with respect to temporary
works. Many of the techniques needed to successfully complete a road scheme will require
temporary works to facilitate the construction. The proposed new road will no doubt require
features such as retaining walls, reinforced soil walls and slopes, gabion and crib walls.
The temporary works are required to aid the construction of such items.
Temporary works need to receive the same attention in design. Temporary works can also be
significant and more difficult to design than the permanent works. Because of this, they can also
add significant cost to the project and create a risk of delay.
18
Luke Kinsella KIN20004553
The advantages and disadvantages of any temporary works solutions are, in many cases, the
same as the permanent solution. To truly access the construction consequences; additional site
investigation is required about the geographical and geological characteristics along the proposed
route.
19
Luke Kinsella KIN20004553
If appropriate risk management techniques are adopted, then the geological hazards can be
greatly reduced.
The industry has also innovated considerably to suit problematic ground conditions such as the
ones identified on our proposed route, developing improved use of geophysics, a greater
understanding of sampling disturbance in soft soils and high-quality drilling methods and coring
in stiff glacial till. The more sophisticated techniques and the appointment of geotechnical
specialists carry a price premium but better ground investigation results in better design which in
turn leads to greater cost certainty.
Along with the site investigation measures detailed above; it is recommended that a detailed desk
study be undertaken to also mitigate risk and identify any unforeseen issues. This desk study
should explore available geographical data to identify features such as historical mining sites,
ancient burial grounds, areas of archaeological and religious interest, and hidden caves, rivers,
etc. Historical geology maps can also be obtained showing varying areas of bedrock and soil
strata.
All information should be compiled to form a better understanding of the area and reduce any
risk due to unforeseen circumstances below ground.
The possibility of re-alignment of the road should be considered to deviate from any areas of
poor ground.
20
Luke Kinsella KIN20004553
7.0 REFERENCES
Brandl, H. 2004. The Civil and Geotechnical Engineer in Society: Ethical and Philosophical
Thoughts, Challenges and Recommendations, The Deep Foundations Institute, Hawthorne, New
Jersey, USA.
Davitt, S 1996. Maintenance Techniques for Bog Roads, National Roads Authority, Galway,
Ireland.
IEI, 2003. Project cost and estimation and control, an Institution of Engineers of Ireland
submission to the Minister for the Environment and Local Government.
IS EN 1997-1 2005. Eurocode 7 - Geotechnical design – Part 1 General rules, NSAI.
IS EN 1997-2 2007. Eurocode 7 – Geotechnical Investigation and Testing, NSAI.
Quigley, P, 2015. Some trends from recent ground investigation contracts in Ireland, ICE
Publishing.
21