SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.

00 30-Jun-16

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Storm Water Drainage Systems Installation SAIC-S-4060 15-Nov-17 PLUMB


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Following are the acceptable materials for drainage piping:


a) The materials listed in Section 6.1 of SAES -S-010 are acceptable for storm drainage piping.

b) Reinforced concrete pipe, ASTM SAES-S-030


A1 C76M Class III, Wall B, for pipes 300 mm and larger. Joints shall be sealed using elastomeric "O"
rings according to ASTM C443 unless otherwise noted in project specification. Para 5.1.1
c) Concrete pipe 250 mm
and smaller shall be in accordance with ASTM C14 Class III non-reinforced, bell and spigot, or
tongue and groove sewer pipe.

All storm drain systems shall be identified on plant drawings in


SAES-S-030
A2 accordance with SAES-A-100. Locations (coordinates) and elevations
Para 4.8
shall be shown in the drawings.

The minimum diameter of a storm drain pipe (except building connections) SAES-S-030
A3
or road crossing culvert shall be 300 mm. Para 4.6.6
SAES-S-030
A4 Branch lines to individual drain inlets shall not be smaller than 200 mm.
Para 4.6.6
The ends of road crossing culverts and the exit of storm drains at an open SAES-S-030
A5
channel shall have concrete headwalls. Para 4.6.7

The headwalls, as well as the ends of concrete box culverts, shall have a
SAES-S-030
A6 cut-off wall at the entrance or exit lip of not less than 0.6 m below the
Para 4.6.7
channel invert

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.00 30-Jun-16

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Storm Water Drainage Systems Installation SAIC-S-4060 15-Nov-17 PLUMB


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

SAES-S-030
A7 The maximum spacing between drainage inlets should not exceed 90 m.
Para 4.6.8

Manholes are required at changes of horizontal or vertical direction of SAES-S-030


A8
storm drain pipes. Para 4.6.9.a

Maximum Spacing of manholes shall be 60m for sewers less than or


SAES-S-030
A9 equal to 300 mm in diameter and 150m for sewers larger than 300 mm in
Para 4.6.9.b
diameter

Storm drain manholes shall have a minimum inside diameter of 1.2 m for SAES-S-030
A10
straight run manholes with a pipe diameter size of 600 mm or less Para 4.6.10.1

Storm drain manholes shall have a minimum inside diameter of 1.8 m for SAES-S-030
A11
straight run manholes with a pipe diameter size larger than 600 mm. Para 4.6.10.2

Storm drain manholes shall have a minimum inside diameter of 1.8 m for SAES-S-030
A12
junction manholes. Para 4.6.10.3

Rip-rap shall be solid stone or concrete measuring at least 300 mm in all SAES-S-030
A13
dimensions as per Standard Drawing AE-036470. Para 5.1.3

Rip-rap shall be hand laid to provide a tight fit between the individual SAES-S-030
A14
pieces Para 5.2.3

The rip-rap shall be solid grouted for a distance of not less than 3 m
upstream and downstream of concrete box culverts and along the outside SAES-S-030
A15
face of all curves plus 3 m upstream and downstream of the curve tangent Para 5.2.3
points.

REMARKS:

REFERENCE DOCUMENTS:
SAES-S-030 -- Storm Water Drainage Systems, 2 Sept. 2014
Standard Drawing AE-036470

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED