GT#8 Generator rotor disassembly :

No. of
Activity Starting day Finished day
days
prepare all special tools and clean it if
1 1 24/1/2018 24/1/2018
necessary .
2 remove the outside wall. 3 24/1/2018 28/1/2018
remove all protection and
3 1 29/1/2018 29/1/2018
measurement devices by C/I people.
remove the roof and the metallic walls
4 1 29/1/2018 29/1/2018
(three) for the carbon brush room .
remove all piping from both side and
5 1 29/1/2018 29/1/2018
carbon brush assembly.
6 remove all covers shield for both side. 2 29/1/2018 30/1/2018
7 install protective shim under rotor. 1 31/1/2018 31/1/2018
slide the rotor shoe on protective shim
8 1 31/1/2018 31/1/2018
and put it in the suitable position.
fix the pulling device and lifting ring
9 1 31/1/2018 31/1/2018
in its place.
10 remove the bearing #4. 1 1/2/2018 1/2/2018
start to pulling the rotor for 1.5 meter
11 and stop the pulling in order to fix 1 4/2/2018 4/2/2018
bearing shoe.
restart to pulling the rotor by the
12 1 4/2/2018 4/2/2018
known method.
Upload the rotor for shipment to
13 1 5/2/2018 5/2/2018
GEMTECH.